What a ticket should show
A ticket the GC can dispute is a ticket you will discount. These are the fields reviewers look for; your subcontract may name more.
| Field | Why it matters |
|---|---|
| Ticket number and date of the work | One ticket per day per crew. A ticket that covers a week is hard to check against the GC's daily reports. |
| Where and why | Location, and what directed the work (an RFI answer, a field directive, an ASI, a named person). That is what ties the work to a change and not to your base scope. |
| Each worker or trade, with hours | Name or classification and hours, regular and overtime apart. Unnamed labor is the first line a GC strikes. |
| Material, with quantities | What was installed, how much, and the supplier invoice when it comes in. |
| Equipment, with hours or days | Owned or rented, and for how long; the rental ticket for rented equipment. |
| GC signature, printed name and date | Signed on the day. A signature confirms the time and material were spent; it usually does not agree the price or that it is extra, so the change order still matters. |
T&M ticket log
One row per line: labor, material, equipment, lower-tier sub or other. Rows with the same ticket number are one ticket. Columns: Ticket, Date, Type, Description, Qty, Rate, Signed by, CO (an Amount column works for lump-sum lines). Leave Signed by blank for an unsigned ticket, and fill CO once the ticket is on a change order. It runs in this browser tab; nothing is uploaded.
Markups from your subcontract
No markup is assumed: a blank is 0%. Use the overhead and profit percentages your subcontract allows on changes, by cost type; the example's figures are only an example.
Tickets
What to do
The change order request lines are the signed tickets not yet on a change order, as pending rows. Paste them into the change order log to see them with the rest of the job's changes.
Change order request
The request lists only figures computed above. It does not give notice of a claim, reserve rights or say what your contract entitles you to; if a change is disputed, read your subcontract's changes and claims clauses, and talk to a construction attorney before a deadline in them passes.
From ticket to pay application
- Get it signed on the day. A superintendent who signs tickets every afternoon remembers the work. One handed a stack at month end does not, and the stack gets cut.
- Price it at the subcontract's rates. Labor at your labor rates (burdened, if the subcontract allows), material at invoice cost, equipment at the agreed rates, then the markup the subcontract allows on each. If the work was directed as "T&M not to exceed", say on each ticket how much of the cap is used.
- Send a change order request. Group the signed tickets for one change and ask for a change order number. The log above flags any signed ticket that has waited longer than your chase window.
- Bill it when the change order is executed. An executed change order becomes a new line on the schedule of values (how change orders enter the SOV). Billing a ticket before then is a common reason pay apps get sent back (pay application checker).
- Keep the notice clock in view. Subcontracts usually set a deadline for written notice of extra work or a claim. A signed ticket may or may not count as that notice; your subcontract decides, not this page.
Common questions
Can I bill a T&M ticket on my pay application?
On most jobs, not until the ticket becomes an executed change order, which then becomes a new line on the schedule of values. Billing a ticket before then is a common reason pay apps get sent back.
What should a T&M ticket include?
The ticket number and date of the work, where and why it was done, each worker or trade with regular and overtime hours apart, material with quantities, equipment with hours or days, and the GC's signature, printed name and date, signed on the day.
Does a signed T&M ticket mean the GC agreed to pay?
Usually not. A signature confirms the time and material were spent; it usually does not agree the price or that the work is extra, so the change order still matters. Whether a ticket counts as written notice of extra work is for your subcontract to decide.
T&M tickets that turn into billed change orders
PayApps is hosted pay-app billing for specialty subcontractors that keeps each job's change orders, pay applications, retainage and lien waivers together, so a signed extra reaches the next pay app instead of a drawer. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.