Conditional vs unconditional lien waivers

A lien waiver (waiver and release) is a document in which you give up your mechanics lien rights, and often your payment bond and stop-notice rights, for a payment. GCs, owners and lenders ask for one with every pay application. Signed at the right moment it is routine paperwork. Signed at the wrong moment it gives away your strongest collection tool for money you have not received.

The four kinds

Progress (a payment partway through)Final (the last payment)
ConditionalWaives rights for work through a date, only once the stated payment is received and clears. Sign it with the pay app.Waives all rights on the job, only once the final payment clears. Sign it with the final pay app.
UnconditionalWaives rights for work through a date, whether or not you were paid. Sign it only after the money is in your account.Waives all rights on the job, whether or not you were paid. Sign only once the final payment, retainage included, has cleared.

The one rule: never sign an unconditional waiver for money you have not received. A common, safe routine is: with this month's pay app, a conditional progress waiver for this month's amount and an unconditional progress waiver for last month's payment, which has now cleared.

Read the details before you sign

States that fix the wording by statute

Read on the state legislature's published statutes on 2026-11-24. A minority of states prescribe waiver forms; the rest leave the wording to the parties. Check your state's current text before relying on this.

Common questions

What is the difference between a conditional and an unconditional lien waiver?

A conditional waiver gives up your lien rights only once the stated payment is received and clears. An unconditional waiver gives them up whether or not you were paid, so sign one only after the money is in your account.

Which lien waivers do I send with a monthly pay app?

A common, safe routine is a conditional progress waiver for this month's amount and an unconditional progress waiver for last month's payment, which has now cleared.

What should a progress lien waiver exclude?

List what you are not waiving: retainage, disputed or unapproved change orders, extra work billed but unpaid, and earlier unpaid progress payments. The waiver should cover work through a stated date and a stated amount, not "all work to date".

Chasing waivers every month?

PayApps is hosted pay-app billing for specialty subcontractors that sends the right waiver with each pay app and tracks which payments have cleared before anything unconditional goes out. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.