The form on this page
| Form | Use it for | Statute |
|---|---|---|
| Unconditional Final Lien Waiver | Residential real property in Missouri as Mo. Rev. Stat. § 429.016.1-.2 define it: new residential construction such as homes of four units or fewer (occupied or not), condominiums, townhouses and cooperatives, and the streets, utilities and common areas on those parcels. Not for repair, remodeling or additions to an owner-occupied home of four units or fewer (§ 429.013), and not for commercial work. On that property an unconditional final waiver is valid only on this form (§ 429.016.27). | Mo. Rev. Stat. § 429.016.27 |
| No statutory form | Every other waiver (partial, conditional, and anything on commercial work or on repairs to an owner-occupied home): no set wording | RSMo § 429.016 |
Each form is the statute's text as read on 2026-11-25, from the official source linked with it. The grey caption under each blank says what goes there; it is our guide, not part of the form. Statutes change: open the linked section before relying on a form, and have a Missouri construction attorney review anything you are unsure of.
What Missouri asks of you
- One form, and only for "residential real property" as § 429.016 defines it: new homes of four units or fewer, condominiums, townhouses and cooperatives built to be sold or occupied. Repair, remodeling or additions to an owner-occupied home of four units or fewer fall under § 429.013 instead, and commercial work has no statutory form.
- On that property, a waiver given "in exchange for a payment of less than the amount claimed due at that time" waives nothing unless it is the statutory unconditional final waiver (§ 429.016.25). Partial and conditional waivers are allowed, with no set wording.
- The unconditional final form is "a complete and absolute waiver": it covers work before the date signed and later work under agreements made before that date, and it binds you "notwithstanding claimant's failure to receive any promised payment" (§ 429.016.26, .29). Sign it only once the money has cleared.
- If you recorded a notice of rights and have been paid in full, you must give it within five calendar days of a written request, or face a presumption of slander of title and a $500 statutory penalty (§ 429.016.30).
Notes on the form
- Missouri: on residential real property (§ 429.016.1-.2) an unconditional, final mechanic's lien waiver is valid only if it is on a form substantially as in § 429.016.27. It waives all lien rights for work before the date signed and for later work under agreements made before that date (§ 429.016.26), and binds the claimant even if the promised payment never arrives (§ 429.016.29).
- Claimant's legal name and the name, title or position, address and telephone number of the signer must be typed or printed above or below the signature, and the date signed beside it (§ 429.016.27).
- A claimant that recorded a notice of rights and has been paid in full must give this waiver within five calendar days of a written request (§ 429.016.30).
- Only the lien right is waived: a waiver signed for less than full payment does not release any other claim, remedy or cause of action (§ 429.016.28).
Unconditional Final Lien Waiver
Use it for: Residential real property in Missouri as Mo. Rev. Stat. § 429.016.1-.2 define it: new residential construction such as homes of four units or fewer (occupied or not), condominiums, townhouses and cooperatives, and the streets, utilities and common areas on those parcels. Not for repair, remodeling or additions to an owner-occupied home of four units or fewer (§ 429.013), and not for commercial work. On that property an unconditional final waiver is valid only on this form (§ 429.016.27).. From Mo. Rev. Stat. § 429.016.27, read 2026-11-25.
UNCONDITIONAL FINAL LIEN WAIVER
FOR RESIDENTIAL REAL PROPERTY
Claimant Claimant's legal name, Claimant's address hereby fully, finally, and unconditionally waives and releases any right to assert or enforce a mechanic's lien claim against the residential real property identified below for all work performed by Claimant prior to the date set forth below and for any work hereafter performed by or on behalf of Claimant under any agreements executed by Claimant prior to said date set forth below:
Legal description of the Property
Signature: sign here
Date signed: Date signed
Claimant's legal name: Claimant's legal name
Name of person signing: Name of person signing
Title or position: Title or position
Address: Signer's address
Telephone: Signer's telephone number
Common questions
Does Missouri have a statutory lien waiver form?
Yes. RSMo § 429.016.27 sets one form: unconditional final, residential property only. How strict: On residential real property an unconditional final waiver "shall only be valid if it is on a form that is substantially as follows"; elsewhere no form. The form on this page is printed word for word from the statute as read on 2026-11-25.
Which Missouri lien waiver form goes with which payment?
Unconditional Final Lien Waiver: Residential real property in Missouri as Mo. Rev. Stat. § 429.016.1-.2 define it: new residential construction such as homes of four units or fewer (occupied or not), condominiums, townhouses and cooperatives, and the streets, utilities and common areas on those parcels. Not for repair, remodeling or additions to an owner-occupied home of four units or fewer (§ 429.013), and not for commercial work. On that property an unconditional final waiver is valid only on this form (§ 429.016.27)..
When should I sign an unconditional lien waiver in Missouri?
Only once the payment it covers has cleared your bank. Before that, give the conditional form if Missouri has one, and keep retainage, unapproved change orders and disputed amounts out of a progress waiver. This page is not legal advice; ask a Missouri construction attorney before signing anything you are unsure of.
Fill these in from your pay app instead
PayApps is hosted pay-app billing for specialty subcontractors that prints Missouri's statutory waiver with each pay application, filled in from the job and the amount due, and holds the unconditional one until the payment has cleared. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.