Pay applications for concrete contractors: unit prices, quantities and extras

Concrete subcontracts (foundations, slabs, flatwork, site concrete and paving) are often written by unit price: so much per cubic yard, square foot or linear foot. The monthly pay application then bills the quantity placed, not a percent. That changes how the schedule of values is set up, what the GC checks and where the errors creep in. This page covers unit-price billing, extras and retainage, with the free guide or tool for each.

What makes concrete billing different

SituationWhat the GC usually wantsHow to bill itFree guide or tool
Unit-price contract (per CY, SF or LF)Quantities placed this period and to date, at the contract unit priceGive each line a unit, a unit price and a contract quantity; bill the quantity placed each month, and the dollars followHow to fill out a pay application
Lump-sum contract with pours by areaPercent complete per area or elementSplit the SOV by element (footings, walls, slab on grade, elevated decks, flatwork) and by areaFree Excel SOV template
Quantities over the contract amountA change order before the overrun is paid, under most subcontractsWatch quantity to date against contract quantity, and ask for the change before the line runs overChange orders and the SOV
Extra pours, winter protection, pumping, standby timeA signed ticket with crew, equipment and materialWrite a T&M ticket the same day with the pump, crew hours and yards, and get it signedT&M ticket log
GC portals that ask for quantitiesThe SOV entered with units and unit valuesSet up the unit-price lines once, the way the portal wants themBilling in Procore, Textura and GCPay
Ready-mix and rebar suppliersLien waivers from them with your pay appCollect conditional waivers with each application and unconditional ones once paidLien waiver log

An example unit-price schedule of values

An example with made-up quantities and prices, to show the shape; your subcontract sets the units and prices. Each month you enter the quantity placed, and the amount is quantity times unit price.

LineExample descriptionUnitHow it is billed
1MobilizationLSOnce, as a lump sum (1 LS)
2Spread footingsCYCubic yards placed this period
3Foundation wallsCYCubic yards placed this period
4Slab on grade, 5 in.SFSquare feet placed and finished
5SidewalksSFSquare feet placed
6Curb and gutterLFLinear feet placed
7Vapor barrierSFSquare feet installed

Where concrete subs lose money on pay apps

Common questions

How do you bill a unit-price contract on a pay application?

Each line carries a unit, a unit price and a contract quantity. Each month you report the quantity placed this period; the amount is that quantity times the unit price, and the to-date quantity shows how much of the contract quantity is used.

What happens when concrete quantities run over the contract quantity?

Under most subcontracts the extra quantity needs an approved change order before it is paid. Track quantity to date against the contract quantity and ask for the change before the overrun.

How should pump time and standby be billed?

As extra work on a T&M ticket signed the same day, showing the pump, crew hours, equipment and any material, unless your subcontract already prices it.

Can lump-sum concrete work be billed by percent complete?

Yes. Split the schedule of values by element and area (footings, walls, slabs, decks, flatwork) and bill each line's percent complete.

Unit-price pay apps that add up to the cent

PayApps is hosted pay-app billing for specialty subcontractors. Its SOV lines can carry a unit, a unit price and a contract quantity; each month you enter the quantity placed and it computes the amount, shows quantities on the PDF and CSV, writes GCPay's unit-price SOV upload, and logs T&M tickets for pump and standby time. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.