Illinois and Michigan, side by side
Read on 2026-11-25 through search results limited to the two legislatures' own sites, not from a full copy of each page. Michigan's site shows more than one version of the section and their wording differs slightly; read the linked text before you rely on a row.
| Question | Illinois, 770 ILCS 60/5 | Michigan, MCL 570.1110 |
|---|---|---|
| Who gives it, to whom | The contractor, to the owner. | The contractor, to the owner or lessee. A subcontractor, to the contractor, and to the owner if the owner demands one. |
| When | Before the owner pays or advances money to the contractor. | When payment is due or requested, or when the owner or lessee demands it. A subcontractor: when payment is due to it or it asks for payment. |
| What it lists | Names and addresses of everyone furnishing labor, services, material, fixtures, apparatus, machinery, forms or form work, and the amounts due or to become due to each. The amounts language came in with Public Act 103-0827, effective 1 January 2025. | Each subcontractor and supplier contracted with, and laborers with unpaid wages or fringe benefits, on a form with columns for name, address and phone, type of improvement furnished, total contract price, amount already paid, amount currently owing, balance to complete (optional), unpaid wages, and unpaid fringe benefits and withholdings. |
| Exceptions and notices | Merchants and dealers in materials only do not have to make one. On an owner-occupied single-family home the contractor gives the owner, before the first payment, a notice in at least 10-point bold type that the law requires a sworn statement. | On residential work the owner gives notice of receipt to claimants who have served notices of furnishing, and a copy to one who asks. |
| What the owner can do with it | Pay relying on it: the statement tells the owner whose claims to protect. An owner who pays after notice of claims without keeping back enough to cover them risks paying twice. | Withhold enough to pay the amounts shown (and must, on the contractor's written demand) and pay those parties directly. |
| If you skip it or get it wrong | The statute asks for it before the owner pays, so an owner can hold payment until it has one. A party named on an incorrect statement is still protected up to the amount listed for it. | The lien survives, but a contractor is not entitled to payment, and nobody can file to enforce the lien, until the statement is provided. A false statement made knowingly with intent to defraud is a crime. |
| Official text | ilga.gov, 770 ILCS 60/5 | legislature.mi.gov, MCL 570.1110 (the statutory form is in the section) |
Other states: no statute is claimed here. If a title company or lender sends you its own sworn statement or "contractor's affidavit" form, use theirs; the builder below gives you the figures to copy into it.
How the numbers fit together
- One row per party, plus one for your own forces (your own labor, overhead and profit). Without that row the statement cannot add up to your contract, and the first question back will be where the rest of the money goes.
- Contract with change orders = contract price + approved change orders. Leave pending changes out until they are signed (the change order log keeps them apart).
- Completed to date − retainage = paid + owing. What a party has earned, net of the retainage you hold from it, is either already paid or owed now.
- Balance to complete = contract with change orders − paid − owing. It includes the retainage still held, which is owed later.
- The totals tie out. All rows together equal your own contract sum, and the "owing" column together equals what this pay application asks for.
Build and check your sworn statement
Paste your list with a header row, as CSV or straight from a spreadsheet (tab separated). Columns it reads by name: name and contract price (required); address, phone, type of work, change orders, completed to date, retainage, amount paid, amount owing, unpaid wages and unpaid fringe benefits (optional). Michigan's and the common Illinois column titles both work. Your numbers stay in this browser tab.
| Party | Contract with COs | Completed | Retainage | Paid | Owing now | Balance to complete |
|---|
Lien waivers to collect with it
An owner or title company paying against a sworn statement usually wants a waiver from each party for what it has been paid, and a conditional one for what it is owed now. Which waiver when.
The example: an electrical sub with a $480,000 contract including a $12,000 change order. Its own forces, a supplier and a low-voltage sub add up to $480,000; $85,000 has been paid and $32,900 is owing this month, which is what the pay application asks for. This builds the table; it does not supply the statutory wording or the oath. Copy the figures onto the statutory form (Michigan) or the form your owner, lender or title company uses, and sign it before a notary.
Before you sign
- List everyone who could lien, even parties already paid in full: a missing name is what makes a statement false.
- Match your suppliers' statements. Pull "paid to date" from your books, not memory; a supplier who says you owe more will tell the owner.
- Send the waivers with it. The statement tells the owner who to expect waivers from; collect them before the GC asks.
- Each month, update it. The statement is as of a date. Last month's statement with this month's pay app is a common reason a draw is held.
Common questions
What is a contractor's sworn statement?
A list of everyone who furnished labor or materials to your part of a job, with what each was contracted for, has been paid and is owed now, signed under oath, usually before a notary, and sent with the pay application. Illinois (770 ILCS 60/5) and Michigan (MCL 570.1110) write it into their lien laws.
What happens without a sworn statement in Michigan?
The lien survives, but a contractor is not entitled to payment, and nobody can file to enforce the lien, until the statement is provided. A false statement made knowingly with intent to defraud is a crime.
Does a sworn statement have to add up to my contract?
Yes. All rows together, including one for your own forces, equal your contract sum, and the owing column together equals what this pay application asks for. For each party, completed to date less retainage equals paid plus owing.
Sworn statements that fill themselves in
PayApps is hosted pay-app billing for specialty subcontractors: subs, suppliers, change orders, payments and lien waivers kept per job, so each month's sworn statement and waiver list come from the same records as the pay application. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.