Change order log for subcontractors

Paste your change order log, or start from the example. The page works out the revised contract sum, how much is pending and at risk and how long it has waited, flags billing on unsigned or rejected changes, and writes the approved change orders as schedule-of-values lines for next month's pay application.

Your log stays in this browser. It does the arithmetic and checks; your contract decides what may be billed and when notice is due.

1. The job

2. Change order log

Columns: CO #, Description, Status (approved, executed or signed; pending, submitted or proposed; rejected; void or withdrawn), Amount (a deduct is negative), Days of time asked for, Submitted and Approved dates, and Billed to date. Only status and amount are required.

3. Where the job stands

Revised contract sum$0.00
Approved change orders, net$0.00
Pending, not yet signed$0.00
Pending past the flag0
CODescriptionStatusAmountDaysBilledWaiting

Summary


  
  

  

Approved change orders as schedule-of-values lines

Each approved change order as its own line, with what is billed to date as "previous". Paste these under your original lines in the pay application generator and fill in this period.


  

  

Exceptions wording for a progress lien waiver

A starting point for the exceptions you list when signing a progress waiver while change orders are still open. Some states require a statutory waiver form; add exceptions only where that form allows them, and ask an attorney if unsure. See lien waivers.


  

How the numbers are worked out

Common questions

What goes in a change order log?

One row per change: its number, a description, its status (pending, approved, rejected or void), the amount, any days of schedule time it asks for, the date it was submitted, the date it was approved, and what has been billed against it.

Can I bill a pending change order on my pay application?

Usually not. Most pay applications only carry executed change orders, so pending work is tracked in the log and billed the month it is signed. Some subcontracts allow billing work approved in principle; check yours.

How do approved change orders get onto the schedule of values?

Each approved change order becomes its own line, CO-1, CO-2 and so on, with its full amount as the scheduled value; a deductive change order is a negative line. This page writes those lines for you in the columns the free pay application generator reads.

Worked example: change orders and the schedule of values.

How do I follow up on a change order the GC has not signed?

In writing, to the person who approves change orders on the job (usually the GC's project manager, not the billing contact), restating the number, the scope, the price and any time it asks for, and asking what is needed to sign it. Note the date of each follow-up next to the date submitted, so the log shows how long it has waited and how often you asked. Your subcontract may set how long the GC has to answer, a notice period for claims, or what happens if nobody answers; check it, because this page does not.

Chasing change orders across several jobs?

PayApps is hosted pay-app billing for specialty subcontractors: a change order log per job that records when each request went to the GC, drafts the follow-up email to the GC's project manager and notes the day you last sent one, shows every change order still waiting for approval across all your jobs with how long it has waited, and adds each one to the next pay app the month it is signed, next to retainage and lien waivers. It is open now: pay applications with retainage and change orders, free on one job, no card. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps.