What makes glazing billing different
| Situation | What the GC usually wants | How to bill it | Free guide or tool |
|---|---|---|---|
| Several elevations and systems | Percent complete per elevation and per system | Split the SOV by elevation or area and by system (curtain wall, storefront, windows, entrances, interior glass), so the percent can be checked from the building | Free Excel SOV template |
| Engineering, calculations and shop drawings | Approved drawings and calculations before fabrication | Give them a small line of their own, billed when approved, not when sent | Front-loading check |
| Frames and glass fabricated or stored off site | Stored materials off site only if the subcontract allows it, with invoices, photos and often a bill of sale and insurance | Bill what is fabricated and allowed as stored, and move it to work completed as it is set, so it is billed once | Billing stored materials |
| The mockup and field water tests | Their own lines, done and passed before the walls go up | Bill the mockup when it is built and each test when it is done; a retest caused by others is a change order | Change orders and the SOV |
| Openings not ready, or glass broken by others | A signed ticket or a written delay notice, not a verbal OK | Write a T&M ticket for return trips and replaced lites, with photos, and get it signed | T&M ticket log |
| Punch, cleaning and the warranty | Items accepted and warranties handed over before final retainage | Keep the punch list and send the warranty with the close-out documents | Getting retainage released |
An example glazing schedule of values
An example with made-up lines, to show the shape; your subcontract sets the lines.
| Line | Example description | Unit | How it is billed |
|---|---|---|---|
| 1 | Engineering, calculations and shop drawings | LS | When approved |
| 2 | Mockup and testing | LS | When built and passed |
| 3 | Curtain wall, east and south: material | LS | As stored materials while fabricated, if allowed |
| 4 | Curtain wall, east and south: install | LS | Percent set and glazed |
| 5 | Storefront and entrances, level 1 | LS | Percent installed |
| 6 | Windows, levels 2 to 4 | LS or EA | Percent installed, or units set |
| 7 | Interior glass and mirrors | LS | Percent installed |
| 8 | Cleaning, punch and warranty | LS | When accepted and the warranty is handed over |
Where glazing subs lose money on pay apps
- Fabricated units in a yard, not on the bill. Framing and glass made to order are cash spent months ahead. If the subcontract allows off-site stored materials, bill them with the backup it asks for, or ask for that right before you sign.
- Return trips for openings not ready. A crew sent home because the opening is not ready is a cost someone owes. A ticket or a written notice the same day is the record.
- Retests nobody priced. A water test that fails because of another trade's flashing is retested at someone's cost. Ask for a change order before the retest.
- A broken lite replaced for free. Glass broken after it is set is replaced by someone. Photograph it and get a ticket signed before ordering the new lite.
Common questions
How should a glazing contractor set up the schedule of values?
By elevation or area and by system (curtain wall, storefront, windows, entrances, interior glass), with engineering, the mockup and testing on lines of their own, and material split from install where the subcontract allows stored materials.
Can I bill for curtain wall or glass stored at the fabricator?
Only if your subcontract allows stored materials off site. Expect to show invoices and photos, and often a bill of sale, insurance on the stored goods and a right for the GC to inspect them. Move them to work completed as they are set, so they are billed once.
Should the mockup and water testing be their own lines?
Yes, when the specifications ask for them: they are real work billed when done and passed, and separate lines keep them from being argued into the wall price. A retest caused by another trade is a change order.
Why is my final glazing retainage held?
Often because close-out is not complete: the punch list, final cleaning, the warranties or a final lien waiver. Ask the GC in writing which items are open, and send them together.
Glazing pay apps that carry fabricated material until it is set
PayApps is hosted pay-app billing for specialty subcontractors. It carries stored materials per line from one application to the next, so fabricated units are billed once, sends each submittal under a transmittal with its needed-on-site date and lead time, logs T&M tickets with photos for return trips and broken glass, and keeps the close-out checklist and punch list the last retainage waits on. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.