Steel pay applications bill a job in three stages that are months apart: detailing, fabrication in the shop, then erection by sequence. Embeds and anchor bolts go to the site before almost anything else, and miscellaneous metals (stairs, rails, lintels) trail to the end. This page covers each, with the free guide or tool for it.

What makes steel billing different

SituationWhat the GC usually wantsHow to bill itFree guide or tool
Detailing and shop drawingsApproved drawings before fabricationGive detailing its own line, billed as drawings are approved, not when sentFront-loading check
Steel fabricated in your shopStored materials off site only if the subcontract allows it, with invoices, photos and often a bill of sale and insuranceBill fabricated pieces as stored by sequence, and move them to work completed as they are erected, so they are billed onceBilling stored materials
Erection by sequence or areaPercent complete per sequence, sometimes by tonSplit fabrication and erection by sequence, so each month's percent can be checked against what is standingFree Excel SOV template
Embeds and anchor bolts delivered earlyA line billed when they are delivered to the concrete sub, with a signed receiptBill them on their own line when delivered and signed for, not with the steel they supportChange order log
Design changes after fabrication startedAn RFI answered in writing and a change order before reworkSend an RFI naming the pieces already fabricated; price rework and extra steel as a change orderRFI drafter
Field fixes and back chargesA signed ticket showing whose error it wasWrite a T&M ticket for field fixes caused by others; answer back charges in writing with your own recordT&M ticket log

An example steel schedule of values

An example with made-up lines, to show the shape; your subcontract sets the lines. Some steel subcontracts are priced per ton; then fabrication and erection lines carry tons and a unit price instead of a percent.

LineExample descriptionUnitHow it is billed
1Detailing and shop drawingsLSAs drawings are approved
2Embeds and anchor boltsLSWhen delivered and signed for
3Structural steel fabrication, sequence 1LS or TONAs stored materials, if allowed, then erected
4Structural steel erection, sequence 1LS or TONPercent erected, or tons
5Structural steel, sequence 2LS or TONAs above
6Metal deckLS or SFPercent installed, or square feet
7Stairs and railsLS or EAPercent installed, or flights
8Lintels, loose items and touch-upLSAs installed, touch-up at the end

Where steel subs lose money on pay apps

Common questions

How should a steel contractor set up the schedule of values?

By sequence or area, with detailing, fabrication and erection on separate lines, embeds and anchor bolts on their own line, and miscellaneous metals (stairs, rails, lintels) apart from the frame. Each month's percent then comes from what is approved, fabricated and standing.

Can I bill for steel fabricated in my shop before it is delivered?

Only if your subcontract allows stored materials off site. Expect to show invoices, photos or a fabrication list, and often a bill of sale, insurance on the stored steel and a right for the GC to inspect it. Move it to work completed as it is erected, so it is billed once.

Can a steel pay application be billed by the ton?

Yes, when the subcontract prices it that way: each line carries tons and a unit price, and each month you report the tons fabricated or erected, backed by the shop's fabrication list or the erection sequence.

How do I get paid for rework after a design change?

Send an RFI as soon as the change arrives, naming the pieces already fabricated or erected, and price the rework and extra steel as a change order before you do it.

Steel pay apps that bill fabrication as well as erection

PayApps is hosted pay-app billing for specialty subcontractors. It takes unit-price lines by the ton, carries stored materials per line from one application to the next so fabricated steel is billed once, keeps an RFI log that turns an answer adding work into a change order, and logs T&M tickets with photos for field fixes caused by others. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.