Pay app guides · schedule of values calculator · Lea esta guía en español

How to fill out a pay application, line by line

A pay application (pay app, payment application, progress billing, draw request) is how a contractor or subcontractor gets paid each month on a commercial job. Most follow the same two-part layout: a summary page with the money, and a continuation sheet with one row per line of the schedule of values. Many owners require the AIA G702/G703 forms, which are copyrighted and sold by the AIA; others take their own form or a portal. The arithmetic is the same either way, and this guide walks through it with one worked example.

Before you start: the schedule of values

A pay application is the line-by-line form of progress billing. If your job bills by stages instead (so much at rough-in, so much at drywall), see progress billing and draw schedules.

The schedule of values (SOV) splits your contract sum into line items, agreed with the GC before the first bill. Every pay app bills against those lines and no others. A good SOV has enough lines that progress on each is easy to measure (conduit, gear, rough-in, trim, not just "electrical"), keeps materials and labor apart where you will store material on site, and puts general conditions and closeout items on their own lines. Front-loading the early lines is common and is also the first thing an owner's reviewer looks for: check yours against your costs.

The continuation sheet, column by column

Our example is a $150,000 electrical subcontract plus one $8,500 change order, on its third application, 10% retainage.

ColumnWhat goes in itSwitchgear line in the example
Item numberThe SOV line number. Change orders get their own numbers (CO-1).3
Description of workThe SOV line description, unchanged from the approved SOV.Switchgear
Scheduled valueThe dollar value of the line from the approved SOV.$60,000
Work completed: from previous applicationThe total billed on this line on all earlier applications. It is last month's "total completed and stored" for the line minus last month's materials presently stored: stored material stays in its own column until it is installed, then it is billed as this period's work (how stored materials roll forward).$9,000
Work completed: this periodInstalled work this period, as a dollar value. Use the percent you can defend on a walk.$6,000
Materials presently storedMaterial delivered and stored (on site or, if the contract allows, off site) but not yet installed.$15,000
Total completed and stored to datePrevious + this period + stored.$30,000
Percent completeTotal completed and stored ÷ scheduled value.50%
Balance to finishScheduled value − total completed and stored.$30,000
RetainageThe line's share of retainage, if the form shows it per line.$3,000

The summary page, line by line

  1. Original contract sum: the base contract, $150,000. It never changes.
  2. Net change by change orders: approved change orders only, added and deducted, $8,500.
  3. Contract sum to date: line 1 + line 2, $158,500. It should equal the scheduled value total on the continuation sheet.
  4. Total completed and stored to date: the continuation sheet total, $79,850.
  5. Retainage: the percentage of completed work and of stored material, $7,985 at 10%. Some forms split this into the two parts.
  6. Total earned less retainage: line 4 − line 5, $71,865.
  7. Less previous certificates for payment: the sum of the payment-due amounts certified on earlier applications (not what you were actually paid, and not what you billed), $31,500.
  8. Current payment due: line 6 − line 7, $40,365.
  9. Balance to finish, including retainage: line 3 − line 6, $86,635.

The calculator fills every one of these from your SOV lines; press "Load an example" to see these exact numbers.

What to attach, and why pay apps get kicked back

Send the backup as one PDF

A GC's billing clerk handles every sub's pay app in the same few days. One PDF, with the application first, a page that lists what follows, and page numbers on every page, is easier to check than a dozen attachments, and is less likely to come back with "missing backup" when the file was really just lost in the email. Put it in the order the GC reviews it: the application, the waivers it asks for, stored-material invoices and insurance certificates, certified payroll if the job is prevailing wage, then photos. The signed copy the GC returns later does not belong in it.

Three kinds of file cause most of the trouble when the packet is put together:

Common reasons for a rejected or reduced pay app: a line billed over its scheduled value; "from previous" not matching last month's approved numbers; billing a change order that is not yet signed; retainage at the wrong rate; stored materials without backup; missing waivers. The calculator flags the first and checks the arithmetic of the rest; the pay application checker compares your draft with last month's approved application, line by line, and catches the "from previous" and changed-value mistakes.

Common questions

What does "less previous certificates for payment" mean on a pay app?

It is the sum of the payment-due amounts certified on earlier applications: not what you were actually paid, and not what you billed.

How do I fill in "work completed from previous application"?

It is the total billed on the line on all earlier applications: last month's total completed and stored for the line minus last month's materials presently stored. Stored material stays in its own column until it is installed.

Why do pay applications get rejected?

Common reasons are a line billed over its scheduled value, "from previous" not matching last month's approved numbers, billing a change order that is not yet signed, retainage at the wrong rate, stored materials without backup, and missing waivers.

Pay apps every month on every job?

PayApps is hosted pay-app billing for specialty subcontractors: carry the SOV forward each month, track retainage and change orders, and collect lien waivers in one place. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.