What makes masonry billing different
| Situation | What the GC usually wants | How to bill it | Free guide or tool |
|---|---|---|---|
| Walls in several areas and materials | Percent complete per elevation or area and per material | Split the SOV by area or elevation and by material (CMU, brick, stone, cast stone), so the percent can be checked from the wall | Free Excel SOV template |
| Brick, block and stone delivered ahead of laying | Stored materials with invoices, delivery tickets and photos, if the subcontract allows it | Bill them as stored and move them to work completed as they are laid, so they are billed once | Billing stored materials |
| The mockup panel | Its own line, approved before the walls go up | Bill the mockup when it is built, on its own line, and keep the approval with the pay app | Change orders and the SOV |
| Cold-weather protection: enclosures, heat, blankets | A change order or signed ticket, unless the subcontract already prices it | Write a T&M ticket each day the protection is up, with the heaters, fuel, labor and material | T&M ticket log |
| Scaffolding and lifts | A line that is billed as it is used, not up front | Put it on its own line and bill it with the walls it serves, or by the month if the subcontract allows | Front-loading check |
| Cleaning, pointing and punch at the end | Items accepted before final retainage is released | Keep the punch list and close it with the GC in writing | Punch list tracker |
An example masonry schedule of values
An example with made-up lines, to show the shape; your subcontract sets the lines. Some masonry subcontracts are priced per square foot of wall or per unit; then each line carries a unit and a quantity instead of a percent.
| Line | Example description | Unit | How it is billed |
|---|---|---|---|
| 1 | Mobilization | LS | Once, or in the parts the subcontract allows |
| 2 | Mockup panel | LS | When built and approved |
| 3 | CMU walls, area A | LS or SF | Percent laid, or square feet of wall |
| 4 | Brick veneer, north and east elevations | LS or SF | Percent laid, or square feet of wall |
| 5 | Brick veneer, south and west elevations | LS or SF | Percent laid, or square feet of wall |
| 6 | Cast stone sills and coping | EA or LF | Pieces or linear feet set |
| 7 | Scaffolding | LS | As used, with the walls it serves |
| 8 | Cleaning and pointing | LS | When the walls are cleaned and accepted |
Where masonry subs lose money on pay apps
- Pallets on site, not on the bill. Units delivered and paid for weeks before they are laid are cash the sub has spent. If the subcontract allows stored materials, bill them.
- Cold-weather protection on a verbal OK. Heaters, enclosures and fuel that run every day of a cold spell add up. A ticket signed each day is the one that gets paid.
- A front-loaded scaffolding line. Scaffolding billed up front is a line a reviewer cuts. Front-loading check compares each line's markup with the job's.
- Final cleaning that never closes. Retainage that waits on cleaning and punch waits longer without a written list both sides have agreed.
Common questions
How should a masonry contractor set up the schedule of values?
By area or elevation and by material (CMU, brick, stone, cast stone), with the mockup, scaffolding and cleaning on their own lines. Each month's percent then comes from the walls that are up.
Can I bill for brick and block delivered but not laid?
Often yes, as stored materials, if your subcontract allows it; attach invoices, delivery tickets and photos. Move them to work completed as they are laid, so they are billed once.
Who pays for cold-weather masonry protection?
Whoever your subcontract says. If it is not in your price, ask for a change order before the protection goes up and keep a signed ticket for each day it is used.
Should the mockup be its own line on the pay application?
Yes, when the subcontract asks for one: it is real work that can be billed when built and approved, and a separate line keeps it from being argued into the wall price.
Masonry pay apps that bill what is on site
PayApps is hosted pay-app billing for specialty subcontractors. It tracks stored materials per line from one application to the next, so pallets are billed once, takes unit-price lines by the square foot or unit, logs T&M tickets for cold-weather protection, and keeps the punch list and close-out checklist the last retainage waits on. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.