Pay app guides · schedule of values calculator

Pay applications for commercial flooring and tile: floor prep, stored material and attic stock

Commercial flooring and tile pay applications bill finishes laid near the end of a job, on slabs other trades have used for months. The money is often lost before the first box is opened: moisture testing, slab prep that was not in the price, and material delivered weeks before the floor is ready. This page covers each, with the free guide or tool for it.

What makes flooring billing different

SituationWhat the GC usually wantsHow to bill itFree guide or tool
Several floors and materialsPercent complete per floor or area and per materialSplit the SOV by floor and by material (carpet tile, resilient, ceramic and porcelain tile, base), so the percent can be checked on the floorFree Excel SOV template
Slab moisture testing and mitigationA change order before the work, unless the subcontract already prices itRecord the test results, ask in writing who pays for mitigation, and price it before you apply itChange orders and the SOV
Floor prep: leveling, patching, grindingThe flatness you were promised and a signed ticket for prep beyond itMeasure the slab before you start, write a ticket for prep beyond your scope and get it signedFF/FL floor flatness calculator
Material delivered before the floor is readyStored materials with invoices and photos, if the subcontract allows itBill it as stored and move it to work completed as it is installed, so it is billed onceBilling stored materials
Finished floors damaged by other tradesA signed ticket naming who caused it before the repairPhotograph it, write a T&M ticket and get it signed before replacing tiles or planksT&M ticket log
Attic stock, cleaning and punchSpare material handed over and items accepted before final retainageKeep the punch list and a signed hand-over of attic stock with the close-out documentsPunch list tracker

An example flooring schedule of values

An example with made-up lines, to show the shape; your subcontract sets the lines. Some flooring subcontracts are priced per square yard or square foot; then each line carries a unit and a quantity instead of a percent.

LineExample descriptionUnitHow it is billed
1Mobilization and submittalsLSOnce, or in the parts the subcontract allows
2Moisture testingLS or EAWhen tests are done and reported
3Floor prep and leveling, as scopedLS or SFPercent done, or square feet
4Carpet tile, floors 2 and 3LS or SYPercent installed, or square yards
5Luxury vinyl tile, corridorsLS or SFPercent installed, or square feet
6Porcelain tile, restroomsLS or SFPercent installed, or square feet
7Rubber baseLS or LFPercent installed, or linear feet
8Attic stock, cleaning and punchLSWhen handed over and accepted

Where flooring subs lose money on pay apps

Common questions

How should a flooring contractor set up the schedule of values?

By floor or area and by material (carpet, resilient, tile, base), with moisture testing, floor prep and attic stock on lines of their own. Each month's percent then comes from what is laid on each floor.

Who pays for slab moisture mitigation?

Whoever your subcontract and the specifications say. If it is not in your price, report the test results, ask for a change order before you apply anything and keep the results with it.

Can I bill for flooring delivered but not installed?

Often yes, as stored materials, if your subcontract allows it; attach invoices, delivery tickets and photos. Move it to work completed as it is installed, so it is billed once.

What is attic stock, and when is it billed?

Spare flooring the specifications ask you to leave with the owner for future repairs. Bill it when it is handed over, and get the hand-over signed: it is usually on the close-out list final retainage waits on.

Flooring pay apps that bill the prep as well as the floor

PayApps is hosted pay-app billing for specialty subcontractors. It takes unit-price lines by the square foot or square yard, carries stored materials per line from one application to the next so material is billed once, logs T&M tickets with photos for prep and repairs, and keeps the punch list and close-out checklist, attic stock included, that the last retainage waits on. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.