Prompt payment laws for subcontractors: how long the GC has to pay you

Most states have a prompt payment law that sets how fast a general contractor must pass the owner's payment down to the subcontractor who did the work, and many add interest when it is late. The clock usually starts when the GC receives the owner's payment, not when you send your pay application, so the first thing to find out each month is when the owner paid.

Deadlines and interest in 7 states

Each row was read from the state legislature's own published text on 2026-11-25, through search results limited to the official sites (the pages could not be opened directly from where this was written). Where that text did not show a figure, the row says so rather than repeating a number from elsewhere. These laws have exceptions, and many let the contract set different terms. Open the linked statute and read your subcontract before relying on a row. This is a summary, not legal advice.

StateStatuteGC must pay the subInterest when lateNotes
TexasProperty Code ch. 28 (§28.002, §28.004)Within 7 days after receiving the owner's payment1½% each month, from the day after the due datePrivate work. The owner has 35 days from a written payment request. A sub can suspend work 10 days after written notice of nonpayment (§28.009). Lower-tier subs: the same 7 days.
CaliforniaBusiness and Professions Code §7108.5Within 7 days after receiving each progress payment, unless agreed otherwise in writingNot confirmed in the current text we could read. Earlier versions set a 2% a month penalty; check the section.Private and most public work. In a good-faith dispute the GC may hold back no more than 150% of the disputed amount. The prevailing party gets attorney's fees.
IllinoisContractor Prompt Payment Act, 815 ILCS 603Within 15 calendar days after the contractor receives payment10% a yearPrivate work. A sub can suspend work after 7 days' written notice. Public local work has its own act (50 ILCS 505).
North CarolinaG.S. ch. 22C (22C-2, 22C-5)Within 7 days after receiving each periodic or final payment1% a month or fraction of a month, from the 8th dayPayment is owed once you have performed under your contract. 2025 House Bill 383 would add a 30-day outer limit; check whether it passed.
PennsylvaniaContractor and Subcontractor Payment Act (1994 Act 7)14 days after the contractor receives payment, or 14 days after your invoice, whichever is later (2018 amendment)At the rate in section 5(d) of the Act; we could not confirm the figure from the text readPrivate work. Retainage is due to you within 14 days of the contractor receiving it. Public work is under 62 Pa.C.S. ch. 39.
VirginiaCode of Virginia §2.2-4354Interest runs on amounts still unpaid 7 days after the contractor is paid by the public body1% a month unless the contract says otherwisePublic work. Withholding needs written notice with the reason. Private work has a parallel rule in Title 11.
FloridaFlorida Statutes §218.735(6) (local government); §713.346 (private)Local government work: within 10 days after the contractor receives payment. Private work: no fixed day count; unpaid undisputed amounts trigger a remedy after 30 daysNot confirmed in the text we readLower-tier subs on local government work: 7 days. Under §713.346, knowingly failing to pay is misapplication of construction funds, and the prevailing party recovers attorney's fees.

Not listed: Georgia, New York, Massachusetts and other states with prompt payment rules. We could not read their current official text from here, so they are left out rather than filled in from memory.

Late payment interest calculator

Pick a state to fill in its deadline and rate, or type your contract's own terms.

Simple interest, no compounding. A month is counted as 30 days and a year as 365: the statutes we read do not define them, and a court or your contract may count differently. The worked example (Texas, $40,000, owner paid 1 March, you were paid 22 April) is 45 days late and comes to $900.00 of interest. Your numbers stay in this browser tab.

What to do when a GC pays late

Follow-up emails to send a GC about a late pay application

Three short drafts to copy and edit. Each names the pay application, the amount and the date, asks one clear question, and offers to fix whatever is holding the payment. None threatens a lien or quotes a statute: add that only after you have checked your notice and lien deadlines. Send them to the person who processes pay applications at the GC (accounts payable or the project accountant), not only the project manager.

Past due: a reminder

Subject: Past due: [job name], pay application #[n], $[amount]

Hello [name],

Our pay application #[n] on [job name] (dated [date], for work through [period end]) for $[amount] has not been paid yet. Under our subcontract's pay terms ([terms]) it was due on [due date].

Could you tell me when we can expect payment? If something is holding it up (a lien waiver, backup, or a question on a line), let me know and I will get it to you right away.

Thank you,
[your name]
[your company]

More than 30 days past due: a second request

Subject: Second request: [job name], pay application #[n], $[amount] past due

Hello [name],

I am following up again on our pay application #[n] on [job name] (dated [date], for work through [period end]) for $[amount], which is still unpaid [days] days after the application date.

Please reply with the date the payment will be released, or tell me what is needed to release it. If there is a problem with the application, I would rather fix it this week than let it wait another cycle.

Thank you,
[your name]
[your company]

Paid short: ask what the balance is held for

Subject: Balance on [job name], pay application #[n]: $[balance]

Hello [name],

Thank you for the $[received] received against our pay application #[n] on [job name]. The application was for $[billed], which leaves $[balance] unpaid.

Could you tell me what the balance is held for? If it is a backcharge, please send the backup for it; if it is waiting on a lien waiver or other paperwork, tell me what you need; and if it was missed, please let me know when it will be paid.

Thank you,
[your name]
[your company]

Work out the balance first with the paid-short reconciler, and the due date with the cash forecast. These are drafts, not legal advice: if the money is large or the GC has gone quiet, talk to a construction attorney before a deadline passes.

Common questions

How many days does a GC have to pay a subcontractor?

It depends on the state and often on the contract. In the statutes this page read, Texas, California and North Carolina give the GC 7 days after it receives the owner's payment, Illinois 15 calendar days, and Pennsylvania 14 days after the contractor is paid or after your invoice, whichever is later.

Does prompt payment interest stop my lien deadline?

No. Prompt payment interest does not stop the clock on mechanics lien or bond claim deadlines, so watch those dates at the same time.

What should I do first when a GC pays late?

Find out when the owner paid, since the deadline counts from that date, then put it in writing: name the pay application, the amount, the statute and the interest so far. Several of these laws make suspending work or claiming interest depend on written notice.

Know the day every payment is due

PayApps is hosted pay-app billing for specialty subcontractors that keeps every pay application, retainage balance and lien waiver per job, so you can see what is owed and how long it has been outstanding. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.