What makes roofing billing different
| Situation | What the GC usually wants | How to bill it | Free guide or tool |
|---|---|---|---|
| Several roof areas or buildings | Percent complete per area and per system | Split the SOV by roof area and by system, so each month's percent can be checked from the roof | Free Excel SOV template |
| Membrane, insulation and metal delivered or loaded ahead of install | Stored materials with invoices, delivery tickets and photos, if the subcontract allows it | Bill it as stored and move it to work completed as it is installed, so it is billed once | Billing stored materials |
| Deck or wet insulation found at tear-off | A measured quantity at the subcontract's unit price for replacement, if it has one, else a change order | Measure and photograph it before covering it, and get the quantity signed the same day | T&M ticket log |
| Weather days | A record of each day lost, and time asked for in writing | Log the day and the hours lost in a daily report; ask for the time, not money, unless your subcontract pays it | Change orders and the SOV |
| Manufacturer's warranty at close-out | The warranty, often after the manufacturer's inspection, before final retainage is released | Put close-out on its own small line and list the warranty in the close-out documents from the start | Getting retainage released |
| Supplier waivers | Lien waivers from the roofing distributor with your pay app | Collect conditional waivers with each application and unconditional ones once paid | Lien waiver log |
| Pricing the roof | A bid that matches the SOV you will bill | Price tear-off, insulation and membrane by the square before you split the SOV | Flat roof bid calculator |
An example commercial roofing schedule of values
An example with made-up lines, to show the shape; your subcontract sets the lines. Areas and systems on their own lines make each month's percent easy to check against the roof itself.
| Line | Example description | Unit | How it is billed |
|---|---|---|---|
| 1 | Mobilization, hoisting and safety | LS | Once, or in the parts the subcontract allows |
| 2 | Roof A: tear-off | LS | Percent of Roof A torn off |
| 3 | Roof A: insulation and cover board | LS | Percent installed |
| 4 | Roof A: membrane | LS | Percent installed |
| 5 | Roof B: tear-off, insulation and membrane | LS | Percent installed |
| 6 | Flashings and edge metal | LS or LF | Percent installed, or linear feet |
| 7 | Deck replacement (unit price) | SF | Square feet replaced, measured and signed |
| 8 | Close-out and warranty | LS | Billed when the warranty is issued |
Where roofing subs lose money on pay apps
- Material on the roof, not on the bill. Material loaded weeks before install is cash the sub has spent. If the subcontract allows stored materials, bill it with the delivery tickets.
- Deck covered before it was counted. Rotted deck replaced and covered the same day without a measured, signed quantity is hard to bill later.
- Retainage waiting on a warranty nobody started. Final retainage that waits on a manufacturer's inspection waits longer when the inspection is booked at the end.
- Late payment nobody charges for. Many states set when a GC must pay a sub after it is paid, some with interest. Check your state.
Common questions
How should a roofing contractor set up the schedule of values?
By roof area or building and by system (tear-off, insulation, membrane, flashing and sheet metal), with close-out and the warranty on a small line of its own. Each month's percent then comes from what is done on each roof.
Can I bill for roofing materials loaded on the roof but not installed?
Often yes, as stored materials, if your subcontract allows it; attach invoices, delivery tickets and photos. Move them to work completed as they are installed, so they are billed once.
How do I bill deck replacement found during tear-off?
At the unit price your subcontract sets for it, if it has one, else as a change order. Measure and photograph the area before it is covered and get the quantity signed by the GC that day.
Why is my final roofing retainage held?
Often because close-out is not complete: the manufacturer's warranty, the punch list, as-builts or a final lien waiver. Ask the GC in writing which items are open, and send them together.
Roofing pay apps with the backup attached
PayApps is hosted pay-app billing for specialty subcontractors. It tracks stored materials per line from one application to the next, keeps a daily report per day with the hours lost to weather, logs T&M tickets with photos for deck found at tear-off, and keeps a close-out checklist and punch list so you can see what the last retainage waits on. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.