What makes steel billing different
| Situation | What the GC usually wants | How to bill it | Free guide or tool |
|---|---|---|---|
| Detailing and shop drawings | Approved drawings before fabrication | Give detailing its own line, billed as drawings are approved, not when sent | Front-loading check |
| Steel fabricated in your shop | Stored materials off site only if the subcontract allows it, with invoices, photos and often a bill of sale and insurance | Bill fabricated pieces as stored by sequence, and move them to work completed as they are erected, so they are billed once | Billing stored materials |
| Erection by sequence or area | Percent complete per sequence, sometimes by ton | Split fabrication and erection by sequence, so each month's percent can be checked against what is standing | Free Excel SOV template |
| Embeds and anchor bolts delivered early | A line billed when they are delivered to the concrete sub, with a signed receipt | Bill them on their own line when delivered and signed for, not with the steel they support | Change order log |
| Design changes after fabrication started | An RFI answered in writing and a change order before rework | Send an RFI naming the pieces already fabricated; price rework and extra steel as a change order | RFI drafter |
| Field fixes and back charges | A signed ticket showing whose error it was | Write a T&M ticket for field fixes caused by others; answer back charges in writing with your own record | T&M ticket log |
An example steel schedule of values
An example with made-up lines, to show the shape; your subcontract sets the lines. Some steel subcontracts are priced per ton; then fabrication and erection lines carry tons and a unit price instead of a percent.
| Line | Example description | Unit | How it is billed |
|---|---|---|---|
| 1 | Detailing and shop drawings | LS | As drawings are approved |
| 2 | Embeds and anchor bolts | LS | When delivered and signed for |
| 3 | Structural steel fabrication, sequence 1 | LS or TON | As stored materials, if allowed, then erected |
| 4 | Structural steel erection, sequence 1 | LS or TON | Percent erected, or tons |
| 5 | Structural steel, sequence 2 | LS or TON | As above |
| 6 | Metal deck | LS or SF | Percent installed, or square feet |
| 7 | Stairs and rails | LS or EA | Percent installed, or flights |
| 8 | Lintels, loose items and touch-up | LS | As installed, touch-up at the end |
Where steel subs lose money on pay apps
- Fabricated steel in the yard, not on the bill. Mill steel, shop labor and coatings are cash spent months before erection. If the subcontract allows off-site stored materials, bill them by sequence with the backup it asks for.
- Rework on a revised drawing nobody priced. A change after pieces are cut is paid when it was raised in writing first. An RFI that names the pieces already fabricated is the record.
- Embeds billed with the frame. Embeds go to the site months before the steel. Billed on their own line, they are paid that month, not at erection.
- Back charges with no record. A fit-up problem caused by an anchor bolt set out of tolerance is not your cost. Survey or photograph it before you fix it and write it up the same day.
Common questions
How should a steel contractor set up the schedule of values?
By sequence or area, with detailing, fabrication and erection on separate lines, embeds and anchor bolts on their own line, and miscellaneous metals (stairs, rails, lintels) apart from the frame. Each month's percent then comes from what is approved, fabricated and standing.
Can I bill for steel fabricated in my shop before it is delivered?
Only if your subcontract allows stored materials off site. Expect to show invoices, photos or a fabrication list, and often a bill of sale, insurance on the stored steel and a right for the GC to inspect it. Move it to work completed as it is erected, so it is billed once.
Can a steel pay application be billed by the ton?
Yes, when the subcontract prices it that way: each line carries tons and a unit price, and each month you report the tons fabricated or erected, backed by the shop's fabrication list or the erection sequence.
How do I get paid for rework after a design change?
Send an RFI as soon as the change arrives, naming the pieces already fabricated or erected, and price the rework and extra steel as a change order before you do it.
Steel pay apps that bill fabrication as well as erection
PayApps is hosted pay-app billing for specialty subcontractors. It takes unit-price lines by the ton, carries stored materials per line from one application to the next so fabricated steel is billed once, keeps an RFI log that turns an answer adding work into a change order, and logs T&M tickets with photos for field fixes caused by others. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.