The four kinds
| Progress (a payment partway through) | Final (the last payment) | |
|---|---|---|
| Conditional | Waives rights for work through a date, only once the stated payment is received and clears. Sign it with the pay app. | Waives all rights on the job, only once the final payment clears. Sign it with the final pay app. |
| Unconditional | Waives rights for work through a date, whether or not you were paid. Sign it only after the money is in your account. | Waives all rights on the job, whether or not you were paid. Sign only once the final payment, retainage included, has cleared. |
The one rule: never sign an unconditional waiver for money you have not received. A common, safe routine is: with this month's pay app, a conditional progress waiver for this month's amount and an unconditional progress waiver for last month's payment, which has now cleared.
Read the details before you sign
- Through date and amount: a progress waiver should cover work through a stated date and a stated amount, not "all work to date".
- Exceptions: list what you are not waiving: retainage, disputed or unapproved change orders, extra work billed but unpaid, and earlier unpaid progress payments. The statutory forms in California and Florida have this built in.
- Extra language: GC-drafted waivers sometimes add releases of all claims, indemnities or warranties. In states with statutory forms, that may not be enforceable or allowed; elsewhere it may be. Strike it or ask.
- Joint checks: if your supplier is paid by joint check, its waiver and yours should match the amounts (joint checks: split and waivers).
- Federal jobs: there is no lien on federal property, so the release in a waiver the GC asks for can limit your Miller Act payment bond claim instead. A waiver of the right to sue on the bond counts only if signed after you started work (Miller Act bond claims and deadlines).
- Your lien deadline still runs: a conditional waiver keeps your rights only while you can still use them. If a payment is late, the mechanics lien deadline calculator works out the last day to serve notice and record a lien in your state, and the lien waiver checker reads a waiver the GC sent you for what it releases.
States that fix the wording by statute
Read on the state legislature's published statutes on 2026-11-24. A minority of states prescribe waiver forms; the rest leave the wording to the parties. Check your state's current text before relying on this.
- California: four statutory forms in the Civil Code: conditional progress (§8132), unconditional progress (§8134), conditional final (§8136) and unconditional final (§8138). The progress forms carve out retentions and unpaid extras. The statute makes a waiver unenforceable unless it is substantially in the statutory form.
- Florida: §713.20 sets out progress and final waiver forms. Lien rights cannot be waived in advance; a person asking for a waiver cannot require a different form; and a lienor may condition a waiver on its check clearing.
- Other states also prescribe forms. Arizona, Nevada, Texas, Utah, Michigan and Wyoming are compared, from each legislature's own text, in statutory lien waiver forms by state. For any other state, look up the statute for the state where the project is.
Common questions
What is the difference between a conditional and an unconditional lien waiver?
A conditional waiver gives up your lien rights only once the stated payment is received and clears. An unconditional waiver gives them up whether or not you were paid, so sign one only after the money is in your account.
Which lien waivers do I send with a monthly pay app?
A common, safe routine is a conditional progress waiver for this month's amount and an unconditional progress waiver for last month's payment, which has now cleared.
What should a progress lien waiver exclude?
List what you are not waiving: retainage, disputed or unapproved change orders, extra work billed but unpaid, and earlier unpaid progress payments. The waiver should cover work through a stated date and a stated amount, not "all work to date".
Chasing waivers every month?
PayApps is hosted pay-app billing for specialty subcontractors that sends the right waiver with each pay app and tracks which payments have cleared before anything unconditional goes out. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.