Pay app guides · schedule of values calculator

Overbilling and underbilling: your pay app against your job costs

Your pay application says how far along the job is by what you billed on each line of the schedule of values. Your books, and the work-in-progress (WIP) schedule your bank and bonding company ask for, usually say it by cost: how much of the job's estimated cost you have spent. When the two disagree, the difference is overbilling (billed ahead of the work) or underbilling (work done but not yet billed). This page explains both, shows the entry an accountant books, and checks one job's numbers.

The three numbers

The cost-to-cost method, the one most small contractors' accountants use for a WIP schedule, needs three figures per job and one from the pay application:

FigureWhere it comes fromWhat to watch
Contract sumThe original contract plus approved change orders (the pay application's contract sum to date)Leave out pending changes until they are approved, or the job looks more profitable than it is.
Estimated total costCost to date plus your current estimate of the cost to finishThe one figure that is a judgment. An estimate left at the bid number while costs run over overstates profit every month.
Cost to dateJob cost report: labor, materials, subs and equipment charged to the jobMaterials bought but not yet installed can overstate progress; accountants often treat them separately.
Billed to dateThe pay application's total completed and stored to date, before retainageUse the gross figure. Retainage is billed, only not paid yet; netting it out would show a false underbilling.

Then: percent complete = cost to date ÷ estimated total cost. Earned revenue = percent complete × contract sum. Billed to date − earned revenue is overbilled when positive and underbilled when negative.

Why your pay app and your costs disagree

What a bank or surety reads into it

Overbilling is a liability on the balance sheet (often called "billings in excess of costs and estimated earnings"): money collected for work you still owe. A moderate amount is normal and helps cash flow. A large one means the cash in the bank is partly borrowed from the end of the job, and that end will cost more than it brings in.

Underbilling is an asset ("costs and estimated earnings in excess of billings"), but a soft one: it counts profit you have not billed and may never collect. Underwriters often discount it, and a pattern of underbillings across jobs is one of the signs they read as estimates going wrong. Either way the entries are called contract liabilities and contract assets in current revenue-recognition guidance; your CPA decides the presentation.

Check one job

Type the job's figures. The worked example is filled in: a $480,000 subcontract estimated to cost $400,000, $150,000 spent, $210,000 billed and $21,000 held as retainage.

The adjusting entry

Shown for a business that records revenue as it bills, as most small contractors' books do between WIP updates. Your accountant may book it differently, reverse it each month, or work on a tax method that ignores it.


  

  

The example: 150,000 ÷ 400,000 = 37.5% complete; 37.5% of $480,000 = $180,000 earned; $210,000 billed − $180,000 = $30,000 overbilled. If $60,000 more is spent next month, the job is 52.5% complete and $252,000 earned, so billing about $42,000 would leave it even. Your numbers stay in this browser tab.

Keeping the gap small

Common questions

What is overbilling in construction?

Billing ahead of the work: billed to date is more than earned revenue, where earned revenue is percent complete (cost to date divided by estimated total cost) times the contract sum. On the balance sheet it is a liability, often called billings in excess of costs and estimated earnings.

What causes underbilling?

Most often work on an unapproved change order, whose cost is in the job cost report while the billing waits for a signature. A cost overrun on an estimate that is not updated, a GC cutting your percent complete, and materials charged to the job before they are billed can cause it too.

Why do sureties care about overbilling and underbilling?

A large overbilling means the cash in the bank is partly borrowed from the end of the job. Underbilling is a soft asset that counts profit you have not billed and may never collect; underwriters often discount it, and a pattern of underbillings across jobs is a sign they read as estimates going wrong.

Pay apps and job costs in one place

PayApps is hosted pay-app billing for specialty subcontractors: schedule of values, pay applications, retainage and change orders kept per job, so billing can be compared with cost without retyping either. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.