Pay applications: the monthly paperwork subcontractors pay to escape

What a monthly pay application involves for a trade sub, what billing tools charge today (sourced), and PayApps, now open free on one job.

Specialty subcontractors on commercial jobs (electrical, mechanical, drywall, concrete) get paid through a monthly document most people outside construction have never seen. This post is about that paperwork, what people already pay to make it easier, and the product this portfolio is building for it, PayApps.

Open now (2026-11-27): PayApps takes sign-ups on its Free plan: one active job, one user, no card. That covers the schedule of values (typed, pasted, or imported from your Excel, CSV or PDF), change orders, retainage, the application summary and continuation sheet as PDF and CSV, the cash and retainage report, and the RFI, submittal, estimate and daily-report logs. Lien waivers, QuickBooks Online and job costing are in the paid plans, which are not on sale yet: checkout is off until payments are set up. It has no customers yet. Start free in PayApps. Check every figure before you send it to a GC: PayApps does the arithmetic, you sign the application.

The problem

On a commercial job, a subcontractor does not send an invoice for the work. They send a pay application to the general contractor (GC), usually on an AIA G702/G703-style form or the GC's own version of it, by a fixed date each month. It has two parts:

  • A schedule of values: every line of the contract (say "rough-in, level 2" or "taping and finishing"), its value, what was billed in earlier periods, what was completed this period, materials stored on site, the percent complete and the balance to finish.
  • A summary page: the contract sum plus approved change orders, total completed to date, the retainage held back (often 5% or 10% of what is billed, released at the end of the job), what earlier certificates already paid, and the payment due now.

Around it sit the jobs that make it slow:

  • Change orders. Approved ones go on the schedule; pending ones must not, but have to be tracked so they get billed when approved.
  • Lien waivers. GCs often want a waiver with each pay app: A conditional waiver for this month, unconditional for last month's money once it clears, and the wording matters, because signing the wrong one can give away rights to money not yet received.
  • Retainage. Five or ten percent of every bill sits with the GC until closeout, often months later. Someone has to track how much is held on each job and ask for it back.
  • Accounting sync. The bill then goes into the books, and QuickBooks has no native retainage (per a vendor guide), so many subs keep a spreadsheet beside it.
  • Every GC wants it differently. Some use a portal from Procore or Trimble, some a PDF, some their own spreadsheet.

Mistakes cost time and cash: a pay app with a line billed over its value can be sent back for correction, and one that misses the GC's cut-off can wait for the next cycle.

What people pay today

Prices are as listed by the sources linked, several of them aggregator sites. Check the vendor's own page before comparing.

ToolWhat it isPrice
PayAppHubpay apps for subs$39.99 / $79.99 / $129.99 a month
Trimble Pay (formerly Flashtract)billing and waiverssub plan $99 a month
SubLienlien and waiver managementfrom $199 a month
Sitelinepay apps for subsquote only, priced by pay-app volume (Siteline)
Knowifycontractor managementfrom $99 a month
Contractor Foremancontractor suite$49–$332 a month
JobTreadcontractor suite$199 a month + $20 a user

Investors think the problem is worth solving: Siteline raised $18.4M to sell this to subcontractors. And the market is large and small-business heavy: NAHB counts 1.9M+ specialty-trade independent contractors, 79% of specialty-trade establishments.

There is also some churn coming among residential tools: CoConstruct is being folded into Buildertrend, with no new CoConstruct projects after 31 March 2027. CoConstruct's own page (read 2026-11-27) adds that active projects can be finished there and old ones stay readable, so the decision is where jobs that start after the cut-off will live, and whether to move a long job mid-stream. CoConstruct is closing to new projects sorts the options by kind of business (a custom or cost-plus builder needs a builder suite; a sub or small GC billing on a schedule of values may only need pay-app billing), lists what to pull out of CoConstruct before moving a partly billed job, and says plainly what PayApps does not do: selections, a homeowner portal or cost-plus billing.

The fee you pay even without software (added 2026-11-25)

The table above is what a sub chooses to buy. On many commercial jobs the GC also requires its own payment portal, and some portals bill the sub. The portal vendors publish the rules in their help pages (read 2026-11-25 through search results limited to those sites):

So an electrical sub with eight $400,000 subcontracts a year on Textura pays $880 on each, $7,040 a year, before buying any billing tool at all. That is more than a year of most of the tools in the table. It is usually a condition of the job, so the useful move is to know it and price it into the bid. The new pay application software comparison puts the options and the portal fees on one page with a calculator for your own subcontracts (source).

What we are building

Ranked first of the paid bets in the market research, the plan is a billing product for specialty subcontractors and small GCs that does four jobs together:

  1. Pay applications from a saved schedule of values, carried forward month to month, with checks for over-billing and front-loading, and output in the formats GCs ask for.
  2. Retainage tracked per job and per line, with what is held, what is due for release and when to ask.
  3. Lien waivers generated with each pay app and checked for wording that releases more than the payment covers.
  4. Change orders tracked from pending to approved, so approved ones land on the next pay app.

A fifth job grew out of the first four: knowing which money is late. An unpaid application is not late just because it is 30 days old. It is late once the subcontract's payment clause has run out. Under net 45 terms, a 40-day-old application is on time. Under net 15 terms, a 20-day-old one is already late. So the cash view in the build takes each job's pay terms and gives every unpaid application a due date. It then splits what is owed into past due and expected in the next 30 days, and names the most overdue application with its due date. A job with no terms entered is left out of the forecast. The forecast does not guess a default. (Added 2026-11-25; still in development.)

The waiver exchange has a second half that is easy to drop. The conditional waiver goes out with the application; once the check clears, the GC often wants the unconditional one for that payment, as the list above says. The build now tracks that second half. When an application is paid and a conditional waiver on it was sent, it says the unconditional waiver is next, on the application's page and in the cash view. It never asks while an application is unpaid or paid short. An unconditional waiver for money not yet received is the costly mistake from the list above. Utah's statute has no unconditional form, so a Utah job is never asked. (Added 2026-11-25; still in development.)

QuickBooks sync is needed from the first version, because that is where the money ends up. Later modules are meant to grow it into a contractor suite: job costing, RFIs, estimating.

Job costing has started, beside the billing: a cost budget for each schedule-of-values line, costs typed or pasted in as they come, and a WIP schedule worked by cost (cost to date divided by estimated total cost). That estimate is where WIP schedules often go wrong. A budget from the bid is only an estimate. When a line overruns, the WIP keeps showing the old budget until someone revises it, and the job looks further along than it is. So the project manager can now type a cost to complete for any line, meaning what it still has to cost from today. The line's estimate becomes the cost spent on it through that day plus the cost to complete. Percent complete, earned revenue, over/under billing and projected profit then follow the new estimate. Costs dated after the estimate are counted against it. If they use it all up, the build says so and holds the estimate at the cost to date. It does not guess a new one.

The build's tests include an example worked by hand. A $100,000 line is billed $50,000 against a $60,000 budget. It had $30,000 of cost by the 15th, when the project manager typed $40,000 to complete, and $6,000 more by the 31st. The estimate is $70,000, $10,000 over budget, so the line is 51.43% complete ($36,000 of $70,000), has earned $51,428.57 and is $1,428.57 underbilled, with $30,000 of projected profit. On the bid budget the same line would read 60% complete, $60,000 earned, $10,000 underbilled and $40,000 of projected profit. The old budget overstates earned revenue by $8,571.43 and profit by $10,000, and a surety reading it would see an underbilling that mostly isn't there. It is a working schedule for the contractor and their accountant, not a financial statement. (Added 2026-11-26; in development, not for sale.)

Then there is money the job has already promised away. A sub that signs a lower-tier subcontract or issues a purchase order has committed to that cost even though most of it has not been invoiced yet. If the estimate ignores it, the WIP again shows a job further along and more profitable than it is. So purchase orders and subcontracts can now be entered per job, and each supplier invoice or sub pay app can be put against one. Whatever is not yet invoiced counts as cost still to come, so a line's estimate never drops below its cost to date plus its open commitments. An invoice that runs past its commitment is flagged, which usually means a change order to it was never recorded.

The tests check the arithmetic on an example worked by hand. A $40,000 line has a $30,000 budget and a $35,000 lower-tier subcontract, with $10,000 invoiced against it so far. On the budget alone the line reads 33.33% complete, $13,333.33 earned and $10,000 of projected profit. Counting the $25,000 still open, the estimate is $35,000, so the line is 28.57% complete, has earned $11,428.57 and will make $5,000. The budget-only view overstates earned revenue by $1,904.76 and projected profit by $5,000, although that $5,000 was gone the day the subcontract was signed. (Added 2026-11-26; in development, not for sale.)

None of that helps if the costs have to be typed twice. In most subcontracting companies the bookkeeper already enters every supplier bill, check and card charge in QuickBooks Online and tags it to a customer or job, because that is how QuickBooks' own job reports work. So a job in PayApps can now be linked to that QuickBooks customer or job, and PayApps reads the bills, checks, card charges and vendor credits tagged to it over the dates you pick. You tick the lines that belong to the job, put each on a schedule-of-values line, check the suggested category ("Job Materials" reads as material, "Equipment Rental" as equipment), and import them as costs. Nothing is written back to QuickBooks. Bill payments are not read, so a bill paid by check is counted once. A line can only be imported once, even if two people press the button at the same time, and if a bill is edited in QuickBooks afterwards, the list shows both amounts so the cost can be corrected. Payroll run through QuickBooks Payroll is not in QuickBooks' accounting data that apps can read, so labor comes in from the payroll report instead (below). (Added 2026-11-26; in development, not for sale, and not yet tried against a live QuickBooks company.)

Not every company tags costs to a customer. Plenty of electrical and mechanical subs on QuickBooks Online Plus or Advanced keep one customer per GC and track each job as a class instead ("Jobs:Mesa Clinic"), so every bill line carries the job's class and the profit-and-loss by class is their job report. For them the link can now be a class: choose "Costs tagged by: Class" and pick it. If the job's invoices already carry a class (set on the QuickBooks page), that class is offered first. PayApps then reads the bills, checks, card charges, vendor credits, payroll journal entries and purchase orders whose lines carry that class, and nothing tagged only to a parent class such as "Jobs". (Added 2026-11-26; in development, not for sale, and not yet tried against a live QuickBooks company.)

Purchase orders count too. A switchgear order placed in September for $18,000 is cost on its way, and if the job report only shows the $9,000 billed so far, the job looks more profitable than it is. So PayApps now also reads the purchase orders tagged to the job in QuickBooks and imports the ones you tick as commitments. Open orders start ticked and closed ones don't, because QuickBooks closes an order once it is billed in full or someone closes it by hand. The other half matters as much. When the bookkeeper turns that order into a bill in QuickBooks, the bill remembers which order it came from, and PayApps uses that link to count the $9,000 bill against the $18,000 order. The job then shows $9,000 spent and $9,000 still to come, not $9,000 spent and $18,000 to come. The link holds whichever of the two you import first, and if you move a bill off its order by hand, it stays where you put it. (Added 2026-11-26; in development, not for sale, and not yet tried against a live QuickBooks company.)

Labor is usually a trade sub's largest cost, and the hardest to get onto a job. It sits in the payroll service, not in the bookkeeping, and gross wages alone understate it: employer payroll taxes come on top, and so do costs no payroll report carries, such as workers' comp and liability insurance. So the job-cost page can now read the payroll service's own payroll-by-job export (a CSV with a pay date, employee, job, cost code, hours, gross pay and employer taxes). It finds the header under the report's title lines, matches the columns by name and picks out this job's rows. Each pay date becomes one labor cost per schedule-of-values line: wages, plus employer taxes and contributions, plus a burden percent on wages if the contractor types one. The burden is the contractor's own number. The build never assumes one, and left blank it counts only what the report says. The file is read in the browser and only the per-date totals are saved, with no employee names. Importing the same report again adds nothing, because each cost is labelled by its pay date and line and a label the job already has is skipped.

The tests check one week by hand: $1,000 of wages on line 1 with $76.50 of employer taxes and a 20% burden is a $1,276.50 labor cost, and $500 on line 2 with $38.25 of taxes is $638.25. Costed at gross wages, the same week would show $1,500 instead of $1,914.75, so labor would be understated by about 22%. The percent-complete figures driven by that cost would be off by about the same share. (Added 2026-11-26; in development, not for sale.)

Some payroll services skip the export step. Each payroll run is posted to QuickBooks as a journal entry, with the wages and employer taxes debited to labor accounts and each line tagged to the customer or job the hours were worked on. Those lines now appear in the same QuickBooks list as the bills and checks, marked "Journal entry", and they import the same way. Only lines on expense accounts count: Expense, Cost of Goods Sold and Other Expense. A debit is a cost. A credit, such as a bookkeeper moving hours to the right job, counts as a negative cost. The cash side of the entry is skipped. So is a receivables write-off, even though QuickBooks puts the customer's name on it, because it is not a cost of doing the work. The QuickBooks list and the payroll report would both cover the same weeks, so take labor from one of them and not both. (Added 2026-11-26; in development, not for sale, and not yet tried against a live QuickBooks company.)

Where it stands (updated 2026-11-27)

Open on the Free plan since 2026-11-27 (above); paid plans not on sale yet. The notes "still in development" further down are dated: each described a feature when it was added, before launch. Built and tested so far:

  • monthly pay applications from a schedule of values, with change orders, retainage and PDF and CSV exports;
  • schedule-of-values import from the contractor's own spreadsheet, and a start partway through a job;
  • lien waiver tracking, with the statutory form printed for the states encoded so far;
  • invitations for a team;
  • a cash and retainage report across jobs;
  • sending a pay application to QuickBooks Online as an invoice, with retainage kept in its own account, and then each check received as a payment against that invoice (below).

Short pays. The newest piece handles a GC that pays an application in pieces or short:

  • Each check or transfer is recorded against the application, with its date and check number.
  • The cash report counts what came in and ages only the balance still owed.
  • After 30 days it flags the application as paid short and names the amount.
  • The application counts as paid once the payments reach the amount the GC certified.
  • Lien waivers follow the checks. Say a $45,000 application is paid as $30,000 and then $15,000, and the unconditional waiver for the first check has gone out. The build then asks for a second unconditional waiver for $15,000, not for the full $45,000. It prefills that amount. (Added 2026-11-25; still in development.)

A short pay does not change the next pay application: line 7 on the summary subtracts earlier certificates, not earlier payments. So the unpaid balance has to be chased on its own, and a report that only knows "paid" or "not paid" would hide it.

Closing a balance that will not come. Some short balances are never paid: the GC took a backcharge, the amount is in dispute, or it is not worth chasing. Left as "owed", that balance sits in the aging report for ever and the next follow-up call is about money that is not coming. The build now closes it on the application as a backcharge, disputed or written off, with a date and a note. The cash report then counts only the money received as paid and lists the rest under its reason, with totals per job and across jobs. A disputed balance keeps a next step, because the contractor still claims it. The unconditional waiver the build asks for, and prefills, covers only the money received. Reopening the balance, or deleting a payment, puts it back as owed. (Added 2026-11-25; still in development.)

The follow-up email. Knowing an application is late is half the job: someone still has to write to the GC. The cash report now drafts that email for each unpaid application from its own figures: the application number and date, the period billed, the amount owed, and the due date under the job's pay terms. A late application gets a reminder that asks when payment is coming and whether anything is holding it up. More than 30 days late, the draft becomes a second request that asks for a release date. An application paid short gets a note that thanks the GC for what came in, names the balance and asks what it is held for. The contractor edits the draft and sends it from their own email; the build sends nothing. The draft does not mention lien rights or interest and does not say a copy is attached, because the build cannot know whether those apply. (Added 2026-11-25; still in development.)

When the GC wants it notarized. Some GCs and owners ask for the pay application to be signed in front of a notary, and the AIA's own application form has a notary section for it. Our PDF had no place for it, so a sub would print it and staple on a notary's certificate. Each job now has a "notary block" switch. With it on, the summary page carries a generic jurat under the contractor's signature: state and county, "subscribed and sworn to (or affirmed) before me on (date) by (name)", the notary's signature and commission expiry, and a box for the seal. All the blanks are left for the notary to fill in. It is our own wording, not any state's form. Some states prescribe the wording of a notary's certificate, so the block says a notary may attach their own certificate instead. To make room on page 1, the summary rows sit closer together when the block is on. A test checks every line and box against the footer in the tallest layout. With the switch off, the page is unchanged. (Added 2026-11-25; still in development.)

An expired insurance certificate. Subcontracts usually require the sub to keep certificates of insurance on file with the GC: general liability, auto and workers' compensation at least. When a policy renews and nobody sends the new certificate, the GC's compliance check can hold the payment, and the sub hears about it only when the check doesn't come. The build now keeps the company's own certificates: the coverage, insurer, policy number and policy dates typed from each one. A certificate counts as expiring 30 days before its expiry date and as expired from that day on. The projects page shows a one-line note while one is expiring or expired. A draft pay application dated on or after an expiry, or less than 30 days before it, lists that certificate with its date, so the renewal can go out with the application. When a policy renews, the old certificate is archived and no longer flagged. The optional weekly "money to chase" email lists every certificate that has expired or will expire within 30 days, so a company with no pay application due that week still hears about it. A renewal has to reach every GC that holds the old certificate (the "certificate holder" box on the form), and on a sub with a dozen jobs that list lives in someone's head. So each certificate can now record which jobs' GCs hold it, with the date it was sent. The insurance page then says "Send the renewal to Peak GC and Sierra Builders", naming each GC once even when it holds the certificate on several jobs. A new certificate is offered the same jobs as the archived one it replaces, the weekly email names the GCs on each renewal line, and a draft pay application names any certificate not recorded as sent to that job's GC. (Added 2026-11-26; still in development.)

Knowing who needs the renewal still leaves the emails to write. So a current certificate now has "Email GCs": one draft per GC, listing that GC's jobs, the insurer, policy number, new policy period, limits and wording as typed, and the date the old certificate expires. It goes to the GC's project manager when the job has one. It never says a file is attached: the sub attaches the PDF and sends it from their own mail. After sending, "Record as sent today" marks that GC's jobs as holding the new certificate, so their pay applications show it on file. (Added 2026-11-26; still in development.)

Dates are only half of it. A subcontract's insurance exhibit also sets minimum limits (for example, a stated amount for each occurrence and in aggregate) and asks for wording on the certificate: additional insured, waiver of subrogation, primary and non-contributory. A certificate that is current but short on any of these can still be sent back. So each certificate can now carry its limits and the wording it shows, and each job can carry what its subcontract asks for, one row per coverage. The job page marks every requirement "Met" or "Gap" and says why in words: no certificate, expired, not started yet, a limit below what is asked (with both figures), a limit nobody typed (never assumed met), or an endorsement the certificate does not show. An umbrella policy counts toward a limit only where the job says the GC accepts that. A draft pay application lists the same gaps as of its own date, so they are fixed before it goes out. The build checks what was typed from the certificate, not the policy itself. The insurance broker still confirms the coverage. (Added 2026-11-26; still in development.)

A free guide covers the same ground for anyone without the product: the ACORD 25 box by box, the endorsement page that proves each request, and why a certificate gets sent back. The short version: the certificate says it confers no rights on its holder, so a ticked "additional insured" box needs the endorsement behind it (often ISO CG 20 10 for ongoing work and CG 20 37 for completed work). (Added 2026-11-27.)

Typing those requirements in from a ten-page exhibit is its own chore, so the form can now read them from the exhibit itself: the PDF (a scan is read by text recognition in the browser) or pasted text. Exhibits come in two shapes, a table ("Each Occurrence $1,000,000") and prose ("limits of not less than $1,000,000 per occurrence and $2,000,000 general aggregate"), and the reader handles both. It knows which amounts are not one of the two limits a certificate check needs (the products-completed operations aggregate, personal and advertising injury, medical expense, a "for subcontracts over $500,000" threshold), that "all policies except Workers' Compensation shall name the Contractor as additional insured" leaves workers' comp out, and that "may be satisfied by a combination of primary and umbrella" lets the umbrella count. No AI model reads the exhibit. Every value it fills in is listed with the sentence it came from, and nothing is saved until you check it and press Save. The file stays in your browser. (Added 2026-11-26; still in development.)

Larger GCs often scale the limits to the size of the subcontract: one umbrella limit for subcontracts up to a set amount, a higher one above it, sometimes three or four bands. Earlier, the reader kept the first figure and flagged the conflict. Now it reads the bands: a heading such as "Subcontracts over $1,000,000 and up to $5,000,000:", a clause such as "$5,000,000 for subcontracts of $1,000,000 or more", or a range such as "$0 - $500,000". The job's contract sum picks the band. Limits from the other bands are set aside, and each one is listed with the band it belongs to. A figure from the job's band replaces one the exhibit gave without a band. If no band holds the contract sum, the reader says so. It uses the original contract sum, so a change order that moves the job into a higher band is for you to catch. (Added 2026-11-26; still in development.)

Many GCs also want the current certificate itself in the backup of every pay application, not only on file. So each certificate in the build now keeps its files: the certificate PDF from the agent, usually an ACORD 25, and any endorsements the subcontract asks for, such as additional insured or waiver of subrogation. A draft pay application lists the files of every active certificate, and one click copies a file into that application's backup, so it goes into the single PDF packet sent to the GC. The files count against the same storage limit as other attachments, and they are deleted with the certificate. (Added 2026-11-26; still in development.)

The other papers a GC asks for. Insurance is not the only file a GC keeps on a sub. Before the first payment, and again when something lapses, the GC's subcontractor onboarding or prequalification form usually asks for the contractor's license in the job's state (class and number), a W-9, a bonding letter from the surety stating bonding capacity, the experience modification rate (EMR) letter, the OSHA 300A summary, the written safety program, and a DBE, MBE or WBE certification where the job has goals. A sub working in three states has three licenses with three renewal dates. The build now keeps these beside the insurance certificates on a "Licenses and documents" page, typed from each document: the state or city, class, number, issuer and dates. The expiry date is optional, because a W-9 or a safety program has none; those are never flagged. One with an expiry date follows the certificate rules: a note on the projects page 30 days before it, and a warning on a draft pay application dated within that window or after it. A W-9 keeps only the date it was signed. Its number is the company's tax ID (an EIN, or a Social Security number for a sole proprietor), so the build refuses to store one. The page also turns the list into text to paste into a GC's prequalification form, licenses first, with an expired document listed and marked rather than left out. It reads what was typed and does not check a license with the state board. (Added 2026-11-26; still in development.)

A scanned schedule of values. The schedule of values often arrives as a scan: the GC's signed copy, or a page someone ran through the office copier. Until now the import read a scan only if the scanner had saved it as a "searchable PDF", with its own text layer. If it hadn't, the import asked the contractor to rescan it. The build now reads a scan that is only pictures, too. It runs the open-source Tesseract text reader inside the browser, so the scan is never uploaded. The text it reads goes through the same checks as any other import, including the check that the lines add up to the sheet's own total.

We tested it on two scans of a 48-line bid breakdown, tilted 1.5 degrees as a page lies on the glass: a grey 300 dpi scan and a black-and-white one. Both came in with all 48 lines and the sheet's $1,120,223.00 total. OCR still makes mistakes. On the grey scan one cost code lost its spaces ("011000"). On the black-and-white scan, one amount came back as "9.200.00". No amount is written with two full stops, so the build reads it as $9,200.00 and says so. The cost codes on that scan were too uneven to read as a column, so its lines were numbered in order instead. Every figure still has to be checked against the paper. The first scan downloads the text reader, about 7 MB, and each page takes a few seconds. (Added 2026-11-26; still in development.)

A scan on its side. A sheet fed into the scanner sideways or upside down used to come back empty or as garbage. Tesseract reads text that runs down the page, but not text that runs up it or is upside down. On our test page it read that text at a mean confidence of 50 out of 100, against 93 for the same page the right way up. The build now works out which way the text runs and turns the page to read it, as you would turn the paper. When most of a page reads as unsure, it reads the page again turned half round and keeps the better result. That second read costs about 3 seconds, and only on such a page. The import then says which page it turned. Tested on the black-and-white scan above with one page turned each way: all 48 lines and the $1,120,223.00 total came through. (Added 2026-11-26; still in development.)

The WIP schedule, as a PDF for the surety. A bonded subcontractor sends a work-in-progress schedule to its surety, and often its bank, every quarter or at year end. The build already works one out from each job's cost budgets, its costs and its latest sent pay application (cost-to-cost percent complete). It now prints that schedule as a one-file PDF: for each active job the contract, the estimated cost and gross profit, cost to date, percent complete, earned revenue, billed to date, over and under billing, cost to complete and the revenue still to earn, with totals and a line for the company to sign. A job still missing a budget line is listed but left out of the totals, and the page says so. The PDF says what it is: a working schedule, not financial statements, an audit or a review, to check with the company's accountant before it goes to the surety. (Added 2026-11-26; still in development.)

The working price range in our notes is about $99 to $249 a month. That is an estimate from the competitor prices above, not a decided price. The paid product is built in a private repository; the free tools stay open source.

Getting retainage into QuickBooks (added 2026-11-25; still in development)

Because QuickBooks has no retainage field in most companies, the build sends each pay application as an ordinary invoice built so the books still show what is held. Take a first application on a $100,000 job at 10% retainage that bills $20,000 of work and $5,000 of stored materials:

Invoice lineItemAmount
1 Rough-inContract Billing (income)$20,000.00
2 Fixtures (materials stored)Contract Billing (income)$5,000.00
Retainage held, pay application #1Retainage (Retainage Receivable, an asset)−$2,500.00
Total: line 8, current payment due$22,500.00

Income is booked in full as the work is billed. The GC owes $22,500 now, and the $2,500 sits in a Retainage Receivable account, so that account's balance is the retainage held across all jobs. When retainage comes back, the release is a positive line on the same item. Each work line is what the application adds to its schedule line (work this period plus the change in stored materials), so materials installed next month are not billed twice.

Three rules keep it honest. The invoice total is always the application's own line 8: the retainage line is the difference, never a figure worked out again from a rate. Each application is sent once, under a number like PA24-117-03, and a retry looks that number up before creating anything. And nothing posts without the contractor pressing the button after seeing the lines. A test runs a job across three applications, with stored materials installed and a cut in the retainage rate, and checks that the invoices add up to the last application's line 6 (total earned less retainage). It has not yet run against a real QuickBooks company.

Checks received, without counting them twice (added 2026-11-25). Once the invoice is in QuickBooks, each check recorded against the application can be sent as a payment from the GC, applied to that invoice, with the date received and the check number. On the $22,500 invoice above, take two checks of $15,000 and $7,500. The bookkeeper may already have keyed the second check in QuickBooks. Sending it again would show the GC as having paid $30,000. So before every send the build reads the invoice's open balance in QuickBooks and compares it with what it expects: $22,500 less the $15,000 already sent, which is $7,500. QuickBooks shows $0, so the build sends nothing and shows both figures. The contractor checks the invoice and marks the check "already in QuickBooks". Each send also carries a fixed request id, so a retry after a dropped connection is the same request. Deleting a check that is already in QuickBooks asks first, because the build never deletes anything in the contractor's books. Like the invoices, this is tested against a simulated QuickBooks company, not yet a real one.

Class and location per job (added 2026-11-26). Many electrical and mechanical subs on QuickBooks Online Plus or Advanced split their profit and loss with classes ("New work", "Service", "Tenant improvements") or locations (a branch or division). An invoice sent without them lands in "unclassified", and someone fixes it by hand every month. In the build, each job gets a class and a location, picked from the company's own lists. Every invoice and credit memo for that job carries them: the class goes on each line or on the invoice, whichever way the company has class tracking set, and the location goes on the invoice. If someone later makes that class inactive in QuickBooks, the job's next invoice is held back with a message naming it. PayApps does not post it to no class. This is also tested against a simulated QuickBooks company only.

Certified payroll on Davis-Bacon jobs (added 2026-11-26). A sub on a Federal or federally assisted job (a VA clinic, a federally funded school or transit project) owes the GC a certified payroll every week, on top of the monthly pay application. The Department of Labor's regulations (29 CFR 5.5(a)(3)(ii)) require the weekly payroll. DOL's own Form WH-347 is optional, and DOL says a properly completed one satisfies the requirement. Each worker gets a row per labor classification, with hours for each of the seven days split into straight time and overtime, the rate paid, fringe benefit credit and cash in lieu, gross pay for this job and for all work, tax, FICA and other deductions, and net pay. A second page carries a statement of compliance that the official who paid the crew signs. The current revision (January 2025) has six checkboxes in that statement, with tables for apprenticeship programs and for each fringe plan's hourly credit per worker.

The arithmetic is where a hand-filled form goes wrong: overtime on more than 40 hours in the week across all jobs, fringe credit times hours, net pay that has to match the check. In the build, the job gets a certified payroll page that works out those columns from what the contractor types. It refuses to print a full Social Security number (DOL's instructions forbid it), hours over 24 in a day, or deductions larger than gross pay. It warns about straight time over 40 hours, an overtime rate under time and a half, a rate under the wage determination's figure the contractor typed, and an unfunded fringe plan, which needs DOL approval first. The PDF follows the form's columns, prints the statement of compliance in the form's own words, and leaves the signature blank, because DOL does not accept a copied one. Workers' names and numbers are not stored on our servers. The draft stays in the contractor's browser, so next week starts from this week's crew. It is not a Department of Labor product and not legal advice: the contractor checks the figures and signs. Like the rest of the build, it is in development.

The hours by day can now come from a time report instead of being typed (added 2026-11-26). The contractor exports a CSV with one row per worker and day worked, such as QuickBooks time activities or a time-card detail report, and the page puts each day's hours on that day of the week. Hours from other jobs are left out. Four things a time export gets wrong are handled rather than guessed at:

  • A payroll register has one date per pay period. Read as if it were by day, it puts 40 hours on a Friday. A date column headed pay date, check date, period end or week ending is refused.
  • Overtime can appear twice. When there is a total column and an overtime column, the overtime is taken out of the total. A row with more overtime than total hours is blocked.
  • Double time is left out of the overtime row and listed. The WH-347's overtime row has one rate, usually time and a half, so double-time hours put there would be priced at 1.5x on a form the contractor signs as true.
  • Holiday, vacation, PTO and sick rows are pay, not hours worked, so they are left out and named.

Rates, deductions and gross pay are not read from the file. They stay typed on the form, where the wage determination checks run. The CSV is read in the browser and never uploaded.

By trade

Each trade bills the same monthly form differently, so the guides now have one page per trade (added 2026-11-27; site work, roofing, masonry and painting the same day, then millwork, flooring, glazing and steel): what the GC checks, an example schedule of values, and where that trade usually loses money.

  • Electrical contractors: switchgear and fixtures as stored materials, rough-in and trim by area, extras on signed tickets, certified payroll on public jobs.
  • HVAC, plumbing and mechanical: equipment deliveries, start-up and balancing as their own lines, and the close-out package retainage waits on.
  • Drywall and framing: lines by floor and phase, stocked board, extras from other trades, back charges and punch lists.
  • Concrete: unit-price billing by cubic yard, square foot and linear foot, overruns, and pump and standby tickets.
  • Site work and excavation: unit prices by cubic yard, linear foot and ton, rock on its own line, load tickets and stored pipe.
  • Commercial roofing: roof areas and systems, material loaded ahead of install, deck found at tear-off and the warranty retainage waits on.
  • Masonry: walls by area and material, pallets on site as stored materials, the mockup and cold-weather protection.
  • Commercial painting: floors and coats, damage by other trades on signed tickets, back charges and punch lists.
  • Millwork and finish carpentry: casework built in your shop as stored materials, shop drawings billed when approved, field dimensions as RFIs.
  • Commercial flooring and tile: slab moisture and floor prep as extras, material on site as stored, attic stock.
  • Glass, glazing and curtain wall: units fabricated off site, the mockup and water tests, return trips and broken glass.
  • Structural steel and misc metals: detailing, fabrication and erection by sequence or ton, embeds delivered early, rework after design changes.
  • Fire sprinkler and fire protection: design billed when the AHJ approves it, rough-in apart from heads set after the ceiling grid, the hydro test, relocated heads on signed tickets, final acceptance before the last retainage.

What exists now, free

Parts of the job already have free tools on this site. They are the starting point, not the product:

  • Pay Application Generator: paste a schedule of values and get the summary, retainage, payment due and flags for over-billed or front-loaded lines. (source)
  • Lien Waiver Checker: paste a waiver and see common wording that costs the signer money. (source)
  • Construction Retainage Calculator: the cash tied up in retainage and what waiting costs. (source)
  • Change Order Log (added 2026-11-25): paste or open your change order log and see the revised contract sum, how much is pending and unsigned, and how long each pending change has waited. It flags money billed on pending, rejected or void changes, and billing outside zero to the approved amount. It writes the approved change orders as schedule-of-values lines (CO-1, CO-2, with billed to date as "previous") in the columns the Pay Application Generator reads; a test feeds them through the generator and checks the net change and revised contract sum match to the cent. It also drafts the exceptions line for a progress lien waiver, listing the open change orders. The hosted product keeps one log per job and adds each change order to the next pay application the month it is signed. (source)
  • Billing stored materials (added 2026-11-25): the stored-materials column is a snapshot, not a running total. Each month, stored now = stored on the last pay app + delivered − installed, and the installed value is billed as this period's work. Leave the stored column alone after installing, and the same switchgear is billed twice: the guide's example shows $25,500 completed and stored when it is right and $34,500 when it is not. The page's rollforward tool does this line by line and flags installing more than was on hand, a line over its value, off-site material without the contract's permission or title papers, and stock that has sat a month. Its off-site rule quotes the federal payment clause, FAR 52.232-5 (read 2026-11-25); private contracts set their own. A test feeds its lines through both the calculator and the Pay Application Generator and checks total completed and stored, and retainage on stored, match to the cent. Writing it turned up an error in our own step-by-step guide, which said "previous" was last month's total less only the stored material since installed; it is last month's total less all of last month's stored. Fixed. (source)
  • Front-loading a schedule of values (added 2026-11-25): put your estimated cost next to each SOV line and the check shows each line's markup against the job's, the value pulled onto early lines, and the late lines (testing, closeout, punch list) priced below cost, which is the part that hurts if the job stops or the final pay app is held. It writes a balanced SOV (every line at the job's markup) and the smallest cost-weighted change that keeps every line within a tolerance you choose, both rounded so they add up to the contract to the cent. With start and finish months it shows billing, over-billing and job cash by month. On the page's 10-line example ($580,000 on $499,000 of cost), $40,431 sits above balance on early lines, the lowest job cash point is $23,000 as submitted against $1,582 balanced, and at a 9% cost of money that early cash is worth about $2,066: the trade a sub is making against a rejected SOV. It makes no claim about what a given contract allows; a mobilization cap is entered from your own contract. A red-team pass the same day found the first version's "within tolerance" SOV failed its own check: it left lines exactly on the band's edge, and rounding pushed 3 of the example's 10 lines (at dollar rounding) a hair outside, so pasting the fix back in still read as front-loaded. It now rounds each line inside its band, and a test re-checks the output on 300 random schedules. (source)
  • Pay application checker (added 2026-11-25): most pay apps that come back for corrections are not wrong inside themselves; they disagree with last month's approved one. Paste last month's approved schedule of values and this month's draft (CSV, cells copied from a spreadsheet, or the calculator's own CSV download) and it matches every line by item number. It flags a "from previous applications" figure that is not last month's previous plus this period, a scheduled value edited without a change order, a line that disappeared, a new line not numbered as a change order, stored materials that fell by more than was billed as installed, a retainage rate change, and a previous certificates figure that is not last month's total earned less retainage (a common slip is typing last month's payment instead). The worked example plants four of those mistakes and the tests check it finds those four and nothing else. The hosted product starts each month's application from the approved one, so these mistakes cannot be typed in the first place. (source)

Why a spreadsheet, and how we know its formulas are right

A spreadsheet needs no account and no new habit, and "schedule of values template" is something people search for, so a free one with the arithmetic done is a reasonable front door. The template fills in total completed and stored, percent complete, balance to finish, retainage per line (work and stored materials at their own rates, rounded to the cent) and the nine summary lines down to current payment due. A check column marks any line billed over its scheduled value, or billed with no scheduled value, and the summary counts them. It has no macros, no links to other files and no add-ins, so it opens in Excel, Google Sheets and LibreOffice without a security prompt.

The file is not drawn by hand. A short script writes it, about 200 lines with no spreadsheet library, so the same code always gives the same bytes, and a test fails if the committed file and the code drift apart. A second test opens the filled-in example in LibreOffice, recalculates every formula from scratch, and checks the result against the guide's hand-worked numbers: $79,850 completed and stored, $7,985 retainage, $40,365.00 due, $86,635 balance to finish including retainage. A third test bills one line $5,000 over its value and adds work to a line with no value, and checks that both are flagged.

What it does not tell us is whether contractors use it. Its downloads are counted only in each visitor's own browser, so we will learn that from search impressions and from people who write in.

Overbilling and underbilling: where the pay app meets the books

  • Overbilling and underbilling

    (added 2026-11-25). A pay application measures progress by what was billed on each line. The work-in-progress (WIP) schedule a bank or surety asks for usually measures it by cost: cost to date divided by estimated total cost. The two rarely agree, and the gap is the job's over- or underbilling. The guide names where the gap comes from: a front-loaded schedule of values, stored materials, cost on change orders not yet signed, an estimate not updated after an overrun, and a GC that cuts the percent you asked for. It shows the adjusting entry and checks one job.

    Its worked example is a $480,000 subcontract estimated at $400,000, with $150,000 spent and $210,000 billed. That is 37.5% complete by cost and $180,000 earned, so the job is $30,000 overbilled even though the pay app says 43.75%. With $21,000 held as retainage, $39,000 more has been certified than the job has cost. If $60,000 is spent next month, billing about $42,000 brings it back to even. The arithmetic is in billing.mjs, and billing.test.mjs checks these figures, plus a cost overrun that caps progress at 100%, a loss job and billing past the contract sum. One choice matters most: billed to date is taken before retainage. Netting retainage out would make every job look underbilled by its retainage. (source)

    This is the first place the free tools set billing beside cost. The hosted suite keeps both per job, so the comparison would come without retyping. The guide links to the existing contractor WIP schedule for every open job at once, and the WIP tool now links back to it.

Every pay app guide page now ends with the same list of all fifteen (added 2026-11-25), grouped as tools, billing guides, and getting paid and lien waivers. Before that, each page linked a hand-picked four to eleven of the others, and the calculator page linked neither the pay-if-paid clause reader, the prompt payment table nor the waiver forms by state. One file (nav.mjs) writes the list into every page, and a test fails when a new page is left out of it. (source)

The sworn statement: who you owe, under oath

  • Contractor's sworn statement

    (added 2026-11-25). In Illinois and Michigan, a pay request goes in with a sworn list of every sub, supplier and (in Michigan) laborer owed wages, with what each was contracted for, has been paid and is owed now. Title companies and construction lenders ask for the same table elsewhere. The page sets the two statutes side by side. Illinois (770 ILCS 60/5) wants the statement before the owner pays, with names, addresses and, since Public Act 103-0827 took effect on 1 January 2025, the amounts due or to become due to each. Michigan (MCL 570.1110) wants it when payment is due or requested, on a statutory form with columns for contract price, paid, owing and balance to complete, and a contractor who has not given one is not entitled to payment until it does. Both were read on 2026-11-25 through search results limited to the legislatures' own sites; this session could not load them directly, so the page says to check the linked text.

    The builder takes the list as pasted from a spreadsheet and checks three things a reviewer checks: each party's completed work less retainage equals paid plus owing; all rows together equal your own contract sum (so a missing own-forces row shows up as money nobody is listed for); and the owing column equals what this pay application asks for. It then lists the waivers to collect with it: unconditional through what each party has been paid, conditional for what it is owed now. Its example, an electrical sub's $480,000 contract with $85,000 paid and $32,900 owing, ties out; asking for $30,000 instead is flagged, because in Michigan the owner can withhold enough to pay the amounts shown. sworn.test.mjs reads Michigan's and the usual Illinois column titles, including a "balance to complete" column that must not be read as work completed. (source)

    It builds the table, not the oath or the statutory wording. In the hosted suite the subs, payments and waivers are already kept per job, which is where this statement would come from without retyping.

    Since 2026-11-28 the hosted statement is also saved with the job. The hard part of a sworn statement is the "paid to date" column, because it has to grow by exactly what was owing last month. "Start next month" carries it forward, but until now the list lived in one browser, so the office manager who prints the statement on a different computer from the owner who typed it started from blank. Now every editor's change is saved with the job as they type, everyone in the company opens the same list, and the page says who saved it last and when. A half-filled list saves; only printing insists on every name and date. A viewer's changes stay in their own browser. (source)

None of these is the AIA's form, none is affiliated with the AIA, and none is legal or accounting advice. Retainage, waiver and payment terms come from your contract and your state's law.

Lien waivers in both directions: a log that pairs them

Every pay application moves lien waivers two ways. The sub signs a conditional waiver for the GC with the pay app, then an unconditional one once the money clears; and it collects the same pair from its own suppliers and lower-tier subs, because a supplier the sub has paid can still claim a lien on the job until it signs an unconditional waiver. Most subs track this in a spreadsheet, and the two failures are quiet ones: an unconditional waiver handed over before the check cleared (it gives up the lien right whether or not the money arrives), and a supplier paid months ago whose unconditional waiver was never collected.

The free lien waiver log reads that spreadsheet as pasted. It pairs each conditional with its unconditional by party, progress or final, and through date, then flags:

  • unconditional waivers given with no cleared-payment date, signed before the payment cleared, or for more than the amount paid;
  • paid conditionals from suppliers with no unconditional held, as a note at first and as a check once a chase window (10 days by default) passes;
  • repeated rows, progress waivers with no through date, and progress waivers signed after a final one.

Given the next pay app's through date, it lists the waivers to collect from each lower tier and writes them as plain requests. In the built-in example (eight waivers on one job) it finds one unconditional waiver for $51,750 given with no payment recorded, $16,150 paid to two lower tiers with no unconditional held, and four waivers to request. The logic is in waivers.mjs with ten tests in waivers.test.mjs.

What it deliberately does not do: decide whether a waiver is valid in a given state or which statutory form applies. Those are in the waiver forms by state guide, each linked to the statute; this page checks the log against itself. In the hosted product, each pay app will carry its own waiver list, so the chasing happens on the job rather than in a separate sheet.

Paid short: splitting the gap before you call the GC

When the check is smaller than line 8, the gap usually has one of three causes. The GC certified less than you applied for, which is a cut to the application, billed again next month once agreed. Or it deducted a backcharge, which you should ask to see in writing with its backup. Or it is holding money without saying why, often for a missing waiver, insurance certificate or certified payroll.

The free paid-short reconciler takes four inputs: what the application asked for, the certified amount, each payment received and each deduction the GC named. It splits the shortfall into those three parts and says what to ask about each. It lists one unconditional waiver per payment actually received, for that payment's amount, and says not to waive the balance. It also drafts the email to the GC.

In the built-in example a $45,000 application is certified at $42,000, with a $1,800 cleanup backcharge, and one $38,000 check comes in. Of the $7,000 short, $3,000 is the cut, $1,800 the backcharge, and $2,200 has no reason given: that $2,200 is the question for the GC. The logic is in shortpay.mjs, with four tests in shortpay.test.mjs. It is arithmetic on what you type. It does not read your subcontract.

When will I get paid: the gap between payroll and the pay app

Payroll goes out every week. A pay application goes in once a month on the GC's cutoff day, and the money comes back after the owner pays the GC and the GC pays you, less retainage. With a cutoff on the 25th, 30-day owner terms and a GC that pays ten days later, work done on 26 March goes on the 25 April application and is paid around 4 June: about 70 days after the crew was paid for it.

The free cash forecast (added 2026-11-25) takes one row per job (monthly billing, retainage, cutoff day, owner days, GC days, months left) and the applications already sent. It dates every expected payment, lists the late ones, and adds up money in week by week. With cash on hand and weekly spending it finds the first week the balance goes below zero. Late money and retainage are kept out of the weeks, because nobody knows when they arrive. It also flags a recent cutoff with no application listed: a missed cutoff costs a month, not a few days.

The built-in example has three jobs, two of them with the same GC, $25,000 in the bank and $21,000 a week going out. It has $265,200 coming in over 13 weeks, so the business is profitable on paper. It still goes $16,550 negative in the week of 27 January, because no pay-app money lands for four weeks in a row. In the example, the $51,300 application that is 21 days late is the difference. The logic is in forecast.mjs, with eight tests in forecast.test.mjs that check the example's dates and totals by hand. The day counts are the user's own. The page compares the GC days with the prompt payment table and never puts the statute's figure in their place.

Early access

If you run a subcontracting or small GC business and bill on pay applications, we would like to hear how you do it now: which GCs, which formats, what goes wrong. Email hello@marisstella.app with "pay apps" in the subject. Be aware that the inbox is read by AI agents working on this project, with the owner responsible for it. There is no list to join yet and nothing to buy; when there is something to try, the people who wrote in will hear first.