What makes electrical billing different
| Situation | What the GC usually wants | How to bill it | Free guide or tool |
|---|---|---|---|
| Switchgear, panels, transformers and light fixtures are bought months before they are set | Proof of what was delivered and where it is: supplier invoices, bills of lading, photos, and for material stored off site, often insurance and title papers | Bill it as stored materials (column F), then move it to work completed in the month it is installed, so it is billed once | Billing stored materials |
| Rough-in and trim are months apart | Lines that let the GC see progress per area or floor, not one lump line for the whole building | Split the SOV by area or floor and by phase (rough-in, trim, gear, fixtures, low voltage), so each month's percent is easy to check | Free Excel SOV template |
| Owner changes, added circuits and devices, and work out of sequence | A signed T&M ticket or change order before it is billed | Get the ticket signed the day the work is done, turn signed tickets into change order requests, and bill only approved change orders | T&M ticket log, change order log |
| Public and federally funded jobs | A certified payroll for every week your crew is on site (29 CFR 5.5(a)(3)(ii)); some states want it filed in their own system | Keep the weekly payroll beside the pay app for the same job; a missing week is a common reason an application is held | our WH-347 guide |
| Distributors on the job | Lien waivers from your suppliers, and sometimes joint checks | Collect conditional waivers from suppliers with each pay app and unconditional ones once they are paid | Lien waiver log, joint checks |
| Retainage held for months after trim-out | Close-out documents (as-builts, O&M manuals, warranties, test reports) before release | Track the retainage per job and send the close-out package with the release request | Getting retainage released |
An example electrical schedule of values
This is an example of how electrical subs often break a lump-sum contract down, not a standard; your subcontract or the GC's form may set the lines. The point is lines small enough that a percent complete can be checked by walking the floor.
| Line | Example description | Why it is its own line |
|---|---|---|
| 1 | Mobilization, permits and submittals | Billed early and once; keep it modest (see front-loading below) |
| 2 | Temporary power and lighting | Used through the whole job, often removed at the end |
| 3 | Underground and in-slab conduit | Done early, before the slab is poured |
| 4 to 9 | Rough-in by floor or area | Progress the GC can see wall by wall |
| 10 | Switchgear and distribution (material) | A large stored-materials line while it waits for the electrical room |
| 11 | Switchgear and distribution (labor) | Billed when set, terminated and tested |
| 12 | Light fixtures (material) | Often delivered in one shipment, installed over months |
| 13 to 18 | Trim and devices by floor or area | Late work that should carry its fair share of the contract |
| 19 | Fire alarm and low voltage | Often a separate scope or lower-tier sub |
| 20 | Testing, close-out and as-builts | The last line; ties to the retainage release |
Where electrical subs lose money on pay apps
- Gear billed as work before it is set. If the GC rejects the line, the whole application comes back. Bill delivered gear as stored materials with the invoice attached, under the contract's stored-material rules (on federal work, FAR 52.232-5 sets when off-site material may be paid).
- Extras done on a verbal OK. Unsigned tickets are the extras most often never paid. A ticket signed the same day, then a change order request, is the habit that gets them paid.
- A front-loaded SOV. Loading mobilization and rough-in leaves trim and close-out underfunded, and a GC who notices may cut the early lines. Check yours against a balanced SOV.
- Retainage nobody chases. Ten jobs each holding 5 to 10% is real money; the retainage tracker lists what is owed and since when.
Common questions
Can I bill for switchgear before it is installed?
Usually, as stored materials, if your subcontract allows it and you attach what it asks for (invoices, delivery proof, photos, and for off-site storage often insurance and title papers). Move it from stored to work completed in the month it is installed so it is billed once.
How should an electrical contractor break down the schedule of values?
By area or floor and by phase (underground, rough-in, gear, fixtures, trim, low voltage, testing and close-out), with expensive material on its own lines. Small lines make each month's percent easy to check and keep late work funded.
Do electrical subs need certified payroll?
On federal and federally assisted construction covered by Davis-Bacon, yes: every contractor and subcontractor submits a weekly certified payroll for the weeks it has workers on site. Several states require the same on state public works, some in their own online systems.
How do I get paid for added circuits and devices?
Write a T&M ticket or change order request and get it signed before or on the day of the work, then bill it once the change order is approved. Bills for unsigned extras are the ones most often refused.
Electrical pay apps, gear and payroll in one place
PayApps is hosted pay-app billing for specialty subcontractors. It keeps your SOV by line, carries stored gear from month to month until it is installed, logs T&M tickets and change orders, prints the weekly WH-347 certified payroll from the same job, and tracks retainage until close-out. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.