An electrical subcontract on a commercial job is usually billed once a month on a pay application: a schedule of values (SOV) with each line's percent complete, plus stored materials, change orders and retainage. Electrical work has its own traps. Gear and fixtures are expensive and arrive long before they are installed, rough-in and trim happen months apart, and public jobs add a certified payroll every week. This page walks through each one and links the free guide or tool for it.

What makes electrical billing different

SituationWhat the GC usually wantsHow to bill itFree guide or tool
Switchgear, panels, transformers and light fixtures are bought months before they are setProof of what was delivered and where it is: supplier invoices, bills of lading, photos, and for material stored off site, often insurance and title papersBill it as stored materials (column F), then move it to work completed in the month it is installed, so it is billed onceBilling stored materials
Rough-in and trim are months apartLines that let the GC see progress per area or floor, not one lump line for the whole buildingSplit the SOV by area or floor and by phase (rough-in, trim, gear, fixtures, low voltage), so each month's percent is easy to checkFree Excel SOV template
Owner changes, added circuits and devices, and work out of sequenceA signed T&M ticket or change order before it is billedGet the ticket signed the day the work is done, turn signed tickets into change order requests, and bill only approved change ordersT&M ticket log, change order log
Public and federally funded jobsA certified payroll for every week your crew is on site (29 CFR 5.5(a)(3)(ii)); some states want it filed in their own systemKeep the weekly payroll beside the pay app for the same job; a missing week is a common reason an application is heldour WH-347 guide
Distributors on the jobLien waivers from your suppliers, and sometimes joint checksCollect conditional waivers from suppliers with each pay app and unconditional ones once they are paidLien waiver log, joint checks
Retainage held for months after trim-outClose-out documents (as-builts, O&M manuals, warranties, test reports) before releaseTrack the retainage per job and send the close-out package with the release requestGetting retainage released

An example electrical schedule of values

This is an example of how electrical subs often break a lump-sum contract down, not a standard; your subcontract or the GC's form may set the lines. The point is lines small enough that a percent complete can be checked by walking the floor.

LineExample descriptionWhy it is its own line
1Mobilization, permits and submittalsBilled early and once; keep it modest (see front-loading below)
2Temporary power and lightingUsed through the whole job, often removed at the end
3Underground and in-slab conduitDone early, before the slab is poured
4 to 9Rough-in by floor or areaProgress the GC can see wall by wall
10Switchgear and distribution (material)A large stored-materials line while it waits for the electrical room
11Switchgear and distribution (labor)Billed when set, terminated and tested
12Light fixtures (material)Often delivered in one shipment, installed over months
13 to 18Trim and devices by floor or areaLate work that should carry its fair share of the contract
19Fire alarm and low voltageOften a separate scope or lower-tier sub
20Testing, close-out and as-builtsThe last line; ties to the retainage release

Where electrical subs lose money on pay apps

Common questions

Can I bill for switchgear before it is installed?

Usually, as stored materials, if your subcontract allows it and you attach what it asks for (invoices, delivery proof, photos, and for off-site storage often insurance and title papers). Move it from stored to work completed in the month it is installed so it is billed once.

How should an electrical contractor break down the schedule of values?

By area or floor and by phase (underground, rough-in, gear, fixtures, trim, low voltage, testing and close-out), with expensive material on its own lines. Small lines make each month's percent easy to check and keep late work funded.

Do electrical subs need certified payroll?

On federal and federally assisted construction covered by Davis-Bacon, yes: every contractor and subcontractor submits a weekly certified payroll for the weeks it has workers on site. Several states require the same on state public works, some in their own online systems.

How do I get paid for added circuits and devices?

Write a T&M ticket or change order request and get it signed before or on the day of the work, then bill it once the change order is approved. Bills for unsigned extras are the ones most often refused.

Electrical pay apps, gear and payroll in one place

PayApps is hosted pay-app billing for specialty subcontractors. It keeps your SOV by line, carries stored gear from month to month until it is installed, logs T&M tickets and change orders, prints the weekly WH-347 certified payroll from the same job, and tracks retainage until close-out. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.