What makes painting billing different
| Situation | What the GC usually wants | How to bill it | Free guide or tool |
|---|---|---|---|
| Several floors or areas | Percent complete per floor and per coat or phase | Split the SOV by floor or area and by phase (prime, finish coats, wallcovering, special coatings), so the percent can be checked on a walk | Free Excel SOV template |
| Repainting damage by other trades | A signed ticket or change order naming the damage, before it is repaired | Photograph the damage, write a T&M ticket and get it signed, and bill it once approved | T&M ticket log |
| Back charges from the GC | A written back charge with its basis | Ask for it in writing, compare it with your subcontract, and answer in writing | Paid short? Reconcile the check |
| Wallcovering and special coatings ordered ahead | Stored materials with invoices, if the subcontract allows it | Bill them as stored and move them to work completed as they are hung or applied | Billing stored materials |
| Punch list and final retainage | Items accepted before retainage is released | Keep the punch list, mark items not yours, and send the back-check in writing | Punch list tracker |
| Pricing the job | A bid that matches the SOV you will bill | Price walls, ceilings and trim by area before you split the SOV | Painting bid calculator |
An example commercial painting schedule of values
An example with made-up lines, to show the shape; your subcontract sets the lines. Floors and phases on their own lines make each month's percent easy to check on a walk.
| Line | Example description | Unit | How it is billed |
|---|---|---|---|
| 1 | Mobilization | LS | Once, or in the parts the subcontract allows |
| 2 | Level 1: prime | LS | Percent primed |
| 3 | Level 1: finish coats | LS | Percent finished |
| 4 | Level 2: prime and finish | LS | Percent finished |
| 5 | Doors and frames | EA or LS | Each finished, or percent |
| 6 | Wallcovering | LS or SY | Percent hung, or square yards |
| 7 | Exterior coatings | LS | Percent applied |
| 8 | Touch-up and punch | LS | When the punch list is accepted |
Where painting subs lose money on pay apps
- Repainting other trades' damage for free. Walls damaged after they were finished are extra work. Without a photo and a signed ticket, they are usually repaired at the painter's cost.
- A punch list that never closes. Items that are other trades' damage should be marked so and raised with the GC in writing, so they leave your list.
- Back charges found on the check. A check smaller than the application is easier to fight with the back charge in writing. Paid short? Reconcile the check reconciles it.
- Late payment nobody charges for. Many states set when a GC must pay a sub after it is paid, some with interest. Check your state.
Common questions
How should a painting contractor set up the schedule of values?
By floor or area and by phase (prime, finish coats, wallcovering, special coatings, exterior), with touch-up and punch on a small line of its own. Each month's percent then comes from what is done on each floor.
How do I get paid for repainting damage caused by other trades?
Photograph the damage, write a T&M ticket or change order request naming it and get it signed by the GC's superintendent before the repair, then bill it once approved.
Can a painting contractor bill for wallcovering before it is hung?
Often yes, as stored materials, if your subcontract allows it; attach the invoices. Move it to work completed as it is hung, so it is billed once.
When is a painter's retainage released?
When your subcontract says, which is often after the GC is paid its own retainage and the punch list is accepted. Ask which items are open in writing, and mark any that are other trades' damage.
Painting pay apps that bill the extras
PayApps is hosted pay-app billing for specialty subcontractors. It logs T&M tickets with photos for damage by other trades and turns signed ones into change orders, keeps the punch list with items marked not yours, records back charges when a check comes in short, and shows the retainage waiting on close-out. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.