Pay app guides · schedule of values calculator

Pay applications for commercial painting contractors: floors, coats and damage by others

Commercial painting comes at the end of the job: the work is billed by floor or area and by coat, and much of the last month is touch-up after other trades and punch. That is where painting subs lose money: repainting damage they did not cause, and retainage that waits on a punch list that keeps growing. This page covers each, with the free guide or tool for it.

What makes painting billing different

SituationWhat the GC usually wantsHow to bill itFree guide or tool
Several floors or areasPercent complete per floor and per coat or phaseSplit the SOV by floor or area and by phase (prime, finish coats, wallcovering, special coatings), so the percent can be checked on a walkFree Excel SOV template
Repainting damage by other tradesA signed ticket or change order naming the damage, before it is repairedPhotograph the damage, write a T&M ticket and get it signed, and bill it once approvedT&M ticket log
Back charges from the GCA written back charge with its basisAsk for it in writing, compare it with your subcontract, and answer in writingPaid short? Reconcile the check
Wallcovering and special coatings ordered aheadStored materials with invoices, if the subcontract allows itBill them as stored and move them to work completed as they are hung or appliedBilling stored materials
Punch list and final retainageItems accepted before retainage is releasedKeep the punch list, mark items not yours, and send the back-check in writingPunch list tracker
Pricing the jobA bid that matches the SOV you will billPrice walls, ceilings and trim by area before you split the SOVPainting bid calculator

An example commercial painting schedule of values

An example with made-up lines, to show the shape; your subcontract sets the lines. Floors and phases on their own lines make each month's percent easy to check on a walk.

LineExample descriptionUnitHow it is billed
1MobilizationLSOnce, or in the parts the subcontract allows
2Level 1: primeLSPercent primed
3Level 1: finish coatsLSPercent finished
4Level 2: prime and finishLSPercent finished
5Doors and framesEA or LSEach finished, or percent
6WallcoveringLS or SYPercent hung, or square yards
7Exterior coatingsLSPercent applied
8Touch-up and punchLSWhen the punch list is accepted

Where painting subs lose money on pay apps

Common questions

How should a painting contractor set up the schedule of values?

By floor or area and by phase (prime, finish coats, wallcovering, special coatings, exterior), with touch-up and punch on a small line of its own. Each month's percent then comes from what is done on each floor.

How do I get paid for repainting damage caused by other trades?

Photograph the damage, write a T&M ticket or change order request naming it and get it signed by the GC's superintendent before the repair, then bill it once approved.

Can a painting contractor bill for wallcovering before it is hung?

Often yes, as stored materials, if your subcontract allows it; attach the invoices. Move it to work completed as it is hung, so it is billed once.

When is a painter's retainage released?

When your subcontract says, which is often after the GC is paid its own retainage and the punch list is accepted. Ask which items are open in writing, and mark any that are other trades' damage.

Painting pay apps that bill the extras

PayApps is hosted pay-app billing for specialty subcontractors. It logs T&M tickets with photos for damage by other trades and turns signed ones into change orders, keeps the punch list with items marked not yours, records back charges when a check comes in short, and shows the retainage waiting on close-out. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.