Deadlines and interest in 7 states
Each row was read from the state legislature's own published text on 2026-11-25, through search results limited to the official sites (the pages could not be opened directly from where this was written). Where that text did not show a figure, the row says so rather than repeating a number from elsewhere. These laws have exceptions, and many let the contract set different terms. Open the linked statute and read your subcontract before relying on a row. This is a summary, not legal advice.
| State | Statute | GC must pay the sub | Interest when late | Notes |
|---|---|---|---|---|
| Texas | Property Code ch. 28 (§28.002, §28.004) | Within 7 days after receiving the owner's payment | 1½% each month, from the day after the due date | Private work. The owner has 35 days from a written payment request. A sub can suspend work 10 days after written notice of nonpayment (§28.009). Lower-tier subs: the same 7 days. |
| California | Business and Professions Code §7108.5 | Within 7 days after receiving each progress payment, unless agreed otherwise in writing | Not confirmed in the current text we could read. Earlier versions set a 2% a month penalty; check the section. | Private and most public work. In a good-faith dispute the GC may hold back no more than 150% of the disputed amount. The prevailing party gets attorney's fees. |
| Illinois | Contractor Prompt Payment Act, 815 ILCS 603 | Within 15 calendar days after the contractor receives payment | 10% a year | Private work. A sub can suspend work after 7 days' written notice. Public local work has its own act (50 ILCS 505). |
| North Carolina | G.S. ch. 22C (22C-2, 22C-5) | Within 7 days after receiving each periodic or final payment | 1% a month or fraction of a month, from the 8th day | Payment is owed once you have performed under your contract. 2025 House Bill 383 would add a 30-day outer limit; check whether it passed. |
| Pennsylvania | Contractor and Subcontractor Payment Act (1994 Act 7) | 14 days after the contractor receives payment, or 14 days after your invoice, whichever is later (2018 amendment) | At the rate in section 5(d) of the Act; we could not confirm the figure from the text read | Private work. Retainage is due to you within 14 days of the contractor receiving it. Public work is under 62 Pa.C.S. ch. 39. |
| Virginia | Code of Virginia §2.2-4354 | Interest runs on amounts still unpaid 7 days after the contractor is paid by the public body | 1% a month unless the contract says otherwise | Public work. Withholding needs written notice with the reason. Private work has a parallel rule in Title 11. |
| Florida | Florida Statutes §218.735(6) (local government); §713.346 (private) | Local government work: within 10 days after the contractor receives payment. Private work: no fixed day count; unpaid undisputed amounts trigger a remedy after 30 days | Not confirmed in the text we read | Lower-tier subs on local government work: 7 days. Under §713.346, knowingly failing to pay is misapplication of construction funds, and the prevailing party recovers attorney's fees. |
Not listed: Georgia, New York, Massachusetts and other states with prompt payment rules. We could not read their current official text from here, so they are left out rather than filled in from memory.
Late payment interest calculator
Pick a state to fill in its deadline and rate, or type your contract's own terms.
Simple interest, no compounding. A month is counted as 30 days and a year as 365: the statutes we read do not define them, and a court or your contract may count differently. The worked example (Texas, $40,000, owner paid 1 March, you were paid 22 April) is 45 days late and comes to $900.00 of interest. Your numbers stay in this browser tab.
What to do when a GC pays late
- Find out when the owner paid. On public jobs this is often a public record; on private jobs, ask the GC in writing. The deadline counts from that date.
- Put it in writing. Send a short letter or email naming the pay application, the amount, the statute and the interest so far. Several of these laws make suspending work or claiming interest depend on written notice.
- Ask for the interest after the check clears too. Interest stops running on the day you are paid, so a payment that came in late leaves a fixed sum behind: the worked example above is $900.00 once the $40,000 arrives. It is easy to forget once the money is in. PayApps lists each application paid after its due date on the cash report, with the interest it earned at the job's rate, and drafts the email asking the GC to add it to the next payment. Once you bill it or decide to let it go, mark it billed or waived (with the invoice number, say) and it leaves the list, so what is left is only what you have not dealt with.
- Watch your lien deadlines at the same time. Prompt payment interest does not stop the clock on mechanics lien or bond claim deadlines. The free mechanics lien deadline calculator works out the dates. On a federal job there is no lien; the payment bond is the claim, with a 90-day notice for second-tier claimants and a one-year limit (Miller Act bond claim deadlines).
- Do not sign an unconditional waiver for money you have not received. See conditional vs unconditional lien waivers.
- Read the subcontract. Pay-when-paid and pay-if-paid clauses, contract interest rates and dispute terms change what these statutes give you, differently in each state. That question is for a construction attorney in your state.
Follow-up emails to send a GC about a late pay application
Three short drafts to copy and edit. Each names the pay application, the amount and the date, asks one clear question, and offers to fix whatever is holding the payment. None threatens a lien or quotes a statute: add that only after you have checked your notice and lien deadlines. Send them to the person who processes pay applications at the GC (accounts payable or the project accountant), not only the project manager.
Past due: a reminder
Subject: Past due: [job name], pay application #[n], $[amount] Hello [name], Our pay application #[n] on [job name] (dated [date], for work through [period end]) for $[amount] has not been paid yet. Under our subcontract's pay terms ([terms]) it was due on [due date]. Could you tell me when we can expect payment? If something is holding it up (a lien waiver, backup, or a question on a line), let me know and I will get it to you right away. Thank you, [your name] [your company]
More than 30 days past due: a second request
Subject: Second request: [job name], pay application #[n], $[amount] past due Hello [name], I am following up again on our pay application #[n] on [job name] (dated [date], for work through [period end]) for $[amount], which is still unpaid [days] days after the application date. Please reply with the date the payment will be released, or tell me what is needed to release it. If there is a problem with the application, I would rather fix it this week than let it wait another cycle. Thank you, [your name] [your company]
Paid short: ask what the balance is held for
Subject: Balance on [job name], pay application #[n]: $[balance] Hello [name], Thank you for the $[received] received against our pay application #[n] on [job name]. The application was for $[billed], which leaves $[balance] unpaid. Could you tell me what the balance is held for? If it is a backcharge, please send the backup for it; if it is waiting on a lien waiver or other paperwork, tell me what you need; and if it was missed, please let me know when it will be paid. Thank you, [your name] [your company]
Work out the balance first with the paid-short reconciler, and the due date with the cash forecast. These are drafts, not legal advice: if the money is large or the GC has gone quiet, talk to a construction attorney before a deadline passes.
Common questions
How many days does a GC have to pay a subcontractor?
It depends on the state and often on the contract. In the statutes this page read, Texas, California and North Carolina give the GC 7 days after it receives the owner's payment, Illinois 15 calendar days, and Pennsylvania 14 days after the contractor is paid or after your invoice, whichever is later.
Does prompt payment interest stop my lien deadline?
No. Prompt payment interest does not stop the clock on mechanics lien or bond claim deadlines, so watch those dates at the same time.
What should I do first when a GC pays late?
Find out when the owner paid, since the deadline counts from that date, then put it in writing: name the pay application, the amount, the statute and the interest so far. Several of these laws make suspending work or claiming interest depend on written notice.
Know the day every payment is due
PayApps is hosted pay-app billing for specialty subcontractors that keeps every pay application, retainage balance and lien waiver per job, so you can see what is owed and how long it has been outstanding. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.