What makes fire sprinkler billing different
| Situation | What the GC usually wants | How to bill it | Free guide or tool |
|---|---|---|---|
| Design, hydraulic calculations and the permit | Drawings and calculations approved by the AHJ before pipe goes up | A small line of its own, billed when approved, not when submitted | Front-loading check |
| Pipe, fittings, heads and the riser bought early | Proof of delivery and where it is stored: invoices, delivery tickets, photos, and off site only if the subcontract allows it | Bill it as stored materials, and move it to work completed as it is installed, so it is billed once | Billing stored materials |
| Mains and branch lines months before heads | Percent complete per floor or area that can be checked by walking it | Split rough-in from trim: mains and branch lines by area, then heads and drops once the ceiling grid is in | Free Excel SOV template |
| The hydrostatic test and the AHJ's rough inspection | A passed test witnessed where the AHJ requires it, and the signed Contractor's Material and Test Certificate | Bill testing on its own line when passed; a retest after another trade cuts or hits the pipe is a T&M ticket | T&M ticket log |
| Heads moved for ceiling, light and duct changes | A signed ticket or change order before the work, not a verbal OK in the field | Write up relocated heads and added drops the day they are done and turn signed tickets into change order requests | Change orders and the SOV |
| Final acceptance and close-out | The AHJ's final, test certificates, as-builts, manuals and spare heads before the last retainage | Keep the close-out list per job and send the package with the retainage release request | Getting retainage released |
The test pressure above is what many local certificate forms state (for example Philadelphia's Contractor's Material and Test Certificate for Aboveground Piping); the edition of NFPA 13 your AHJ has adopted and its own form are what count.
An example fire sprinkler schedule of values
An example with made-up lines, to show the shape; your subcontract sets the lines, and scopes such as the underground, the fire pump or the standpipes may belong to someone else.
| Line | Example description | Unit | How it is billed |
|---|---|---|---|
| 1 | Design, hydraulic calculations and permit | LS | When approved by the AHJ |
| 2 | Underground fire line (where in scope) | LS or LF | Percent installed, then flushed and tested |
| 3 | Riser, backflow and valves: material | LS | As stored materials until set, if allowed |
| 4 | Riser, backflow and valves: install | LS | Percent installed |
| 5 to 8 | Mains and branch lines by floor or area | LS | Percent installed (rough-in) |
| 9 to 12 | Heads and drops by floor or area | LS or EA | Percent set after the ceiling grid, or heads set |
| 13 | Fire pump and standpipes (where in scope) | LS | Percent installed, then the acceptance test |
| 14 | Hydrostatic testing and inspections | LS | When passed |
| 15 | Final acceptance, as-builts and close-out | LS | When accepted and the close-out package is handed over |
Where fire sprinkler subs lose money on pay apps
- Pipe and heads in the shop, not on the bill. Material bought for a long job is cash spent months ahead. If the subcontract allows stored materials, bill them with the backup it asks for, or ask for that right before you sign.
- Heads moved for free. Ceiling, light and duct changes move heads late in the job. A head relocated on a verbal OK is the extra most often never paid; a ticket signed the same day is the record.
- Retests nobody priced. Pipe cut, hit or left open by another trade means another test in front of the inspector. Photograph it and get a ticket signed before the retest.
- Painted or damaged heads. A head painted over or knocked by another trade has to be replaced, not cleaned. Write it up with photos as a back charge to whoever caused it, rather than swapping it at your cost.
- Retainage waiting on someone else's inspection. The last money often waits for the fire marshal, the fire alarm tie-in or another trade's punch. Track the retainage per job and ask in writing what is still open.
Common questions
How should a fire sprinkler contractor set up the schedule of values?
By building, floor or area and by phase: design and permit, underground, mains and branch lines (rough-in), heads and drops after the ceiling (trim), the riser, fire pump and standpipes where they are in your scope, then testing, acceptance and close-out on lines of their own. Small lines let the GC check each month's percent from the floor.
Can I bill for design and hydraulic calculations before any pipe is installed?
Usually, if design is in your scope and has its own line: bill it when the drawings and calculations are approved by the AHJ, not when they are sent. Keep the line modest; a large design line is the first thing a reviewer reads as front-loading.
When do I bill the hydrostatic test?
When it is done and passed, ideally on a testing line of its own. Many jurisdictions' forms for the Contractor's Material and Test Certificate (for example Philadelphia's) state the aboveground test as at least 200 psi for two hours, or 50 psi above static pressure where that is higher; a retest caused by another trade's damage is extra work on a signed ticket.
Why is my final sprinkler retainage held?
Usually because acceptance or close-out is not complete: the AHJ's final inspection, the signed test certificates, as-builts, the owner's manuals and spare heads, or a final lien waiver. Ask the GC in writing which items are open and send them together.
Sprinkler pay apps that carry stored pipe until it is installed
PayApps is hosted pay-app billing for specialty subcontractors. It carries stored materials per line from one application to the next, so pipe and heads are billed once, keeps the submittal log with each needed-on-site date and lead time, logs T&M tickets with photos for relocated heads and retests, prints the weekly WH-347 certified payroll on public jobs, and keeps the close-out checklist and punch list the last retainage waits on. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.