Pay app guides · schedule of values calculator

Pay applications for glass, glazing and curtain wall: engineering, fabricated units and water testing

Glazing pay applications bill systems that are engineered and fabricated long before they are set: storefront and curtain wall framing, insulating glass made to order, entrances and hardware. Lead times are long, so a glazing sub can carry most of a job's material cost months before the first unit goes in. This page covers each step, with the free guide or tool for it.

What makes glazing billing different

SituationWhat the GC usually wantsHow to bill itFree guide or tool
Several elevations and systemsPercent complete per elevation and per systemSplit the SOV by elevation or area and by system (curtain wall, storefront, windows, entrances, interior glass), so the percent can be checked from the buildingFree Excel SOV template
Engineering, calculations and shop drawingsApproved drawings and calculations before fabricationGive them a small line of their own, billed when approved, not when sentFront-loading check
Frames and glass fabricated or stored off siteStored materials off site only if the subcontract allows it, with invoices, photos and often a bill of sale and insuranceBill what is fabricated and allowed as stored, and move it to work completed as it is set, so it is billed onceBilling stored materials
The mockup and field water testsTheir own lines, done and passed before the walls go upBill the mockup when it is built and each test when it is done; a retest caused by others is a change orderChange orders and the SOV
Openings not ready, or glass broken by othersA signed ticket or a written delay notice, not a verbal OKWrite a T&M ticket for return trips and replaced lites, with photos, and get it signedT&M ticket log
Punch, cleaning and the warrantyItems accepted and warranties handed over before final retainageKeep the punch list and send the warranty with the close-out documentsGetting retainage released

An example glazing schedule of values

An example with made-up lines, to show the shape; your subcontract sets the lines.

LineExample descriptionUnitHow it is billed
1Engineering, calculations and shop drawingsLSWhen approved
2Mockup and testingLSWhen built and passed
3Curtain wall, east and south: materialLSAs stored materials while fabricated, if allowed
4Curtain wall, east and south: installLSPercent set and glazed
5Storefront and entrances, level 1LSPercent installed
6Windows, levels 2 to 4LS or EAPercent installed, or units set
7Interior glass and mirrorsLSPercent installed
8Cleaning, punch and warrantyLSWhen accepted and the warranty is handed over

Where glazing subs lose money on pay apps

Common questions

How should a glazing contractor set up the schedule of values?

By elevation or area and by system (curtain wall, storefront, windows, entrances, interior glass), with engineering, the mockup and testing on lines of their own, and material split from install where the subcontract allows stored materials.

Can I bill for curtain wall or glass stored at the fabricator?

Only if your subcontract allows stored materials off site. Expect to show invoices and photos, and often a bill of sale, insurance on the stored goods and a right for the GC to inspect them. Move them to work completed as they are set, so they are billed once.

Should the mockup and water testing be their own lines?

Yes, when the specifications ask for them: they are real work billed when done and passed, and separate lines keep them from being argued into the wall price. A retest caused by another trade is a change order.

Why is my final glazing retainage held?

Often because close-out is not complete: the punch list, final cleaning, the warranties or a final lien waiver. Ask the GC in writing which items are open, and send them together.

Glazing pay apps that carry fabricated material until it is set

PayApps is hosted pay-app billing for specialty subcontractors. It carries stored materials per line from one application to the next, so fabricated units are billed once, sends each submittal under a transmittal with its needed-on-site date and lead time, logs T&M tickets with photos for return trips and broken glass, and keeps the close-out checklist and punch list the last retainage waits on. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.