What makes flooring billing different
| Situation | What the GC usually wants | How to bill it | Free guide or tool |
|---|---|---|---|
| Several floors and materials | Percent complete per floor or area and per material | Split the SOV by floor and by material (carpet tile, resilient, ceramic and porcelain tile, base), so the percent can be checked on the floor | Free Excel SOV template |
| Slab moisture testing and mitigation | A change order before the work, unless the subcontract already prices it | Record the test results, ask in writing who pays for mitigation, and price it before you apply it | Change orders and the SOV |
| Floor prep: leveling, patching, grinding | The flatness you were promised and a signed ticket for prep beyond it | Measure the slab before you start, write a ticket for prep beyond your scope and get it signed | FF/FL floor flatness calculator |
| Material delivered before the floor is ready | Stored materials with invoices and photos, if the subcontract allows it | Bill it as stored and move it to work completed as it is installed, so it is billed once | Billing stored materials |
| Finished floors damaged by other trades | A signed ticket naming who caused it before the repair | Photograph it, write a T&M ticket and get it signed before replacing tiles or planks | T&M ticket log |
| Attic stock, cleaning and punch | Spare material handed over and items accepted before final retainage | Keep the punch list and a signed hand-over of attic stock with the close-out documents | Punch list tracker |
An example flooring schedule of values
An example with made-up lines, to show the shape; your subcontract sets the lines. Some flooring subcontracts are priced per square yard or square foot; then each line carries a unit and a quantity instead of a percent.
| Line | Example description | Unit | How it is billed |
|---|---|---|---|
| 1 | Mobilization and submittals | LS | Once, or in the parts the subcontract allows |
| 2 | Moisture testing | LS or EA | When tests are done and reported |
| 3 | Floor prep and leveling, as scoped | LS or SF | Percent done, or square feet |
| 4 | Carpet tile, floors 2 and 3 | LS or SY | Percent installed, or square yards |
| 5 | Luxury vinyl tile, corridors | LS or SF | Percent installed, or square feet |
| 6 | Porcelain tile, restrooms | LS or SF | Percent installed, or square feet |
| 7 | Rubber base | LS or LF | Percent installed, or linear feet |
| 8 | Attic stock, cleaning and punch | LS | When handed over and accepted |
Where flooring subs lose money on pay apps
- Mitigation done before anyone agreed to pay. A slab that fails a moisture test is a decision for the GC, not a free fix. Ask in writing first; a change order request with the test results is the record.
- Prep beyond the scope, on a verbal OK. Grinding and leveling a slab that was not flat take crew days. A ticket signed the day the work is done is the one that gets paid.
- Boxes in a storage room, not on the bill. Material delivered and paid for weeks before the floor is ready is cash you have spent. If the subcontract allows stored materials, bill them.
- Attic stock nobody signed for. Spare material handed over without a receipt is a close-out item that stays open, and the last retainage waits with it.
Common questions
How should a flooring contractor set up the schedule of values?
By floor or area and by material (carpet, resilient, tile, base), with moisture testing, floor prep and attic stock on lines of their own. Each month's percent then comes from what is laid on each floor.
Who pays for slab moisture mitigation?
Whoever your subcontract and the specifications say. If it is not in your price, report the test results, ask for a change order before you apply anything and keep the results with it.
Can I bill for flooring delivered but not installed?
Often yes, as stored materials, if your subcontract allows it; attach invoices, delivery tickets and photos. Move it to work completed as it is installed, so it is billed once.
What is attic stock, and when is it billed?
Spare flooring the specifications ask you to leave with the owner for future repairs. Bill it when it is handed over, and get the hand-over signed: it is usually on the close-out list final retainage waits on.
Flooring pay apps that bill the prep as well as the floor
PayApps is hosted pay-app billing for specialty subcontractors. It takes unit-price lines by the square foot or square yard, carries stored materials per line from one application to the next so material is billed once, logs T&M tickets with photos for prep and repairs, and keeps the punch list and close-out checklist, attic stock included, that the last retainage waits on. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.