Pay app guides · schedule of values calculator

Pay applications for finish carpentry and millwork: shop-built casework, field measure and install

Millwork and finish carpentry pay applications bill work that is mostly built before it reaches the job: shop drawings, field measurements, casework and paneling made in your own shop, then the install. Most of the money is spent weeks before anything is set, which is why the stored-materials line matters more here than in most trades. This page covers each step, with the free guide or tool for it.

What makes millwork billing different

SituationWhat the GC usually wantsHow to bill itFree guide or tool
Shop drawings and samplesApproved drawings and finish samples before fabrication startsGive them a small line of their own, billed when they are approved, not when they are sentFront-loading check
Casework and paneling built in your shopStored materials off site only if the subcontract allows it, with invoices, photos and often a bill of sale and insurance for the stored goodsBill what is built and allowed as stored, and move it to work completed as it is installed, so it is billed onceBilling stored materials
Field dimensions that differ from the drawingsA written question before you build to a dimension nobody confirmedSend an RFI with the dimension you measured and a proposed answer; price any added work as a change orderRFI drafter
Install by floor or areaPercent complete per floor and per type of workSplit the SOV by floor or area and by type (casework, countertops, wood trim, doors and hardware), so the percent can be checked in the fieldFree Excel SOV template
Finished work damaged by other tradesA signed ticket before the repair, naming who caused itPhotograph it, write a T&M ticket and get the superintendent's signature before you fix itT&M ticket log
Attic stock, adjustments and punchItems accepted and spare material handed over before final retainageKeep the punch list and the hand-over of attic stock in writingPunch list tracker

An example millwork schedule of values

An example with made-up lines, to show the shape; your subcontract sets the lines.

LineExample descriptionUnitHow it is billed
1Shop drawings, samples and field measureLSWhen approved, in the parts the subcontract allows
2Casework fabrication, floors 1 and 2LSAs stored materials while in your shop, if allowed
3Casework install, floors 1 and 2LSPercent installed
4Solid surface and quartz countertopsLSPercent installed
5Wood trim, paneling and wall protectionLS or LFPercent installed, or linear feet
6Doors, frames and hardware installLS or EAPercent installed, or openings hung
7Attic stockLSWhen handed over and signed for
8Punch and close-outLSWhen the punch list is accepted

Where millwork subs lose money on pay apps

Common questions

How should a millwork contractor set up the schedule of values?

By floor or area and by type of work (casework, countertops, trim and paneling, doors and hardware), with shop drawings, attic stock and punch on small lines of their own. Each month's percent then comes from what is installed on each floor.

Can I bill for casework built in my shop before it is delivered?

Only if your subcontract allows stored materials off site. Expect to show invoices and photos, and often a bill of sale, insurance on the stored goods and a right for the GC to inspect them. Move them to work completed as they are installed, so they are billed once.

Should shop drawings be their own line on the pay application?

Yes, if the subcontract allows it, as a small line billed when the drawings are approved. A large line billed before approval reads as front-loading.

What happens when field dimensions do not match the drawings?

Send an RFI before you build, with the dimension you measured and a proposed answer. If the answer adds work, price it as a change order before you do it.

Millwork pay apps that bill what is in your shop

PayApps is hosted pay-app billing for specialty subcontractors. It carries stored materials per line from one application to the next, so casework is billed once, keeps an RFI log that turns an answer adding work into a change order, sends each submittal under a transmittal with its needed-on-site date, and keeps the punch list and close-out checklist the last retainage waits on. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.