Pay app guides · schedule of values calculator

Miller Act payment bond claims: who can claim, the 90-day notice and the one-year limit

On a federal construction job you cannot put a mechanic's lien on the building: it is government property. What protects subcontractors and suppliers instead is the payment bond the prime contractor must furnish under the Miller Act (now 40 U.S.C. 3131 to 3134). The bond pays if the prime or a subcontractor does not, but only for claimants in the right tier and only if two deadlines are met. This page works out both from the date you last worked or delivered, and drafts the notice a second-tier claimant has to send.

Your deadlines

Enter the last day you performed labor or supplied material under your contract on this job. Your entries stay in this browser tab.

Notice to the prime contractor (second tier)

The statute asks the notice to state the amount claimed "with substantial accuracy" and the name of the party you furnished material to or did the labor for. Fill these in for a draft.

The example: a drywall sub-subcontractor (second tier) that last worked on 2 March 2026 on a $2.4M federal clinic contract. Its 90-day notice must reach the prime by 31 May 2026; it may sue from 1 June 2026 and must sue by 2 March 2027. This is a draft, not legal advice: have an attorney look at it before you rely on it, above all if a date is close.

Who can claim on the bond

The two deadlines, in the statute's words

How we count: 90 calendar days starting the day after your last day, and the one-year date as the same calendar date next year (29 February becomes 28 February, the earlier date). Courts have not all counted the same way, and the "last day" is often argued over: do not count on punch-list, warranty or correction work to move the date later. Send the notice and file well before either date.

Getting the bond, and keeping your rights

Sources, read 2026-11-25: 40 U.S.C. 3133 and 40 U.S.C. 3131 (Cornell LII, checked against the govinfo.gov 2023 edition; last amended 2006), FAR 28.102-1 on acquisition.gov, and the Bateson opinion on Cornell LII.

Common questions

Who can make a Miller Act payment bond claim?

Subcontractors and suppliers who contracted with the prime (first tier), and those who contracted with one of the prime's subcontractors (second tier). Anyone further down has no bond claim: in J.W. Bateson Co. v. United States (1978) the Supreme Court held that "subcontractor" in the Act means one who contracts with the prime.

What is the Miller Act 90-day notice?

A second-tier claimant must give the prime contractor written notice within 90 days from its last labor or material (40 U.S.C. 3133(b)(2)), by a means that gives written, third-party verification of delivery, such as certified mail with a return receipt. The statute requires no notice from a first-tier claimant.

How long do I have to sue on a Miller Act bond?

The action must be brought no later than one year after the last labor was performed or material supplied (3133(b)(4)), in the federal district court where the contract was performed. You may sue once you have not been paid in full within 90 days after your last day.

Federal job deadlines tracked per job

PayApps is hosted pay-app billing for specialty subcontractors. Each job keeps its pay applications, payments and lien waivers, and the cash report shows which money is late, so the last day of work and what is still unpaid are already on file when a bond notice is due, and on a federal job it dates the 90-day notice and drafts it to the prime from them. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.