The forms on this page
| Form | Use it for | Statute |
|---|---|---|
| Conditional Waiver and Release on Progress Payment | conditional progress waivers | Cal. Civ. Code § 8132 |
| Unconditional Waiver and Release on Progress Payment | unconditional progress waivers | Cal. Civ. Code § 8134 |
| Conditional Waiver and Release on Final Payment | conditional final waivers | Cal. Civ. Code § 8136 |
| Unconditional Waiver and Release on Final Payment | unconditional final waivers | Cal. Civ. Code § 8138 |
Each form is the statute's text as read on 2026-11-25, from the official source linked with it. The grey caption under each blank says what goes there; it is our guide, not part of the form. Statutes change: open the linked section before relying on a form, and have a California construction attorney review anything you are unsure of.
What California asks of you
- A waiver given for a payment is "null, void, and unenforceable unless it is in substantially the following form", one form per kind: conditional progress (§ 8132), unconditional progress (§ 8134), conditional final (§ 8136) and unconditional final (§ 8138).
- Watch the change-order sentence. Every form waives rights for work done "pursuant to a written change order that has been fully executed by the parties prior to the date that this document is signed by the claimant ... unless listed as an Exception below". If a signed change order is still unpaid, list it.
- The progress forms do not affect "Retentions", "Extras for which the claimant has not received payment" or your contract rights. The conditional progress form also lists earlier conditional waivers you gave "but has not received payment", with their dates and amounts.
- The final forms have one exception: "Disputed claims for extras in the amount of" a sum you fill in.
- The unconditional forms carry a "Notice to Claimant" that must be "in at least as large a type as the largest type otherwise in the form": "THIS DOCUMENT IS ENFORCEABLE AGAINST YOU IF YOU SIGN IT, EVEN IF YOU HAVE NOT BEEN PAID."
- A conditional waiver releases the owner, lender or bond surety only with evidence of payment: your endorsement on a check that has been paid, or your written acknowledgment of payment (§ 8124). No contract term can waive your rights unless you sign one of these waivers (§ 8122), and a statement giving them up is void unless it is one of these waivers or you have been paid in full (§ 8126).
Notes on the forms
- California: a waiver and release given for a payment is null, void, and unenforceable unless it is in substantially the form of Cal. Civ. Code § 8132, 8134, 8136 or 8138, and it releases the owner, construction lender or payment-bond surety only if it is signed by the claimant (§ 8124(a)).
- California: a conditional release also needs evidence of payment before it releases them: the claimant's endorsement on a single or joint payee check that has been paid by the financial institution on which it was drawn, or the claimant's written acknowledgment of payment (§ 8124(b)).
- California's unconditional forms say they are enforceable against the claimant "even if you have not been paid" (§§ 8134, 8138): use them only once the payment has been received.
- California's final forms list one exception, disputed claims for extras in a stated amount (§§ 8136, 8138); the progress forms except retentions, unpaid extras and contract rights.
Conditional Waiver and Release on Progress Payment
Use it for: conditional progress waivers. From Cal. Civ. Code § 8132, read 2026-11-25.
CONDITIONAL WAIVER AND RELEASE ON PROGRESS PAYMENT
NOTICE: THIS DOCUMENT WAIVES THE CLAIMANT’S LIEN, STOP PAYMENT NOTICE, AND PAYMENT BOND RIGHTS EFFECTIVE ON RECEIPT OF PAYMENT. A PERSON SHOULD NOT RELY ON THIS DOCUMENT UNLESS SATISFIED THAT THE CLAIMANT HAS RECEIVED PAYMENT.
Identifying Information
Name of Claimant: Name of Claimant
Name of Customer: Name of Customer
Job Location: Job Location
Owner: Owner
Through Date: Through Date
Conditional Waiver and Release
This document waives and releases lien, stop payment notice, and payment bond rights the claimant has for labor and service provided, and equipment and material delivered, to the customer on this job through the Through Date of this document. Rights based upon labor or service provided, or equipment or material delivered, pursuant to a written change order that has been fully executed by the parties prior to the date that this document is signed by the claimant, are waived and released by this document, unless listed as an Exception below. This document is effective only on the claimant’s receipt of payment from the financial institution on which the following check is drawn:
Maker of Check: Maker of Check
Amount of Check: Amount of Check
Check Payable to: Check Payable to
Exceptions
This document does not affect any of the following:
(1) Retentions.
(2) Extras for which the claimant has not received payment.
(3) The following progress payments for which the claimant has previously given a conditional waiver and release but has not received payment:
Date(s) of waiver and release: Date(s) of waiver and release
Amount(s) of unpaid progress payment(s): Amount(s) of unpaid progress payment(s)
(4) Contract rights, including (A) a right based on rescission, abandonment, or breach of contract, and (B) the right to recover compensation for work not compensated by the payment.
Signature
Claimant’s Signature: sign here
Claimant’s Title: Claimant’s Title
Date of Signature: Date of Signature
Unconditional Waiver and Release on Progress Payment
Use it for: unconditional progress waivers. From Cal. Civ. Code § 8134, read 2026-11-25.
UNCONDITIONAL WAIVER AND RELEASE ON PROGRESS PAYMENT
NOTICE TO CLAIMANT: THIS DOCUMENT WAIVES AND RELEASES LIEN, STOP PAYMENT NOTICE, AND PAYMENT BOND RIGHTS UNCONDITIONALLY AND STATES THAT YOU HAVE BEEN PAID FOR GIVING UP THOSE RIGHTS. THIS DOCUMENT IS ENFORCEABLE AGAINST YOU IF YOU SIGN IT, EVEN IF YOU HAVE NOT BEEN PAID. IF YOU HAVE NOT BEEN PAID, USE A CONDITIONAL WAIVER AND RELEASE FORM.
Identifying Information
Name of Claimant: Name of Claimant
Name of Customer: Name of Customer
Job Location: Job Location
Owner: Owner
Through Date: Through Date
Unconditional Waiver and Release
This document waives and releases lien, stop payment notice, and payment bond rights the claimant has for labor and service provided, and equipment and material delivered, to the customer on this job through the Through Date of this document. Rights based upon labor or service provided, or equipment or material delivered, pursuant to a written change order that has been fully executed by the parties prior to the date that this document is signed by the claimant, are waived and released by this document, unless listed as an Exception below. The claimant has received the following progress payment: Progress payment received
Exceptions
This document does not affect any of the following:
(1) Retentions.
(2) Extras for which the claimant has not received payment.
(3) Contract rights, including (A) a right based on rescission, abandonment, or breach of contract, and (B) the right to recover compensation for work not compensated by the payment.
Signature
Claimant’s Signature: sign here
Claimant’s Title: Claimant’s Title
Date of Signature: Date of Signature
Conditional Waiver and Release on Final Payment
Use it for: conditional final waivers. From Cal. Civ. Code § 8136, read 2026-11-25.
CONDITIONAL WAIVER AND RELEASE ON FINAL PAYMENT
NOTICE: THIS DOCUMENT WAIVES THE CLAIMANT’S LIEN, STOP PAYMENT NOTICE, AND PAYMENT BOND RIGHTS EFFECTIVE ON RECEIPT OF PAYMENT. A PERSON SHOULD NOT RELY ON THIS DOCUMENT UNLESS SATISFIED THAT THE CLAIMANT HAS RECEIVED PAYMENT.
Identifying Information
Name of Claimant: Name of Claimant
Name of Customer: Name of Customer
Job Location: Job Location
Owner: Owner
Conditional Waiver and Release
This document waives and releases lien, stop payment notice, and payment bond rights the claimant has for labor and service provided, and equipment and material delivered, to the customer on this job. Rights based upon labor or service provided, or equipment or material delivered, pursuant to a written change order that has been fully executed by the parties prior to the date that this document is signed by the claimant, are waived and released by this document, unless listed as an Exception below. This document is effective only on the claimant’s receipt of payment from the financial institution on which the following check is drawn:
Maker of Check: Maker of Check
Amount of Check: Amount of Check
Check Payable to: Check Payable to
Exceptions
This document does not affect any of the following:
Disputed claims for extras in the amount of: Disputed claims for extras in the amount of
Signature
Claimant’s Signature: sign here
Claimant’s Title: Claimant’s Title
Date of Signature: Date of Signature
Unconditional Waiver and Release on Final Payment
Use it for: unconditional final waivers. From Cal. Civ. Code § 8138, read 2026-11-25.
UNCONDITIONAL WAIVER AND RELEASE ON FINAL PAYMENT
NOTICE TO CLAIMANT: THIS DOCUMENT WAIVES AND RELEASES LIEN, STOP PAYMENT NOTICE, AND PAYMENT BOND RIGHTS UNCONDITIONALLY AND STATES THAT YOU HAVE BEEN PAID FOR GIVING UP THOSE RIGHTS. THIS DOCUMENT IS ENFORCEABLE AGAINST YOU IF YOU SIGN IT, EVEN IF YOU HAVE NOT BEEN PAID. IF YOU HAVE NOT BEEN PAID, USE A CONDITIONAL WAIVER AND RELEASE FORM.
Identifying Information
Name of Claimant: Name of Claimant
Name of Customer: Name of Customer
Job Location: Job Location
Owner: Owner
Unconditional Waiver and Release
This document waives and releases lien, stop payment notice, and payment bond rights the claimant has for all labor and service provided, and equipment and material delivered, to the customer on this job. Rights based upon labor or service provided, or equipment or material delivered, pursuant to a written change order that has been fully executed by the parties prior to the date that this document is signed by the claimant, are waived and released by this document, unless listed as an Exception below. The claimant has been paid in full.
Exceptions
This document does not affect the following:
Disputed claims for extras in the amount of: Disputed claims for extras in the amount of
Signature
Claimant’s Signature: sign here
Claimant’s Title: Claimant’s Title
Date of Signature: Date of Signature
Common questions
Does California have a statutory lien waiver form?
Yes. Civ. Code §§ 8132–8138 sets 4 forms: conditional and unconditional, progress and final. How strict: "Null, void, and unenforceable unless it is in substantially the following form". The forms on this page are printed word for word from the statute as read on 2026-11-25.
Which California lien waiver form goes with which payment?
Conditional Waiver and Release on Progress Payment: conditional progress waivers. Unconditional Waiver and Release on Progress Payment: unconditional progress waivers. Conditional Waiver and Release on Final Payment: conditional final waivers. Unconditional Waiver and Release on Final Payment: unconditional final waivers.
When should I sign an unconditional lien waiver in California?
Only once the payment it covers has cleared your bank. Before that, give the conditional form if California has one, and keep retainage, unapproved change orders and disputed amounts out of a progress waiver. This page is not legal advice; ask a California construction attorney before signing anything you are unsure of.
Fill these in from your pay app instead
PayApps is hosted pay-app billing for specialty subcontractors that prints California's statutory waiver with each pay application, filled in from the job and the amount due, and holds the unconditional one until the payment has cleared. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.