What makes site work billing different
| Situation | What the GC usually wants | How to bill it | Free guide or tool |
|---|---|---|---|
| Unit-price contract (per CY, LF, SF or ton) | Quantities this period and to date at the contract unit price, with how they were measured | Give each line a unit, a unit price and a contract quantity; bill the quantity installed each month, and keep the survey, count or tickets behind it | How to fill out a pay application |
| Rock, unsuitable soil or undercut | A measured quantity, often agreed in the field before it is removed, at the rock or undercut unit price if the subcontract has one | Bill it on its own line, not inside general excavation, and get the quantity signed the day it is measured | Change orders and the SOV |
| Quantities over the contract amount | A change order before the overrun is paid, under most subcontracts | Watch quantity to date against contract quantity and ask for the change before the line runs over | Change orders and the SOV |
| Import, export and stone by the load | Load or scale tickets that add up to the quantity billed | Total the tickets per period and keep them with the pay app as backup | T&M ticket log |
| Pipe, structures and fittings delivered ahead of install | Stored materials with invoices and delivery tickets, if the subcontract allows it | Bill them as stored and move them to work completed as they are laid, so they are billed once | Billing stored materials |
| Pumping, dewatering, standby and extra mobilizations | A signed ticket with crew, equipment hours and material | Write a T&M ticket the same day and get it signed by the GC's superintendent | T&M ticket log |
| Planning the job's quantities | A balanced SOV whose lines can be checked against the plans | Work out cut and fill from the grid before you set the lines | Earthwork cut and fill calculator |
An example site work schedule of values
An example with made-up lines, to show the shape; your subcontract sets the units, prices and quantities. Each month you enter the quantity installed, and the amount is quantity times unit price.
| Line | Example description | Unit | How it is billed |
|---|---|---|---|
| 1 | Mobilization | LS | Once, or in the parts the subcontract allows |
| 2 | Erosion and sediment control | LS or LF | Percent installed, or linear feet of silt fence |
| 3 | Clearing and grubbing | AC | Acres cleared this period |
| 4 | Unclassified excavation | CY | Cubic yards moved, from survey or agreed counts |
| 5 | Rock excavation | CY | Measured rock removed, on its own line |
| 6 | Storm pipe, 18 in. | LF | Linear feet laid and backfilled |
| 7 | Catch basins | EA | Each structure set |
| 8 | Aggregate base | TON | Tons placed, from scale tickets |
Where site work subs lose money on pay apps
- Rock billed as dirt. Rock or unsuitable soil dug out without a measured, signed quantity ends up inside the unclassified line at the cheaper price.
- Tickets that do not add up. A missing load ticket is a quantity the GC will not pay. Total the tickets before the pay app goes out.
- Overruns dug before the change order. Under most subcontracts the GC pays the contract quantity until a change is approved. Ask while the work is happening.
- Front-loaded mobilization. A mobilization line well above its cost is the first thing a reviewer cuts. Front-loading check compares each line's markup with the job's.
Common questions
How do you bill unit-price excavation on a pay application?
Each line carries a unit, a unit price and a contract quantity. Each month you report the quantity installed, measured by survey, count or tickets; the amount is that quantity times the unit price.
How do I get paid for rock excavation?
Bill it on its own line at the rock unit price if your subcontract has one, else as a change order. Measure it, get the quantity signed in the field before or while it is removed, and keep the measurement as backup.
Can I bill for pipe and structures delivered but not installed?
Often yes, as stored materials, if your subcontract allows it; attach invoices and delivery tickets. Move them to work completed as they are installed, so they are billed once.
Are weather days paid on a site work job?
Usually as extra time, not money, unless your subcontract says otherwise. Record each day lost in a daily report and ask for the time in writing, so it is there if a delay claim is needed later.
Quantity pay apps that add up to the cent
PayApps is hosted pay-app billing for specialty subcontractors. Its SOV lines can carry a unit, a unit price and a contract quantity; each month you enter the quantity installed and it computes the amount. It also tracks stored materials, logs T&M tickets for dewatering and standby, and keeps a daily report per day with the hours lost to weather. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.