Pay applications for site work and excavation contractors: unit prices, rock and haul tickets

Excavation, grading and site utility subcontracts are often written with unit prices: so much per cubic yard of cut, per linear foot of pipe, per ton of stone or asphalt, with separate prices for rock and unsuitable soil. The monthly pay application then bills quantities measured or ticketed, and most disputes are about the quantities. This page covers quantity billing, rock and overruns, stored pipe and structures, and weather days, with the free guide or tool for each.

What makes site work billing different

SituationWhat the GC usually wantsHow to bill itFree guide or tool
Unit-price contract (per CY, LF, SF or ton)Quantities this period and to date at the contract unit price, with how they were measuredGive each line a unit, a unit price and a contract quantity; bill the quantity installed each month, and keep the survey, count or tickets behind itHow to fill out a pay application
Rock, unsuitable soil or undercutA measured quantity, often agreed in the field before it is removed, at the rock or undercut unit price if the subcontract has oneBill it on its own line, not inside general excavation, and get the quantity signed the day it is measuredChange orders and the SOV
Quantities over the contract amountA change order before the overrun is paid, under most subcontractsWatch quantity to date against contract quantity and ask for the change before the line runs overChange orders and the SOV
Import, export and stone by the loadLoad or scale tickets that add up to the quantity billedTotal the tickets per period and keep them with the pay app as backupT&M ticket log
Pipe, structures and fittings delivered ahead of installStored materials with invoices and delivery tickets, if the subcontract allows itBill them as stored and move them to work completed as they are laid, so they are billed onceBilling stored materials
Pumping, dewatering, standby and extra mobilizationsA signed ticket with crew, equipment hours and materialWrite a T&M ticket the same day and get it signed by the GC's superintendentT&M ticket log
Planning the job's quantitiesA balanced SOV whose lines can be checked against the plansWork out cut and fill from the grid before you set the linesEarthwork cut and fill calculator

An example site work schedule of values

An example with made-up lines, to show the shape; your subcontract sets the units, prices and quantities. Each month you enter the quantity installed, and the amount is quantity times unit price.

LineExample descriptionUnitHow it is billed
1MobilizationLSOnce, or in the parts the subcontract allows
2Erosion and sediment controlLS or LFPercent installed, or linear feet of silt fence
3Clearing and grubbingACAcres cleared this period
4Unclassified excavationCYCubic yards moved, from survey or agreed counts
5Rock excavationCYMeasured rock removed, on its own line
6Storm pipe, 18 in.LFLinear feet laid and backfilled
7Catch basinsEAEach structure set
8Aggregate baseTONTons placed, from scale tickets

Where site work subs lose money on pay apps

Common questions

How do you bill unit-price excavation on a pay application?

Each line carries a unit, a unit price and a contract quantity. Each month you report the quantity installed, measured by survey, count or tickets; the amount is that quantity times the unit price.

How do I get paid for rock excavation?

Bill it on its own line at the rock unit price if your subcontract has one, else as a change order. Measure it, get the quantity signed in the field before or while it is removed, and keep the measurement as backup.

Can I bill for pipe and structures delivered but not installed?

Often yes, as stored materials, if your subcontract allows it; attach invoices and delivery tickets. Move them to work completed as they are installed, so they are billed once.

Are weather days paid on a site work job?

Usually as extra time, not money, unless your subcontract says otherwise. Record each day lost in a daily report and ask for the time in writing, so it is there if a delay claim is needed later.

Quantity pay apps that add up to the cent

PayApps is hosted pay-app billing for specialty subcontractors. Its SOV lines can carry a unit, a unit price and a contract quantity; each month you enter the quantity installed and it computes the amount. It also tracks stored materials, logs T&M tickets for dewatering and standby, and keeps a daily report per day with the hours lost to weather. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.