A pay-when-paid clause says when the general contractor pays you: so many days after the owner pays the GC. A pay-if-paid clause says whether: the owner's payment is a condition of you being paid at all, so if the owner never pays, the GC argues it never owes you. The words decide which one you signed, and your state decides whether a pay-if-paid clause holds. Paste the clause below to see both.

Clause reader

Paste the payment clause from your subcontract (usually titled "Payment", "Progress payments" or "Final payment"). It runs in this browser tab; nothing is uploaded.

    What to ask

      The reader looks for the wording courts have pointed to (a "condition precedent", "if and only if", a named risk of the owner not paying, the owner's payment as the "sole source", or a number of days after receipt). It does not read the rest of your subcontract, and a court reads the contract as a whole. Treat its answer as a starting point for a conversation with the GC or a construction attorney, not as a legal opinion.

      How 11 states treat a pay-if-paid clause

      Each row was read on 2026-11-25 from the state legislature's own published statute, or from the court opinion on Justia, through search results limited to those sites (the pages could not be opened directly from where this was written). Statutes and case law change; a later court may have narrowed an older decision. Open the link before relying on a row. This is a summary, not legal advice.

      StateSourceEffect on pay-if-paidWhat it says
      CaliforniaWm. R. Clarke Corp. v. Safeco Ins. Co. (1997) 15 Cal.4th 882 (case law)Pay-if-paid unenforceableThe California Supreme Court held pay-if-paid provisions contrary to public policy and unenforceable, because in practice they waive the sub's mechanics lien rights. They do not shield the GC or its payment bond surety.
      FloridaPeacock Construction Co. v. Modern Air Conditioning, 353 So. 2d 840 (Fla. 1977) (case law)Read as timing unless clearA clause tying payment to the owner's payment is read as setting the time for payment, so the GC owes the sub within a reasonable time, unless the contract unambiguously says the sub takes the risk of the owner not paying. The court called the time-for-payment reading the majority rule.
      Illinois770 ILCS 60/21(e), Mechanics Lien Act (added by Public Act 103-0827) (statute)No defense to lien claimsA provision conditioning the contractor's payment to a sub or supplier on receipt of payment from any other party, including a private or public owner, is not a defense to a claim under sections 21, 22, 23 or 28 of the Act. For this section a contractor includes a subcontractor or supplier.
      MarylandMd. Code, Real Property §9-113 (statute)No defense to lien claimsA provision in an executory contract between a contractor and a sub that makes payment depend on the contractor being paid by the owner or a third party cannot take away the sub's mechanics lien right or right to sue on the contractor's bond. A provision made in violation of the section is void as against public policy.
      MissouriRSMo §431.183 (statute)No defense to lien claimsA provision making a contractor's payment to a subcontractor, trade or specialty contractor or supplier contingent on payment from any other private party, including a private owner, is no defense to a claim to enforce a mechanic's lien under chapter 429.
      NevadaNRS 624.624–624.626 (statute)Outside date applies anywayNRS 624.626 gives a lower-tiered sub remedies, including stopping work, when the higher-tiered contractor fails to pay within 45 days after the 25th day of the month in which the sub asked for payment, even if the higher-tiered contractor has not been paid and the agreement says it pays only if or when it is paid. NRS 624.628 voids other listed provisions. Check the current subsection numbers on the chapter page.
      New YorkWest-Fair Electric Contractors v. Aetna Casualty & Surety Co., 87 N.Y.2d 148 (1995) (case law)Pay-if-paid unenforceableA clause making the owner's payment a condition precedent, so the sub bears the risk of the owner not paying, is void and unenforceable as contrary to the public policy in Lien Law §34. A clause that only sets a time for payment is still allowed, and payment on a stated event is read as timing unless the words say otherwise.
      North CarolinaN.C. Gen. Stat. §22C-2 (statute)Pay-if-paid unenforceablePayment by the owner to a contractor is not a condition precedent for payment to a subcontractor, nor is a contractor's payment to one sub a condition for payment to another; an agreement to the contrary is unenforceable. 2025 House Bill 383 would also make pay-when-paid clauses unenforceable and add a 30-day limit; check whether it passed.
      Ohio (federal court applying Ohio law)Thos. J. Dyer Co. v. Bishop International Engineering Co., 303 F.2d 655 (6th Cir. 1962) (case law)Read as timing unless clearA clause saying payment is due five days after the owner pays was read as an unconditional promise to pay, with the time postponed until the owner pays or for a reasonable time if the owner does not. Reading it as an endless wait was an unreasonable construction the parties did not intend. This is a federal court's reading of Ohio law, not an Ohio statute.
      South CarolinaS.C. Code §29-6-230 (statute)Pay-if-paid unenforceablePerformance under its contract entitles a construction sub to payment from the party it contracted with. The owner's payment to the contractor, or the contractor's payment to another sub or supplier, is not a condition precedent for payment to the sub, and an agreement to the contrary is not enforceable.
      WisconsinWis. Stat. §779.135(3) (statute)Condition void; delay allowedIn a contract to improve land in Wisconsin, a provision making payment to the prime contractor by someone who has no contract with the sub a condition precedent to the prime paying the sub is void. The subsection does not stop a provision that delays the sub's payment until the prime is paid.

      Not listed: the other states. We have not read their current rules, so they are left out rather than filled in from memory. Several of them have prompt payment statutes that set deadlines whatever the subcontract says; see prompt payment laws.

      Three kinds of rule

      Before you sign

      Common questions

      What is the difference between pay-if-paid and pay-when-paid?

      Pay-when-paid sets the time for payment: the GC pays after the owner pays, or within a reasonable time. Pay-if-paid makes the owner's payment a condition, so the sub takes the risk of the owner never paying. Courts look for words like "condition precedent" before reading a clause as pay-if-paid.

      Is a pay-if-paid clause enforceable?

      It depends on the state. North Carolina and South Carolina by statute, and California and New York by their highest courts, will not let the owner's payment be a condition of yours. Illinois, Maryland and Missouri say the clause is no defense to a mechanics lien claim. Whether a clause holds on your job is a question for a construction attorney licensed in the project's state.

      What wording should I ask for instead of pay-if-paid?

      Ask for timing wording with an outside date, such as payment within 7 days after the contractor receives payment and in any event within 45 days after the pay application is approved, and strike "condition precedent" and "assumes the risk".

      See which jobs are waiting on the owner

      PayApps is hosted pay-app billing for specialty subcontractors that keeps every pay application, payment date, retainage balance and lien waiver per job, so you can see what is owed, since when, and which lien deadlines are coming. On a pay-when-paid job you record the day the GC says the owner paid, and it counts your subcontract's days from that date instead of guessing; until then the application is listed as waiting on the owner, with a draft email asking the GC whether the owner has paid. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.