Pay app guides · schedule of values calculator

Pay applications for commercial roofing contractors: roof areas, stored materials and the warranty

Commercial roofing pay applications bill a roof in pieces: by roof area and by system (tear-off, insulation, membrane, flashing, sheet metal), with expensive material often delivered and loaded weeks before it is installed. What turns up at tear-off (rotted deck, wet insulation) is extra work, and the last retainage often waits on the manufacturer's warranty. This page covers each, with the free guide or tool for it.

What makes roofing billing different

SituationWhat the GC usually wantsHow to bill itFree guide or tool
Several roof areas or buildingsPercent complete per area and per systemSplit the SOV by roof area and by system, so each month's percent can be checked from the roofFree Excel SOV template
Membrane, insulation and metal delivered or loaded ahead of installStored materials with invoices, delivery tickets and photos, if the subcontract allows itBill it as stored and move it to work completed as it is installed, so it is billed onceBilling stored materials
Deck or wet insulation found at tear-offA measured quantity at the subcontract's unit price for replacement, if it has one, else a change orderMeasure and photograph it before covering it, and get the quantity signed the same dayT&M ticket log
Weather daysA record of each day lost, and time asked for in writingLog the day and the hours lost in a daily report; ask for the time, not money, unless your subcontract pays itChange orders and the SOV
Manufacturer's warranty at close-outThe warranty, often after the manufacturer's inspection, before final retainage is releasedPut close-out on its own small line and list the warranty in the close-out documents from the startGetting retainage released
Supplier waiversLien waivers from the roofing distributor with your pay appCollect conditional waivers with each application and unconditional ones once paidLien waiver log
Pricing the roofA bid that matches the SOV you will billPrice tear-off, insulation and membrane by the square before you split the SOVFlat roof bid calculator

An example commercial roofing schedule of values

An example with made-up lines, to show the shape; your subcontract sets the lines. Areas and systems on their own lines make each month's percent easy to check against the roof itself.

LineExample descriptionUnitHow it is billed
1Mobilization, hoisting and safetyLSOnce, or in the parts the subcontract allows
2Roof A: tear-offLSPercent of Roof A torn off
3Roof A: insulation and cover boardLSPercent installed
4Roof A: membraneLSPercent installed
5Roof B: tear-off, insulation and membraneLSPercent installed
6Flashings and edge metalLS or LFPercent installed, or linear feet
7Deck replacement (unit price)SFSquare feet replaced, measured and signed
8Close-out and warrantyLSBilled when the warranty is issued

Where roofing subs lose money on pay apps

Common questions

How should a roofing contractor set up the schedule of values?

By roof area or building and by system (tear-off, insulation, membrane, flashing and sheet metal), with close-out and the warranty on a small line of its own. Each month's percent then comes from what is done on each roof.

Can I bill for roofing materials loaded on the roof but not installed?

Often yes, as stored materials, if your subcontract allows it; attach invoices, delivery tickets and photos. Move them to work completed as they are installed, so they are billed once.

How do I bill deck replacement found during tear-off?

At the unit price your subcontract sets for it, if it has one, else as a change order. Measure and photograph the area before it is covered and get the quantity signed by the GC that day.

Why is my final roofing retainage held?

Often because close-out is not complete: the manufacturer's warranty, the punch list, as-builts or a final lien waiver. Ask the GC in writing which items are open, and send them together.

Roofing pay apps with the backup attached

PayApps is hosted pay-app billing for specialty subcontractors. It tracks stored materials per line from one application to the next, keeps a daily report per day with the hours lost to weather, logs T&M tickets with photos for deck found at tear-off, and keeps a close-out checklist and punch list so you can see what the last retainage waits on. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.