Pay app guides · schedule of values calculator

Why pay applications get sent back, and a checker

A pay application that comes back for corrections usually misses that month's payment cycle, and the GC's reviewer rarely says everything that is wrong the first time. Most of what they mark is not arithmetic inside the new application; it is the new application disagreeing with last month's approved one. A spreadsheet cannot see that. This page lists what a reviewer compares and checks your draft against last month's application line by line.

What a reviewer compares with last month

These are the consistency rules of the continuation sheet itself, the same ones the column-by-column guide explains. Your subcontract and the GC's own instructions can add more (a notarized summary, a particular waiver form, a cut-off date).

CheckThe ruleHow it goes wrong
From previous applicationsOn each line, last month's "from previous" plus last month's "this period", as approved.The new sheet is copied from last month's submitted file, not the one the GC approved after cutting a line back.
Scheduled valuesFixed once the schedule of values is approved. Changes come in as change order lines.A line's value is edited to absorb extra work, or money is moved between lines to bill ahead.
LinesEvery line stays, in the same order and numbering, until closeout; new lines are change orders.A finished line is deleted, or a new base-contract line appears with no change order behind it.
Previous certificatesLast month's total earned less retainage (the amount certified to date).It is typed as what was paid, or the last payment alone, so this month's payment due is wrong.
Stored materialsThey leave the stored column when installed, and come back as work completed on the same line.Stored goes down but the work billed is smaller, so materials vanish from the sheet or are billed twice.
RetainageThe subcontract rate, unless a reduction was agreed in writing; released retainage only goes up.A rate drops without paperwork, or release is entered as this month's amount instead of to date.

Check this month's draft against last month

Paste each schedule of values with its header row: CSV or straight from a spreadsheet (tab separated). The columns it needs are item, scheduled value, from previous applications, this period, and optionally description and materials presently stored; the calculator's Download CSV works as it is. Lines are matched by item number. Your numbers stay in this browser tab.

Current payment due on this draft
Previous certificates should be (last month's earned less retainage)

The example has four planted mistakes: a scheduled value raised on item 2, a new item 5 that is not numbered as a change order, switchgear stored materials that dropped by more than was billed as installed, and previous certificates typed as last month's payment rather than the total certified. This is a worksheet check, not an approval: the GC, its contract and the owner's architect decide what is payable.

Before you send it

Common questions

Why do pay applications get sent back?

Most often because this month's sheet does not match last month's approved one: a "from previous" column copied from the submitted file instead of the approved one, an edited scheduled value, a new line with no change order behind it, previous certificates typed as last month's payment, or stored materials that vanish or are billed twice.

What goes in previous certificates for payment?

Last month's total earned less retainage, which is the amount certified to date. Typing it as what was paid, or as the last payment alone, makes this month's payment due wrong.

Can I change a scheduled value on a pay application?

Not once the schedule of values is approved. Changes come in as change order lines, and every line stays in the same order and numbering until closeout.

Pay apps that roll themselves forward

PayApps is hosted pay-app billing for specialty subcontractors: each month's application starts from last month's approved one, change orders flow onto the schedule of values when signed, and retainage and lien waivers are tracked per job. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.