What makes millwork billing different
| Situation | What the GC usually wants | How to bill it | Free guide or tool |
|---|---|---|---|
| Shop drawings and samples | Approved drawings and finish samples before fabrication starts | Give them a small line of their own, billed when they are approved, not when they are sent | Front-loading check |
| Casework and paneling built in your shop | Stored materials off site only if the subcontract allows it, with invoices, photos and often a bill of sale and insurance for the stored goods | Bill what is built and allowed as stored, and move it to work completed as it is installed, so it is billed once | Billing stored materials |
| Field dimensions that differ from the drawings | A written question before you build to a dimension nobody confirmed | Send an RFI with the dimension you measured and a proposed answer; price any added work as a change order | RFI drafter |
| Install by floor or area | Percent complete per floor and per type of work | Split the SOV by floor or area and by type (casework, countertops, wood trim, doors and hardware), so the percent can be checked in the field | Free Excel SOV template |
| Finished work damaged by other trades | A signed ticket before the repair, naming who caused it | Photograph it, write a T&M ticket and get the superintendent's signature before you fix it | T&M ticket log |
| Attic stock, adjustments and punch | Items accepted and spare material handed over before final retainage | Keep the punch list and the hand-over of attic stock in writing | Punch list tracker |
An example millwork schedule of values
An example with made-up lines, to show the shape; your subcontract sets the lines.
| Line | Example description | Unit | How it is billed |
|---|---|---|---|
| 1 | Shop drawings, samples and field measure | LS | When approved, in the parts the subcontract allows |
| 2 | Casework fabrication, floors 1 and 2 | LS | As stored materials while in your shop, if allowed |
| 3 | Casework install, floors 1 and 2 | LS | Percent installed |
| 4 | Solid surface and quartz countertops | LS | Percent installed |
| 5 | Wood trim, paneling and wall protection | LS or LF | Percent installed, or linear feet |
| 6 | Doors, frames and hardware install | LS or EA | Percent installed, or openings hung |
| 7 | Attic stock | LS | When handed over and signed for |
| 8 | Punch and close-out | LS | When the punch list is accepted |
Where millwork subs lose money on pay apps
- Casework in the shop, not on the bill. Material, labor and shop time spent before delivery are cash you have already paid. If the subcontract allows off-site stored materials, bill them, with the backup it asks for.
- Building to an unconfirmed dimension. A rebuild because a wall moved is paid when the question was asked in writing first. An RFI with your measured dimension is the record.
- A shop drawing line billed when sent. Billing drawings before they are approved, or making the line large, is what a reviewer cuts. Front-loading check compares each line's markup with the job's.
- Repairs done for free. Finished wood scratched by later trades is repaired by someone. A ticket signed before the repair is the one that gets paid.
Common questions
How should a millwork contractor set up the schedule of values?
By floor or area and by type of work (casework, countertops, trim and paneling, doors and hardware), with shop drawings, attic stock and punch on small lines of their own. Each month's percent then comes from what is installed on each floor.
Can I bill for casework built in my shop before it is delivered?
Only if your subcontract allows stored materials off site. Expect to show invoices and photos, and often a bill of sale, insurance on the stored goods and a right for the GC to inspect them. Move them to work completed as they are installed, so they are billed once.
Should shop drawings be their own line on the pay application?
Yes, if the subcontract allows it, as a small line billed when the drawings are approved. A large line billed before approval reads as front-loading.
What happens when field dimensions do not match the drawings?
Send an RFI before you build, with the dimension you measured and a proposed answer. If the answer adds work, price it as a change order before you do it.
Millwork pay apps that bill what is in your shop
PayApps is hosted pay-app billing for specialty subcontractors. It carries stored materials per line from one application to the next, so casework is billed once, keeps an RFI log that turns an answer adding work into a change order, sends each submittal under a transmittal with its needed-on-site date, and keeps the punch list and close-out checklist the last retainage waits on. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.