What each punch item should record
A template is only these columns. Keep one row per item, numbered, so the GC and you are talking about the same thing.
| Column | Why it matters |
|---|---|
| Item number | Use the GC's numbers when the list came from them. "Item 14 is done" beats "the plate by the lobby". |
| Location | Room, gridline or floor, as the drawings name it, so the crew and the back-check find the same spot. |
| Description | What is wrong, in the words of whoever listed it. Rewording it invites "that is not what I wrote". |
| Listed by, listed and due dates | GC, architect, owner, inspector or your own walk, and when they need it. Without a due date, nothing is ever overdue and nothing is ever finished. |
| Fixed (date and who) | Your record that the work was done, and the date you asked for the back-check from. |
| Accepted (date and who) | The GC's initials or a name and date. This is what you show when retainage is held "for the punch list". |
| Not ours | The reason an item is another trade's work or built as drawn. Tell the GC in writing; it stays out of your count here, not off their list. |
The tracker below downloads exactly these columns as a CSV, with a blank GC initials column to print and walk with.
Punch list tracker
Paste a table with a header row (Item, Location, Description, Listed by, Listed, Due, Fixed, Fixed by, Accepted, Accepted by, Not ours; only Description is required), or paste the list straight from the GC's email, one item per line: numbering like 1. or P-004 is dropped and a location before " - ", ": " or a tab is split off. Dates as YYYY-MM-DD or MM/DD/YYYY. It runs in this browser tab; nothing is uploaded.
Items
What to do
Back-check request
The email lists the items you marked fixed and how many are still open. It does not say your subcontract's conditions for payment or retainage are met; those are in your subcontract.
Closing a punch list fast
- Walk your own scope first. A list you write before the GC's walk is shorter than the one they write, and it is yours to schedule.
- Get the list in writing, numbered, with due dates. Ask for it the day of the walk. Push back on items that are not yours that same week, in writing; once a list has been open a month, nobody remembers who caused the damaged tile.
- Fix in batches by area and record the date and who fixed each item as you go.
- Ask for one back-check per batch. One email naming every fixed item (the tracker writes it) gets them walked together, instead of a call per item.
- Get each item initialled. A signed or initialled list is what ends the "still open" conversation when you ask for retainage. Then send the request: getting retainage released lists the close-out documents usually asked for alongside the punch list and writes the request letter.
Common questions
What is a punch list in construction?
The list of small items still to fix or finish near the end of a job, written at a walk-through by the GC, architect, owner or an inspector. Each item is fixed, marked done, then back-checked and accepted by whoever listed it.
Who is responsible for punch list items?
The trade whose work the item is. An item that is another trade's work, or work built as the drawings show, should be raised with the GC in writing straight away, so it is reassigned instead of staying on your list.
Does the punch list hold up retainage?
Often. Many subcontracts tie retainage release to completion and acceptance of your scope, and an open punch item is the most common reason given for holding the balance. Your subcontract says what release actually depends on.
A punch list that ends in your retainage
PayApps is hosted pay-app billing for specialty subcontractors. Each job keeps its punch list (open, overdue, done and accepted, the back-check email, a printable list with a column for the GC's initials) next to its close-out documents, pay applications and retainage, and says what still stands between the job and the release. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.