Pay applications for fire sprinkler and fire protection: design, rough-in, the hydro test and the AHJ's acceptance

Fire sprinkler pay applications bill work that has to pass someone other than the GC: the layout is approved by the authority having jurisdiction (AHJ) before pipe goes up, the piping is pressure tested in front of an inspector, and the last money usually waits for the fire marshal's final acceptance. Heads are set months after the mains, once the ceiling grid is in. This page covers each step, with the free guide or tool for it.

What makes fire sprinkler billing different

SituationWhat the GC usually wantsHow to bill itFree guide or tool
Design, hydraulic calculations and the permitDrawings and calculations approved by the AHJ before pipe goes upA small line of its own, billed when approved, not when submittedFront-loading check
Pipe, fittings, heads and the riser bought earlyProof of delivery and where it is stored: invoices, delivery tickets, photos, and off site only if the subcontract allows itBill it as stored materials, and move it to work completed as it is installed, so it is billed onceBilling stored materials
Mains and branch lines months before headsPercent complete per floor or area that can be checked by walking itSplit rough-in from trim: mains and branch lines by area, then heads and drops once the ceiling grid is inFree Excel SOV template
The hydrostatic test and the AHJ's rough inspectionA passed test witnessed where the AHJ requires it, and the signed Contractor's Material and Test CertificateBill testing on its own line when passed; a retest after another trade cuts or hits the pipe is a T&M ticketT&M ticket log
Heads moved for ceiling, light and duct changesA signed ticket or change order before the work, not a verbal OK in the fieldWrite up relocated heads and added drops the day they are done and turn signed tickets into change order requestsChange orders and the SOV
Final acceptance and close-outThe AHJ's final, test certificates, as-builts, manuals and spare heads before the last retainageKeep the close-out list per job and send the package with the retainage release requestGetting retainage released

The test pressure above is what many local certificate forms state (for example Philadelphia's Contractor's Material and Test Certificate for Aboveground Piping); the edition of NFPA 13 your AHJ has adopted and its own form are what count.

An example fire sprinkler schedule of values

An example with made-up lines, to show the shape; your subcontract sets the lines, and scopes such as the underground, the fire pump or the standpipes may belong to someone else.

LineExample descriptionUnitHow it is billed
1Design, hydraulic calculations and permitLSWhen approved by the AHJ
2Underground fire line (where in scope)LS or LFPercent installed, then flushed and tested
3Riser, backflow and valves: materialLSAs stored materials until set, if allowed
4Riser, backflow and valves: installLSPercent installed
5 to 8Mains and branch lines by floor or areaLSPercent installed (rough-in)
9 to 12Heads and drops by floor or areaLS or EAPercent set after the ceiling grid, or heads set
13Fire pump and standpipes (where in scope)LSPercent installed, then the acceptance test
14Hydrostatic testing and inspectionsLSWhen passed
15Final acceptance, as-builts and close-outLSWhen accepted and the close-out package is handed over

Where fire sprinkler subs lose money on pay apps

Common questions

How should a fire sprinkler contractor set up the schedule of values?

By building, floor or area and by phase: design and permit, underground, mains and branch lines (rough-in), heads and drops after the ceiling (trim), the riser, fire pump and standpipes where they are in your scope, then testing, acceptance and close-out on lines of their own. Small lines let the GC check each month's percent from the floor.

Can I bill for design and hydraulic calculations before any pipe is installed?

Usually, if design is in your scope and has its own line: bill it when the drawings and calculations are approved by the AHJ, not when they are sent. Keep the line modest; a large design line is the first thing a reviewer reads as front-loading.

When do I bill the hydrostatic test?

When it is done and passed, ideally on a testing line of its own. Many jurisdictions' forms for the Contractor's Material and Test Certificate (for example Philadelphia's) state the aboveground test as at least 200 psi for two hours, or 50 psi above static pressure where that is higher; a retest caused by another trade's damage is extra work on a signed ticket.

Why is my final sprinkler retainage held?

Usually because acceptance or close-out is not complete: the AHJ's final inspection, the signed test certificates, as-builts, the owner's manuals and spare heads, or a final lien waiver. Ask the GC in writing which items are open and send them together.

Sprinkler pay apps that carry stored pipe until it is installed

PayApps is hosted pay-app billing for specialty subcontractors. It carries stored materials per line from one application to the next, so pipe and heads are billed once, keeps the submittal log with each needed-on-site date and lead time, logs T&M tickets with photos for relocated heads and retests, prints the weekly WH-347 certified payroll on public jobs, and keeps the close-out checklist and punch list the last retainage waits on. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.