What makes concrete billing different
| Situation | What the GC usually wants | How to bill it | Free guide or tool |
|---|---|---|---|
| Unit-price contract (per CY, SF or LF) | Quantities placed this period and to date, at the contract unit price | Give each line a unit, a unit price and a contract quantity; bill the quantity placed each month, and the dollars follow | How to fill out a pay application |
| Lump-sum contract with pours by area | Percent complete per area or element | Split the SOV by element (footings, walls, slab on grade, elevated decks, flatwork) and by area | Free Excel SOV template |
| Quantities over the contract amount | A change order before the overrun is paid, under most subcontracts | Watch quantity to date against contract quantity, and ask for the change before the line runs over | Change orders and the SOV |
| Extra pours, winter protection, pumping, standby time | A signed ticket with crew, equipment and material | Write a T&M ticket the same day with the pump, crew hours and yards, and get it signed | T&M ticket log |
| GC portals that ask for quantities | The SOV entered with units and unit values | Set up the unit-price lines once, the way the portal wants them | Billing in Procore, Textura and GCPay |
| Ready-mix and rebar suppliers | Lien waivers from them with your pay app | Collect conditional waivers with each application and unconditional ones once paid | Lien waiver log |
An example unit-price schedule of values
An example with made-up quantities and prices, to show the shape; your subcontract sets the units and prices. Each month you enter the quantity placed, and the amount is quantity times unit price.
| Line | Example description | Unit | How it is billed |
|---|---|---|---|
| 1 | Mobilization | LS | Once, as a lump sum (1 LS) |
| 2 | Spread footings | CY | Cubic yards placed this period |
| 3 | Foundation walls | CY | Cubic yards placed this period |
| 4 | Slab on grade, 5 in. | SF | Square feet placed and finished |
| 5 | Sidewalks | SF | Square feet placed |
| 6 | Curb and gutter | LF | Linear feet placed |
| 7 | Vapor barrier | SF | Square feet installed |
Where concrete subs lose money on pay apps
- Rounding. A unit price times a quantity has to come out to the cent the same way every month, or the to-date total drifts from the quantities. Keep the quantity and price, and let the dollars be computed.
- Overruns placed before the change order. Under most subcontracts the GC pays the contract quantity until a change is approved. Ask early.
- Pump and standby time on a verbal OK. Tickets signed on the day of the pour are the ones that get paid.
- Late payment nobody charges for. Many states set when a GC must pay a sub after it is paid, some with interest. Check your state.
Common questions
How do you bill a unit-price contract on a pay application?
Each line carries a unit, a unit price and a contract quantity. Each month you report the quantity placed this period; the amount is that quantity times the unit price, and the to-date quantity shows how much of the contract quantity is used.
What happens when concrete quantities run over the contract quantity?
Under most subcontracts the extra quantity needs an approved change order before it is paid. Track quantity to date against the contract quantity and ask for the change before the overrun.
How should pump time and standby be billed?
As extra work on a T&M ticket signed the same day, showing the pump, crew hours, equipment and any material, unless your subcontract already prices it.
Can lump-sum concrete work be billed by percent complete?
Yes. Split the schedule of values by element and area (footings, walls, slabs, decks, flatwork) and bill each line's percent complete.
Unit-price pay apps that add up to the cent
PayApps is hosted pay-app billing for specialty subcontractors. Its SOV lines can carry a unit, a unit price and a contract quantity; each month you enter the quantity placed and it computes the amount, shows quantities on the PDF and CSV, writes GCPay's unit-price SOV upload, and logs T&M tickets for pump and standby time. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.