Pay app guides · schedule of values calculator

Retainage explained, with the public retainage caps in 25 states

Retainage (also called retention) is the part of each progress payment the owner holds back until the job is finished, as security that the work gets completed and corrected. On a subcontract, the general contractor usually holds the same percentage back from you. On a typical job it is 5 or 10 percent of every bill, which for a specialty sub is often the whole profit margin, sitting in someone else's account for months.

How retainage is calculated on a pay application

Retainage is a percentage of the work completed to date, and usually of materials stored too, not of this month's bill alone. Each application recalculates the total held:

Worked example. A $158,500 electrical subcontract with 10% retainage has $79,850 completed and stored. Retainage held is $7,985, earned less retainage is $71,865, and with $31,500 certified on earlier applications, this month's payment due is $40,365. You can load this example in the calculator and change the rate to see what a 5% cap would be worth: $3,992.50 more cash this month.

Reduction and release

Many contracts, and some statutes, cut the rate once the job is 50% complete or stop withholding new retainage altogether. The balance is released at substantial or final completion, usually against a final lien waiver, closeout documents and sometimes a punch list. Subs on early trades (sitework, foundations, steel) can wait a year or more for their retainage unless the contract allows line-item or early release. Ask for it in writing at the subcontract stage, not after.

A partial release has to land on the continuation sheet line by line, and the lines have to add up to the cent. Split the release in proportion to what each line holds. Say the GC agrees to release half the retainage: line 1 holds $6,000.00 and line 2 holds $2,050.00, so $8,050.00 is held and $4,025.00 comes out. Line 1 releases $3,000.00 and line 2 releases $1,025.00. When a share comes to a fraction of a cent, round the lines down and give the leftover cents to the lines with the largest fractions, so the total stays exact and no line releases more than it holds. The release lowers retainage held on that application (line 5) and raises its payment due (line 8) by the same amount.

Read a reduction clause closely, because it can mean two numbers. On a $100,000 subcontract with $70,000 completed, "10%, then 5% after 50% complete" holds $3,500 if 5% applies to everything billed. It holds $6,000 if 5% applies only to work after the halfway point ($5,000 on the first $50,000 plus $1,000 on the next $20,000). The pay application generator works out either one.

Lines with their own rate, or none

Retainage does not have to be one rate across the whole continuation sheet. Some subcontracts bill certain lines without retainage, the bond premium being a common one since the sub pays it up front, and some hold a different rate on one scope. When yours does, work out retainage line by line: each line's work to date and stored materials times that line's rate, then add the lines up for line 5. Say application #1 bills a $2,000 bond line in full and $10,000 of rough-in at 10%. With the bond exempt, retainage is $1,000 and payment due is $11,000; held at 10% across the board it would be $1,200 and $10,800. Say on the application which lines carry their own rate, so the GC's reviewer sees why line 5 is not a flat 10%, and keep that rate when the job-wide rate drops at 50% unless the contract says otherwise. Your subcontract's retainage clause decides which lines qualify; this is arithmetic, not legal advice.

Flow-down

Several of the statutes below say the prime contractor cannot hold back a higher percentage from a subcontractor than the owner holds from the prime (California and Texas say so directly). Read your subcontract against that: a 10% sub retainage on a 5% public job is worth a question.

Retainage caps on public construction, 25 states

The first twelve rows were read on 2026-11-24 through search results limited to each state legislature's own site. On 2026-11-25 the statute pages themselves were loaded: Texas, Florida, New York, North Carolina, Michigan, Virginia, Washington, Massachusetts and Arizona matched the rows as written; California, Pennsylvania and Illinois refused automated loads and still rest on the first reading. Minnesota, Nevada, Oregon and Utah were added on 2026-11-25 from the statute pages directly. Delaware, Idaho, Iowa, Kansas, Maine, Missouri and Ohio were added on 2026-11-28, and North Dakota and South Carolina later the same day, each from the statute page on the legislature's own site; the text read is kept in sources/retainage-caps.txt. These statutes cover public work, often only certain public owners, and have exceptions not shown here. They change: open the linked statute and read your contract before relying on a row. This is a summary, not legal advice.

StateStatuteCap on public workNotes
CaliforniaPublic Contract Code §72015% of each payment, and 5% of the contract price in totalSame cap flows down to subs. A higher rate is allowed only if the project is first found "substantially complex" (at a public hearing for local agencies).
TexasGovernment Code §2252.03210% if the contract is under $5 million; 5% at $5 million or moreDam contracts stay at 10%. A prime may not hold more from a sub than the owner holds from the prime. No retainage after the prime's work is complete.
FloridaFlorida Statutes §255.0785% of each progress paymentRetainage paid for sub or supplier work must be passed down promptly. Older versions allowed 10% until 50% complete. Federally funded work can differ.
New YorkGeneral Municipal Law §106-b5% of each progress paymentUp to 10% only if the public owner does not require full performance and payment bonds. The same 5% rule applies from contractor to subcontractor.
Pennsylvania62 Pa.C.S. §392110% until 50% complete, then 5%Half the retained amount is returned at 50% completion. Department of General Services contracts: 6%, then 3%.
Illinois30 ILCS 550/1 (Public Construction Bond Act)10% before 50% complete, then reduced so no more than 5% is heldIDOT is excluded. Private jobs: the Contractor Prompt Payment Act, 815 ILCS 603/20, sets the same 10%/5% pattern (effective 2019-08-20).
North CarolinaG.S. 143-134.15% of each periodic paymentLimits on further retainage once the project is 50% complete. Small projects carry no retainage: the text read says under $150,000, and a 2025 session bill (H1123) changes that threshold, so check the current section.
MichiganMCL 125.156310% until 50% complete, then no moreUp to 10% of later work only if progress is unsatisfactory. Retained funds go in an interest-bearing account.
VirginiaCode of Virginia §2.2-43335% (the contractor is paid at least 95% of the earned sum)Applies to subcontracts with progress payments on public projects. Localities offer an escrow option on contracts of $200,000 or more.
WashingtonRCW 60.28.0115% of moneys earnedSubs: no more than 5% either. A bond can replace cash retainage. Release 60 days after completion, subject to claims and tax liens. Federal transportation work relies on the bond instead.
MassachusettsM.G.L. c.30 §39G5% of each periodic paymentDrops to 1% at substantial completion. Private jobs: Acts of 2014, chapter 276, caps retainage at 5% of each progress payment.
ArizonaA.R.S. §34-22110% of each progress estimateAt 50% complete, half the retained amount is payable on request if progress is satisfactory, and later payments may be held at 5%. State agency contracts: A.R.S. §41-2576.
MinnesotaMinn. Stat. §15.725% of each progress paymentThe agency may reduce or drop retainage while work progresses satisfactorily, and must release all of it within 60 days of substantial completion. If it reduces retainage, the contractor must reduce subs' retainage at the same rate, and must pay subs their retainage within 10 days of receiving it unless their work is disputed.
NevadaNRS 338.5155% until 50% completeAfter 50%, the public body may stop withholding and pay back retainage if progress is satisfactory, and if it keeps withholding, further limits apply. It may release a sub's share early once that sub's work is done and lien releases are in. Interest accrues on retainage (NRS 338.460). Department of Transportation contracts are excluded (NRS 338.480).
OregonORS 279C.570(7)5% of each progress paymentAfter 50% complete the agency may drop retainage on the remaining payments, on the contractor's written application with the surety's approval. Bonds or securities can stand in for cash retainage (ORS 279C.560). Retainage a contractor holds from its subs follows ORS 701.420 (ORS 279C.555).
UtahUtah Code §13-8-55% of each payment, and 5% of the total construction priceCovers private nonresidential work too, not only public. The same cap applies from the prime to subs and between subs, and a lower owner rate flows down. Retainage sits in an interest-bearing account and is released within 45 days of the later of the billing, the certificate of occupancy or final acceptance. The version that takes effect on 1 January 2027 keeps these rules and changes only cross-references (both versions compared on le.utah.gov, 2026-11-25).
Delaware29 Del. C. §6962(d)(5)5% of the value of the work completedState agencies' large public works contracts. On completion the agency may release 60% of what it holds; the rest waits for the contract's reports, payment of the subs in trades listed on the bid form (150% of a disputed amount may be kept) and final payment.
IdahoIdaho Code §54-1926(3)5% of the total amount payableApplies where the public body requires a performance or payment bond over 50% of the contract. The prime may not hold more than 5% from a sub either, and must pay the sub's retainage within 30 days after the subcontract is complete. Retainage on portions accepted as complete is released within 30 days of acceptance.
IowaIowa Code §573.123% of each monthly paymentThe prime may hold from a sub no more than the lesser of 3% and the subcontract's rate. The 2026 Iowa Code's history note lists an amendment to these paragraphs by 2025 Acts, chapter 29, so check an older subcontract form against it; §573.13 repeats that the retained fund is never more than 3%. Subs are paid within 7 days after the prime is paid for their work.
KansasK.S.A. 16-19045%, or up to 10% where the owner or contractor finds a higher rate is needed to ensure performanceThe Kansas Fairness in Public Construction Contract Act; it covers contractor-to-sub contracts too, and its rights cannot be waived by contract (K.S.A. 16-1901). Roads, highways and bridges are excluded (K.S.A. 16-1902). All remaining retainage on undisputed payments is released within 30 days after substantial completion. Alternate security can be requested before work starts.
Maine5 M.R.S. §17465% of the money due, held until the State accepts the projectState contracts for public improvements. Once the contract is substantially complete the State may reduce the amount held on request. The contractor may draw retained money out by depositing approved securities with the Treasurer of State.
MissouriRSMo §8.9605% of the value of the contract or subcontractUp to 10% where no bond is required because the contract is not estimated to exceed $50,000. Covers state and local public works and subcontracts on them. The section was RSMo 34.057 until it was transferred in 2022.
OhioOhio Rev. Code §153.12, §153.14Labor paid at no less than 96% of the approved estimate (4% held); materials delivered but not yet installed paid at 92% of invoice (§153.14)No subcontract may be paid at a lower rate than the contractor. Since 30 September 2025 (House Bill 96), §153.13 no longer says retainage stops at 50% complete or goes into escrow; retainage and its interest on the substantially completed portion are paid within 30 days, the rest within 30 days of final completion. Unauthorized withholding of retainage earns interest (§153.14).
North DakotaN.D. Cent. Code §48-01.2-1310% of each estimate until 50% complete, then no moreFurther retainage after 50% only if unsatisfactory progress or performance is documented. At 95% complete the governing body may pay up to 95% of what it has retained; the rest when the architect or engineer approves. Retained money may be invested for the contractor's benefit, and an approved estimate unpaid after 30 days earns interest (§48-01.2-14).
South CarolinaS.C. Code §11-35-3030(4)3.5% of each progress paymentThe State Consolidated Procurement Code, and the same 3.5% applies in a subcontract. On a state job each contractor's or sub's work is its own division: its retainage is released when that division is certified complete, and the prime pays the sub within ten days of receiving it.

Georgia and New Jersey also regulate public retainage; they are left out because their current text could not be confirmed on this date. Several other states (Vermont, 9 V.S.A. §4005, for one) set when retainage must be paid without capping the rate, so they are not in this table. Private-project rules differ from the public ones above in most states.

What to do with this

Common questions

How is retainage calculated on a pay application?

Retainage held is the work completed to date times the work rate, plus stored materials times the stored rate, minus retainage already released. It is a percentage of everything completed and stored to date, not of this month's bill alone.

Can a GC hold more retainage from a sub than the owner holds from the GC?

Several state statutes say the prime contractor cannot hold back a higher percentage from a subcontractor than the owner holds from the prime; California and Texas say so directly. A 10% sub retainage on a 5% public job is worth a question.

When is retainage released?

The balance is released at substantial or final completion, usually against a final lien waiver, closeout documents and sometimes a punch list. Many contracts, and some statutes, cut the rate once the job is 50% complete.

Tracking retainage across every open job?

PayApps is hosted pay-app billing for specialty subcontractors that keeps retainage held, released and due on every job in one view. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.