Pay app guides · lien waiver forms by state

Georgia lien waiver forms

Georgia sets the wording of lien waivers in statute (O.C.G.A. § 44-14-366). How strict: "Shall substantially follow the language of the following form", "in at least 12 point font"; no statement waives lien or bond rights unless it is one of these forms and you have been paid. Below are both statutory forms, word for word, with a blank line wherever the statute leaves one. Print the one you need, fill it in by hand, and keep a copy.

The forms on this page

FormUse it forStatute
Waiver and Release of Lien and Payment Bond Rights upon Interim Paymentprogress payments, before or after the money clears (the form itself is neither conditional nor unconditional)O.C.G.A. § 44-14-366(d)
Waiver and Release of Lien and Payment Bond Rights upon Final Paymentfinal payments, before or after the money clears (the form itself is neither conditional nor unconditional)O.C.G.A. § 44-14-366(e)

Each form is the statute's text as read on 2026-11-26, from the official source linked with it. The grey caption under each blank says what goes there; it is our guide, not part of the form. Statutes change: open the linked section before relying on a form, and have a Georgia construction attorney review anything you are unsure of.

What Georgia asks of you

Notes on the forms

Waiver and Release of Lien and Payment Bond Rights upon Interim Payment

Use it for: progress payments, before or after the money clears (the form itself is neither conditional nor unconditional). From O.C.G.A. § 44-14-366(d), read 2026-11-26. The statute requires at least 12 point type; it prints that way here.

WAIVER AND RELEASE OF LIEN AND PAYMENT BOND RIGHTS UPON INTERIM PAYMENT

STATE OF GEORGIA

COUNTY OF County (heading)

THE UNDERSIGNED MECHANIC AND/OR MATERIALMAN HAS BEEN EMPLOYED BY Name of contractor (NAME OF CONTRACTOR) TO FURNISH Materials and/or labor furnished (DESCRIBE MATERIALS AND/OR LABOR) FOR THE CONSTRUCTION OF IMPROVEMENTS KNOWN AS Title of the project or building (TITLE OF THE PROJECT OR BUILDING) WHICH IS LOCATED IN THE CITY OF City the improvements are in, COUNTY OF County the improvements are in, AND IS OWNED BY Name of owner (NAME OF OWNER) AND MORE PARTICULARLY DESCRIBED AS FOLLOWS:

Property description

(DESCRIBE THE PROPERTY UPON WHICH THE IMPROVEMENTS WERE MADE BY USING EITHER A METES AND BOUNDS DESCRIPTION, THE LAND LOT DISTRICT, BLOCK AND LOT NUMBER, OR STREET ADDRESS OF THE PROJECT.)

UPON THE RECEIPT OF THE SUM OF Sum, THE MECHANIC AND/OR MATERIALMAN WAIVES AND RELEASES ANY AND ALL LIENS OR CLAIMS OF LIENS IT HAS UPON THE FOREGOING DESCRIBED PROPERTY OR ANY RIGHTS AGAINST ANY LABOR AND/OR MATERIAL BOND THROUGH THE DATE OF Through date (DATE) AND EXCEPTING THOSE RIGHTS AND LIENS THAT THE MECHANIC AND/OR MATERIALMAN MIGHT HAVE IN ANY RETAINED AMOUNTS, ON ACCOUNT OF LABOR OR MATERIALS, OR BOTH, FURNISHED BY THE UNDERSIGNED TO OR ON ACCOUNT OF SAID CONTRACTOR FOR SAID BUILDING OR PREMISES.

GIVEN UNDER HAND AND SEAL THIS ______ DAY OF ______________, ____.

(SEAL): sign here

Claimant: Claimant

(WITNESS): sign here

(ADDRESS): sign here

NOTICE: WHEN YOU EXECUTE AND SUBMIT THIS DOCUMENT, YOU SHALL BE CONCLUSIVELY DEEMED TO HAVE WAIVED AND RELEASED ANY AND ALL LIENS AND CLAIMS OF LIENS UPON THE FOREGOING DESCRIBED PROPERTY AND ANY RIGHTS REGARDING ANY LABOR OR MATERIAL BOND REGARDING THE SAID PROPERTY TO THE EXTENT (AND ONLY TO THE EXTENT) SET FORTH ABOVE, EVEN IF YOU HAVE NOT ACTUALLY RECEIVED SUCH PAYMENT, 90 DAYS AFTER THE DATE STATED ABOVE UNLESS YOU FILE AN AFFIDAVIT OF NONPAYMENT PRIOR TO THE EXPIRATION OF SUCH 90 DAY PERIOD. THE FAILURE TO INCLUDE THIS NOTICE LANGUAGE ON THE FORM SHALL RENDER THE FORM UNENFORCEABLE AND INVALID AS A WAIVER AND RELEASE UNDER O.C.G.A. § 44-14-366.

Waiver and Release of Lien and Payment Bond Rights upon Final Payment

Use it for: final payments, before or after the money clears (the form itself is neither conditional nor unconditional). From O.C.G.A. § 44-14-366(e), read 2026-11-26. The statute requires at least 12 point type; it prints that way here.

WAIVER AND RELEASE OF LIEN AND PAYMENT BOND RIGHTS UPON FINAL PAYMENT

STATE OF GEORGIA

COUNTY OF County (heading)

THE UNDERSIGNED MECHANIC AND/OR MATERIALMAN HAS BEEN EMPLOYED BY Name of contractor (NAME OF CONTRACTOR) TO FURNISH Materials and/or labor furnished (DESCRIBE MATERIALS AND/OR LABOR) FOR THE CONSTRUCTION OF IMPROVEMENTS KNOWN AS Title of the project or building (TITLE OF THE PROJECT OR BUILDING) WHICH IS LOCATED IN THE CITY OF City the improvements are in, COUNTY OF County the improvements are in, AND IS OWNED BY Name of owner (NAME OF OWNER) AND MORE PARTICULARLY DESCRIBED AS FOLLOWS:

Property description

(DESCRIBE THE PROPERTY UPON WHICH THE IMPROVEMENTS WERE MADE BY USING EITHER A METES AND BOUNDS DESCRIPTION, THE LAND LOT DISTRICT, BLOCK AND LOT NUMBER, OR STREET ADDRESS OF THE PROJECT.)

UPON THE RECEIPT OF THE SUM OF Sum, THE MECHANIC AND/OR MATERIALMAN WAIVES AND RELEASES ANY AND ALL LIENS OR CLAIMS OF LIENS IT HAS UPON THE FOREGOING DESCRIBED PROPERTY OR ANY RIGHTS AGAINST ANY LABOR AND/OR MATERIAL BOND ON ACCOUNT OF LABOR OR MATERIALS, OR BOTH, FURNISHED BY THE UNDERSIGNED TO OR ON ACCOUNT OF SAID CONTRACTOR FOR SAID PROPERTY.

GIVEN UNDER HAND AND SEAL THIS ______ DAY OF ______________, ____.

(SEAL): sign here

Claimant: Claimant

(WITNESS): sign here

(ADDRESS): sign here

NOTICE: WHEN YOU EXECUTE AND SUBMIT THIS DOCUMENT, YOU SHALL BE CONCLUSIVELY DEEMED TO HAVE WAIVED AND RELEASED ANY AND ALL LIENS AND CLAIMS OF LIENS UPON THE FOREGOING DESCRIBED PROPERTY AND ANY RIGHTS REGARDING ANY LABOR OR MATERIAL BOND REGARDING THE SAID PROPERTY TO THE EXTENT (AND ONLY TO THE EXTENT) SET FORTH ABOVE, EVEN IF YOU HAVE NOT ACTUALLY RECEIVED SUCH PAYMENT, 90 DAYS AFTER THE DATE STATED ABOVE UNLESS YOU FILE AN AFFIDAVIT OF NONPAYMENT PRIOR TO THE EXPIRATION OF SUCH 90 DAY PERIOD. THE FAILURE TO INCLUDE THIS NOTICE LANGUAGE ON THE FORM SHALL RENDER THE FORM UNENFORCEABLE AND INVALID AS A WAIVER AND RELEASE UNDER O.C.G.A. § 44-14-366.

Common questions

Does Georgia have a statutory lien waiver form?

Yes. O.C.G.A. § 44-14-366 sets 2 forms: interim payment and final payment, each waiving "upon the receipt of the sum". How strict: "Shall substantially follow the language of the following form", "in at least 12 point font"; no statement waives lien or bond rights unless it is one of these forms and you have been paid. The forms on this page are printed word for word from the statute as read on 2026-11-26.

Which Georgia lien waiver form goes with which payment?

Waiver and Release of Lien and Payment Bond Rights upon Interim Payment: progress payments, before or after the money clears (the form itself is neither conditional nor unconditional). Waiver and Release of Lien and Payment Bond Rights upon Final Payment: final payments, before or after the money clears (the form itself is neither conditional nor unconditional).

When should I sign an unconditional lien waiver in Georgia?

Only once the payment it covers has cleared your bank. Before that, give the conditional form if Georgia has one, and keep retainage, unapproved change orders and disputed amounts out of a progress waiver. This page is not legal advice; ask a Georgia construction attorney before signing anything you are unsure of.

Fill these in from your pay app instead

PayApps is hosted pay-app billing for specialty subcontractors that prints Georgia's statutory waiver with each pay application, filled in from the job and the amount due, and holds the unconditional one until the payment has cleared. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.