California 20-day preliminary notice: who gets it, when, and a draft

On a private California job, a subcontractor or supplier that has not given a preliminary notice cannot record a valid mechanics lien or give a valid stop payment notice (Cal. Civ. Code § 8200(c)), and needs it (or a § 8612 notice) for a payment bond claim (§ 8200(d)). It is due 20 days after you first furnish work. Enter your dates below for the last day by delivery method and what a late notice still protects, then fill in the job for a draft with every item the statute lists.

Your dates

Your entries stay in this browser tab; nothing is uploaded.

"Work" in the statute covers labor, service, equipment and material. Dates count calendar days and are not moved off a weekend or holiday here, so serve well before the last day. Mail sent by one of the § 8110 services is given the day it is deposited (§ 8116(b)); ordinary first-class mail is not one of them.

Who gets the notice

A laborer gives none, and a claimant with a direct contract with the owner gives it only to the lender, if any (§ 8200(e)). One notice to each person covers all of your work on the job, and work you add later even outside its description (§ 8206(a), (c)), but if you work under contracts with more than one subcontractor, give a separate notice for each contract (§ 8206(b)).

Leaving it out has a second cost: for a licensed subcontractor whose subcontract pays more than $400, failing to give the notice is grounds for discipline under the Contractors' State License Law (§ 8216).

What the notice must say

California sets the contents, not a form. A notice that varies from the list still counts if it is enough to substantially inform the person of the required information (§ 8102(b)).

ItemSection
Name and address of the owner or reputed owner§ 8102(a)(1)
Name and address of the direct contractor§ 8102(a)(2)
Name and address of the construction lender, if any§ 8102(a)(3)
A description of the site sufficient to identify it, including its street address (a sufficient legal description saves a wrong or missing address)§ 8102(a)(4)
Your name, address and relationship to the parties§ 8102(a)(5)
A general description of the work provided and to be provided§§ 8102(a)(6)(A), 8202(a)(1)
The name of the person you provide the work to or for§ 8102(a)(6)(B)
A statement or estimate of your demand, if any, after all just credits and offsets§ 8102(a)(6)(C)
An estimate of the total price of the work provided and to be provided§ 8202(a)(2)
The NOTICE TO PROPERTY OWNER statement, in boldface§ 8202(a)(3)
From a subcontractor that has not paid all compensation due a laborer: the laborer's name and address, and any benefit fund owed (§ 8024(b))§ 8202(b)

A material invoice or certified payroll that carries all of this, given the way notices must be given, is enough on its own (§ 8202(c)).

Draft the notice

Fill in what you know. Anything the statute lists that is still blank is named under the draft. Print gives the statement in bold, as § 8202(a)(3) requires; a copied text needs the statement set in bold before you send it.

This is a draft built from the statute's list, not legal advice and not a form approved by anyone. Send one copy to each person in "Who gets the notice", and keep the proof (below). If the job is a public work, these sections do not apply; public works have their own notice rules (§ 9300 and following).

How to give it, and how to prove it

The statement, word for word (§ 8202(a)(3))

NOTICE TO PROPERTY OWNER

EVEN THOUGH YOU HAVE PAID YOUR CONTRACTOR IN FULL, if the person or firm that has given you this notice is not paid in full for labor, service, equipment, or material provided or to be provided to your construction project, a lien may be placed on your property. Foreclosure of the lien may lead to loss of all or part of your property. You may wish to protect yourself against this by (1) requiring your contractor to provide a signed release by the person or firm that has given you this notice before making payment to your contractor, or (2) any other method that is appropriate under the circumstances.

This notice is required by law to be served by the undersigned as a statement of your legal rights. This notice is not intended to reflect upon the financial condition of the contractor or the person employed by you on the construction project.

If you record a notice of cessation or completion of your construction project, you must within 10 days after recording, send a copy of the notice of completion to your contractor and the person or firm that has given you this notice. The notice must be sent by registered or certified mail. Failure to send the notice will extend the deadline to record a claim of lien. You are not required to send the notice if you are a residential homeowner of a dwelling containing four or fewer units.

Source: Cal. Civ. Code §§ 8102, 8106, 8110, 8116, 8118, 8200, 8202, 8204, 8206 and 8216, text from the California Legislative Counsel's official bulk download of California law (pubinfo_2025.zip), read 2026-11-25. Each section was added by Stats. 2010, Ch. 697 (SB 189), operative July 1, 2012, with no later amendment listed. Read them on leginfo.legislature.ca.gov before relying on this page. For the lien filing dates after the notice, see the free mechanics lien deadline calculator.

Common questions

Who has to send a California preliminary notice?

Before recording a lien claim, giving a stop payment notice or claiming on a payment bond, a claimant gives preliminary notice to the owner, the direct contractor and the construction lender, if any (Cal. Civ. Code § 8200(a)). A laborer does not have to, and a claimant with a direct contract with the owner gives it only to the construction lender, if any (§ 8200(e)).

When is the California preliminary notice due?

Not later than 20 days after you first furnished work on the job (§ 8204(a)). By personal delivery, certified or registered mail, express mail or an overnight carrier the notice is given the day it is delivered or deposited; left and mailed under Code Civ. Proc. § 415.20 it is given five days after mailing (§ 8116).

What if I send the preliminary notice late?

You can still give it, but a lien, stop payment notice or bond claim then covers only work performed within the 20 days before the notice and after (§ 8204(a)). Work before that window is not covered.

Is there an official California preliminary notice form?

No. The statute sets the contents, not a form: the names and addresses of the owner, direct contractor and lender, the site, who you are and your relationship to the parties, the work, who hired you, an estimate of the total price, and the NOTICE TO PROPERTY OWNER statement in boldface (§§ 8102, 8202).

Never miss the 20 days on a new job

PayApps is hosted pay-app billing for specialty subcontractors. On a California job it fills this notice from the job (owner, GC, site, contract sum plus approved change orders), counts the 20 days from the day you first furnish work, records each notice given (to whom, how, the day and tracking number) with its receipts, prints the § 8118 proof of notice declaration, and reminds you until the owner and the GC each have one. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.