Pay app guides · schedule of values calculator

Payment bond claims on state and local public jobs: notice and suit deadlines in 31 states

A school, a county road or a state university building cannot be liened: it is public property. What protects subcontractors and suppliers instead is the payment bond the prime contractor furnishes under the state's own bond law, often called a "little Miller Act" after the federal Miller Act. The bond pays when the prime or a sub does not, but only if your notices go out on time and you sue before the limit. Each state counts those dates differently, and some count from a day you do not control, such as the public body's acceptance of the work.

The deadlines, state by state

"Not in contract with the prime" means you contracted with one of the prime's subcontractors (a sub-sub or a supplier to a sub). "Everyone" applies to first-tier subs and suppliers too. Each statute was read on its legislature's own site on 2026-11-27 (Colorado, Iowa, Maine, Louisiana, Kansas, Delaware, Nebraska, Rhode Island, Montana, North Dakota, South Carolina, South Dakota, Alaska and Wyoming on 2026-11-28).

StateStatuteNot in contract with the primeEveryoneSuit on the bond
TexasTex. Gov't Code ch. 2253Notice of the unpaid claim to the prime by the 15th day of the 2nd month after each month of work (§ 2253.047(c))Notice with a sworn statement of account to the prime and the surety by the 15th day of the 3rd month after each month of work (§ 2253.041); retainage claims by the 90th day after final completion of the public work contract (§ 2253.046)May sue if unpaid on the 61st day after the notice is mailed (§ 2253.073); not after the first anniversary of mailing (§ 2253.078(b))
FloridaFla. Stat. § 255.05Notice to the contractor that you will look to the bond, before or within 45 days after you start; a sworn notice of nonpayment to the contractor (copy to the surety) no later than 90 days after your last day (§ 255.05(2)(a)2)None beyond the suit (laborers are exempt from the notices)Within 1 year after your last labor or material (§ 255.05(10)); the contractor can shorten it to 60 days with a recorded notice of contest
New YorkN.Y. State Fin. Law § 137Written notice to the contractor within 120 days from your last day, delivered personally or by registered mail (§ 137(3))None beyond the suitMay sue after 90 days unpaid; within one year from the public owner's completion and acceptance of the improvement (§ 137(4)(b))
VirginiaVa. Code § 2.2-4341Written notice to the contractor within 90 days from your last day, by registered or certified mail; retainage claims are not held to the 90 days (§ 2.2-4341(B))None beyond the suitMay sue after 90 days unpaid; within one year after your last day (§ 2.2-4341(C))
WashingtonRCW 39.08.030, 39.08.065Material suppliers to a subcontractor: notice to the contractor within 10 days after the first delivery (RCW 39.08.065)Notice of claim filed with the public body (not the contractor) within 30 days after completion of the contract and acceptance of the work (RCW 39.08.030(1))Not stated in these sections; no attorney fees for a suit filed within 30 days of the notice
ArizonaA.R.S. § 34-223The preliminary twenty-day notice (as § 33-992.01 provides) and a ninety-day notice to the contractor within 90 days after your last day, by a means with third-party verification of delivery (§ 34-223(A))None beyond the suitMay sue after 90 days unpaid; within one year after your last day (§ 34-223(B))
North CarolinaN.C. Gen. Stat. §§ 44A-27, 44A-28Notice of claim to the contractor within 120 days from your last day, by certified mail or signature confirmation (§ 44A-27(b), (c)); a notice of public subcontract for the part of a claim over $20,000, which reaches back only 75 days before it is servedNone beyond the suitMay sue after 90 days unpaid; within the longer of one year from your last day or one year from final settlement with the contractor (§ 44A-28(b))
OhioOhio Rev. Code § 153.56On labor or materials over $30,000, a notice of furnishing to the principal contractor; recovery reaches back only 21 days before it is served (§ 153.56(C), (D))A statement of the amount due to the sureties not later than 90 days after the contract's completion and the improvement's acceptance (§ 153.56(A))Not until 60 days after the statement; not later than one year from acceptance (§ 153.56(B))
MassachusettsMass. Gen. Laws ch. 149, § 29Written notice to the contractor within 65 days after your last day, by registered or certified mail; a sub's supplier of specially fabricated material also notifies the order within 20 days after its final written approval (§ 29, third paragraph)None beyond the petition (a claimant in contract with the prime may file once unpaid 65 days after the amount was due)A petition in equity within one year after your last day (§ 29, second paragraph); no decree before the 70th day
MichiganMCL 129.207, 129.209A notice to the principal contractor within 30 days after you first furnish (what, for whom, where), and a notice of claim to the principal contractor and the governmental unit within 90 days from your last day, both by certified mail (MCL 129.207)None beyond the suitMay sue after 90 days unpaid; not after one year from the day final payment was made to the principal contractor (MCL 129.209)
MinnesotaMinn. Stat. § 574.31The same notice as everyoneA sworn notice of claim to the surety and the contractor, at the addresses in the bond, within 120 days after your last day, personally or by certified mail; the statute sets out the form (subd. 2(a))Within one year from your last day (subd. 2(c)), extendable by stipulation or an unanswered notice to the surety (subd. 2(d))
NevadaNRS 339.035, 339.055A notice to the contractor within 30 days after you first furnish, and a notice of claim within 90 days from your last day, by registered or certified mail (NRS 339.035(2))None beyond the suitMay sue after 90 days unpaid; within one year from your last day (NRS 339.055(2)). Bonds are required on contracts over $100,000
OregonORS 279C.600-279C.610The same notice as everyoneA signed notice of claim, in the form ORS 279C.605(3) sets out, to the contractor and the contracting agency within 180 days after your last day, by registered or certified mail or by hand (200 days for benefit fund contributions)Within two years after your last day (ORS 279C.610(3))
IdahoIdaho Code § 54-1927A sub's sub or supplier: written notice to the contractor within 90 days from your last day, stating the amount and who you worked for, by registered or certified mailNone beyond the suitMay sue after 90 days unpaid; within one year from your last day, or for a subcontractor of the prime one year from the day final payment under its subcontract became due
MarylandMd. Code, State Fin. & Proc. §§ 17-108, 17-109Written notice to the contractor within 90 days after your last day, stating the amount and who you worked for, by certified mail (§ 17-108(b))None beyond the suitMay sue after 90 days unpaid; within 1 year after the public body finally accepts the work (§ 17-109(b)). A contract term waiving the bond right, or making it wait on the owner paying, is void
MissouriMo. Rev. Stat. § 107.170Only a remote supplier (a material supplier to a second-tier or lower sub, or to another supplier): written notice to the contractor that it has not been paid, within ninety days of its last supply (§ 107.170.2)NoneNot stated in this section. Bonds are required on public works estimated over $50,000
UtahUtah Code §§ 63G-6a-1103, 38-1b-202The same notice as everyoneEvery subcontractor not in contract with the owner (wage laborers aside) files a preliminary notice with the State Construction Registry by the later of 20 days after starting work and 20 days after the notice of commencement (§ 38-1b-202(1)); filed late, it covers only work from five days after filingMay sue after 90 days unpaid; within one year after your last day, in a county where the contract was performed, with attorney fees to the prevailing party (§ 63G-6a-1103(4))
ColoradoC.R.S. §§ 38-26-105 to 38-26-107The same filing as everyoneA verified statement of the amount due and unpaid, filed with the public body that awarded the contract, at any time up to and including final settlement; on a contract over $150,000 the public body publishes the settlement date at least ten days ahead (§ 38-26-107(1))Within 90 days following the published final settlement date, with a notice of lis pendens filed with the public body to keep the funds withheld (§ 38-26-107(2), (3)); on a local contract over $50,000, within six months after the completion of the work (§ 38-26-105(1)). Read from the 2024 printout, the latest the General Assembly's site serves
IowaIowa Code ch. 573A one-time written notice to the principal contractor (your name, mailing address, phone and the subcontractor you work for) within 30 days of first furnishing, not needed on highway, bridge or culvert projects (§ 573.15)An itemized, sworn statement of the claim filed with the officer or board that let the contract, within 30 days after completion and final acceptance, or later while the public body has not paid in full and no action is pending (§§ 573.7, 573.10)An action in equity in the county of the work, after 30 and not later than 60 days following completion and final acceptance (§ 573.16(1)); within 30 days of the contractor's written demand to sue (§ 573.16(2))
Maine14 M.R.S. § 871Written notice to the contractor within 90 days from your last day, stating the amount and who you worked for, by registered or certified mail (§ 871(4))None beyond the suitMay sue after 90 days unpaid; not after one year from your last day, in the county of the work (§ 871(4), (6)). Bonds are required on contracts over $125,000
LouisianaLa. R.S. 38:2242, 38:2247Also written notice to the contractor within 45 days from the recordation of the acceptance (or of default), stating the amount and who you worked for, by registered or certified mail to its Louisiana office (§ 38:2247(A))A sworn statement of the amount due, filed with the public body and recorded with the parish recorder of mortgages within 45 days after the recordation of the acceptance of the work (or of default) (§ 38:2242(B))Within one year from the registry of acceptance (or of default) (§ 38:2247(A)); 10% attorney's fees on a full recovery after demand (§ 38:2246). Bonds are required on contracts over $25,000
KansasK.S.A. 60-1111None in the statuteNone beyond the suitNot after six months from the completion of the public improvement (60-1111(b)). Bonds are required on contracts over $100,000 and filed with the district court clerk of the county
Delaware29 Del. C. § 6962(d)(9)None in the statuteNone beyond the suitIn the agency's name, within 3 years after the last work was done on the contract, or 1 year after the contractor ceased work if the bond so provides (§ 6962(d)(9)d)
NebraskaNeb. Rev. Stat. §§ 52-118.01, 52-118.02Written notice to the contractor within four months from your last day, stating the amount and who you worked for, by registered or certified mail (§ 52-118.01)None beyond the suitMay sue after 90 days unpaid; not after one year from final settlement of the prime contract (§ 52-118.02). Bonds are required over $15,000 (state) or $10,000 (local)
Rhode IslandR.I. Gen. Laws §§ 37-12-2, 37-12-5Written notice to the contractor within 90 days from your last day, stating the amount and who you worked for, by certified mail (§ 37-12-2)None beyond the suitMay sue after 90 days unpaid; not after two years from your last day, or the bond's longer limit (§ 37-12-5)
MontanaMont. Code Ann. §§ 18-2-204, 18-2-206A supplier of materials to a sub: notice of a right of action on the security to the contractor within 30 days after the first delivery, personally or by certified mail (§ 18-2-206)Written notice of claim filed with the public body within 90 days after completion and its acceptance of the work, in the form the statute gives (§ 18-2-204)No limit in the bond statute itself; ask a Montana attorney which applies
North DakotaN.D. Cent. Code §§ 48-01.2-11, 48-01.2-12Written notice to the contractor within 90 days from your last day, stating the amount and who you worked for, by registered mail (§ 48-01.2-11)None beyond the suitMay sue after 90 days unpaid; not after one year from completion and acceptance of the project (§ 48-01.2-12). Bonds are required over $250,000
South CarolinaS.C. Code § 11-35-3030(2)A remote claimant: written notice to the contractor within 90 days from your last day, personally or by registered or certified mail (§ 11-35-3030(2)(c)); a notice of furnishing sent earlier keeps the claim from being capped at what the contractor owes your customerNone beyond the suitMay sue after 90 days unpaid; within one year from your last day (§ 11-35-3030(2)(c), (d)). State Procurement Code jobs; a local body with its own code may differ
South DakotaS.D. Codified Laws § 5-21-6None in the statuteAn affidavit of nonpayment to the public body, for a certified copy of the contract and bondIn the public body's name, not until six months after complete performance and final settlement of the contract, then within one year; one action, which others join within a year of completion
AlaskaAS 36.25.010, 36.25.020Written notice to the contractor within 90 days from your last day, stating the amount and who you worked for, by registered mail or served like a summons (AS 36.25.020(b))None beyond the suitMay sue after 90 days unpaid; in the name of the state or political subdivision, not after one year from final settlement of the contract (AS 36.25.020(c)). Bonds are required over $100,000 and cover half the contract up to $1,000,000, 40% up to $5,000,000, then $2,500,000
WyomingW.S. 16-6-112 to 16-6-117None in the statuteNone before the suit; on suing, notice of the action to the public entity named in the bond (W.S. 16-6-113)Within one year after the date of final completion, which the public entity posts on its website or the state procurement site (W.S. 16-6-115, 16-6-116(a)(iv)). Bonds are required over $150,000

This table summarises each statute's text only. Court rulings, the bond's own terms, how the state reads "subcontractor" (who is too remote to claim) and other statutes can change the answer, and a city or authority job's bond may rest on a different law than the state's: read the bond itself. Ask the public body or the prime for a copy; Arizona and the federal Act give you a right to a certified copy on request.

What trips subs up

Common questions

What is a little Miller Act?

A state law that requires a payment bond on state and local public construction, because public property cannot be liened. Subcontractors and suppliers who are not paid claim on that bond instead, and each state sets its own notice periods and suit limits.

How long do I have to make a bond claim on a state public job?

It depends on the state and on who you contracted with. In the statutes this page read, a sub of a sub must notify the contractor within 65 days in Massachusetts, within 90 days in Virginia, Arizona, Michigan, Nevada, Idaho, Maryland, Maine, Rhode Island, South Carolina, North Dakota and Alaska, within four months in Nebraska (and a remote material supplier in Missouri), within 120 days in New York and North Carolina, and by the 15th day of the second month after each unpaid month in Texas. In Minnesota (120 days) and Oregon (180 days) everyone gives a notice, first-tier subs included. Washington, Ohio, Iowa and Montana count from the public body's acceptance of the work instead (Iowa: the sworn claim within 30 days, the action by day 60; Montana: everyone's notice to the public body within 90 days), Louisiana from the day that acceptance is recorded in the parish mortgage records (the sworn statement within 45 days, suit within a year), Colorado from the final settlement date it publishes, and Utah asks every subcontractor for a preliminary notice to the state registry within 20 days of starting.

Do I need to send a notice if I contracted directly with the prime contractor?

In Virginia, Arizona, North Carolina, New York, Florida, Massachusetts, Michigan, Nevada, Idaho, Maryland, Maine, Nebraska, Rhode Island, South Carolina, North Dakota, Alaska and Missouri the notice to the contractor is required only from claimants who are not in contract with it; a first-tier sub still has to sue within the limit. Texas, Washington, Ohio, Minnesota, Oregon, Utah, Iowa, Colorado, Louisiana and Montana require a notice, statement or registry filing from everyone. Kansas, Delaware and South Dakota ask for no notice at all, only a suit within the limit; Wyoming asks none before the suit, then notice of the suit to the public entity.

Bond claim dates on every public job

PayApps is hosted pay-app billing for specialty subcontractors. Mark a job as a state or local public job and it lists that state's bond claim steps for the thirty-one states above, dated from your last day on the job and the public body's acceptance, next to the state's retainage cap, and the cash page and weekly email name the next step 45 days before it is due while money is still owed; a federal job gets the Miller Act dates and a draft notice. The unpaid balance is already on file from your pay applications. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.