Florida's Notice to Owner for subcontractors: the form, the 45 days and the 40-day mailing rule

Fla. Stat. § 713.06 for subs and suppliers: who serves a Notice to Owner, the 45-day deadline, the form, copies, and the 40-day mailing rule.

In Florida, a subcontractor, sub-subcontractor or supplier who has no contract with the property owner can lose its lien rights before it sends its first pay application. The step that protects them is the Notice to Owner. Section 713.06(2)(a) of the Florida Statutes makes it a prerequisite: "All lienors under this section, except laborers, as a prerequisite to perfecting a lien under this chapter and recording a claim of lien, must serve a notice on the owner".

Florida has more specialty trade contractors than any state but California (44,445 establishments in the Census Bureau's 2022 County Business Patterns, NAICS 238). So we read the statute and added the notice to PayApps. Everything below quotes the 2026 Florida Statutes as the Florida Senate publishes them (§ 713.06, § 713.18), read on 2026-11-27.

The deadline: 45 days, and it is strict

The notice "must be served before commencing, or not later than 45 days after commencing, to furnish his or her labor, services, or materials, but, in any event, before the date of the owner's disbursement of the final payment after the contractor has furnished the affidavit".

Two things make this the date to watch:

  • Missing it ends the lien. "The failure to serve the notice, or to timely serve it, is a complete defense to enforcement of a lien by any person."
  • The timing gets no slack. Paragraph (2)(f) forgives errors in the notice's contents that did not hurt anyone, "However, a lienor must strictly comply with the time requirements of paragraph (a)."

The clock starts on the first day you furnish labor, services or materials, not when you sign the subcontract or send your first bill. On a job that starts with a week of deliveries, the first delivery starts it.

The 40-day mailing rule

Section 713.18 lists the ways to serve the notice: hand delivery; common carrier or "registered, Global Express Guaranteed, or certified mail" with evidence of delivery; or posting on the site if neither works. Subsection (2) adds a rule worth planning around. A notice to owner is served as of the day it is mailed, rather than the day it arrives, if all of these hold:

  • it goes by registered, Global Express Guaranteed or certified mail, postage prepaid;
  • it is mailed "within 40 days after the date the lienor first furnishes labor, services, or materials";
  • you keep a mail log with the USPS certified or registered number, the name and address served and the postmark date, or the USPS tracking records.

So there are two dates. The 45th day is the last day to serve. The 40th day is the last day you can mail and know the notice counts from mailing, even if the owner never picks up the envelope.

First day of workMail by (40 days)Serve by (45 days)
2 Nov 202612 Dec 202617 Dec 2026
20 Jan 202829 Feb 20285 Mar 2028

These are calendar days. Neither section read here moves a deadline that lands on a weekend or holiday, so don't count on one moving. Ask counsel if you are cutting it that close.

Who gets a copy

  • The owner, at the address in the recorded notice of commencement. With no notice of commencement, you "may rely on the information contained in the building permit application" (§ 713.06(2)(e)).
  • The contractor, if you are a sub-subcontractor or a supplier to a subcontractor: "A sub-subcontractor or a materialman to a subcontractor must serve a copy of the notice on the contractor". Many first-tier subs copy the GC anyway.
  • The subcontractor above you, if you supply a sub-subcontractor and know that subcontractor's name and address.
  • Anyone the owner named in the notice of commencement to receive copies (§ 713.06(2)(b)). Missing this copy "does not invalidate an otherwise valid lien", but send it.

What the form says

The statute gives the form and says the notice "may be in substantially the following form and must include the information and the warning contained in the following form". It opens with three lines in capitals ("WARNING! FLORIDA'S CONSTRUCTION LIEN LAW ALLOWS SOME UNPAID CONTRACTORS, SUBCONTRACTORS, AND MATERIAL SUPPLIERS TO FILE LIENS AGAINST YOUR PROPERTY EVEN IF YOU HAVE MADE PAYMENT IN FULL." and two more). Then come the blanks: the owner's name and address, a general description of your services or materials, the property, and "under an order given by" the company that hired you. A block headed "IMPORTANT INFORMATION FOR YOUR PROTECTION" follows, and the form ends with the lienor's signature, name and address and a "Copies to" line.

Since the contents need only be substantially right but the warning must be there, the safe choice is the statute's own wording, all of it. That is what PayApps prints.

After the notice: the claim of lien, 90 days

The notice is not the lien. "The serving of the notice does not dispense with recording the claim of lien" (§ 713.06(2)(a)), and the claim of lien "may be recorded at any time during the progress of the work or thereafter but not later than 90 days after the final furnishing of the labor or services or materials by the lienor" (§ 713.08(5)). It is served on the owner before recording or within 15 days after (§ 713.08(4)(c)), and it asks for "the date and method of service of the notice to owner" (§ 713.08(1)(h)), which is one more reason to keep the mail log with the job.

Texas is different: a notice for every month you are not paid

Florida asks for one notice at the start of the job. Texas asks for one per month of unpaid work, from every tier, to both the owner and the general contractor. For original contracts signed on or after 1 January 2022 (H.B. 2237), the notice of claim goes out "not later than the 15th day of the third month after the month during which" the labor or materials were provided, or the second month on a residential construction project (Tex. Prop. Code § 53.056(a-1)). March work is due 15 June on a commercial job. A missed month costs the lien for that month's work, not the whole job.

Two details differ from Florida. Texas moves a date that falls "on a Saturday, Sunday, or legal holiday" to the next day that is none of them (§ 53.003(e)). Chapter 53 does not list the legal holidays; the Government Code does. Section 662.021 says a legal holiday "includes only" the national holidays and the first six state holidays of § 662.003, so 24 and 26 December, though state holidays, do not move a date (Gov't Code ch. 662). That matters more than it sounds: November 2026 work is due 15 February 2027, which is Presidents' Day, so the last day is Tuesday the 16th. Plan on the unmoved 15th anyway. And retainage has its own notice, due by the earlier of 30 days after your contract ends or 30 days after the original contract is terminated or abandoned (§ 53.057(a-1)), much sooner than the monthly clock.

The free Texas lien notice guide lists the date for each unpaid month with any weekend or holiday extension beside it, the retainage notice, the lien affidavit (§ 53.052), its five-day copies (§ 53.055) and the one-year suit date (§ 53.158(a)), and drafts the § 53.056(a-2) or § 53.057(a-2) form word for word, with the § 53.254(g) statement for a homestead. Its tests check both forms and every quoted phrase against the statute text read on 2026-11-27. In PayApps, a Texas job's notice panel prints both forms from the job (date, project and address, your company, the GC), and "Texas deadlines" beside it lists each unpaid month's date, the retainage notice and both lien affidavit dates. Mark the job as tracked (residential or not) and PayApps reads the months from the job's own pay apps: every month a sent pay app with a balance covers gets its notice date, rolled past weekends and the legal holidays above, and the names of whoever has no notice recorded for it yet. Record each notice as you send it, to the owner or the original contractor, by certified mail, in person or a traceable carrier (the three ways § 53.003(b) allows), with the mail number; PayApps says whether it went out by the date. From 30 days before each month's date, the cash page and the weekly email carry a line for it until both have one. It does not yet track the retainage notice's 30 days or keep the green card with the record.

Free: the dates and the form in your browser

The Florida Notice to Owner guide does the arithmetic above without an account. Pick your place in the contract chain and it lists who gets the notice and who gets a copy; enter the first day you furnished work and how you are serving it, and it gives the 45-day date, the 40-day mail-by date, whether a notice already sent was on time (on mailing, or on delivery when it went after day 40 or by courier), and, with your last day of work, the 90-day claim of lien date. Below that, fill in the blanks for a printable draft of the § 713.06(2)(c) form, word for word. Its tests check the whole form and every quoted phrase against the statute's text. It runs in the browser and uploads nothing.

In PayApps

On a Florida job, the "Preliminary notice of right to lien" panel fills the § 713.06(2)(c) form from the job: the owner, the site, the GC as the party who gave the order and as the first copy, and your company. You add the work and your address and print a PDF. Enter the first day you furnished work and the panel shows both dates above. A test compares every word of the printed form with the statute's text, and four one-phrase edits to the form each fail it.

Then record each notice as it goes out: to whom (the owner, the contractor, the subcontractor above you, the notice of commencement's designee, the lender), how (certified, registered or Global Express Guaranteed mail, hand delivery, a common carrier, posting), the day sent and the mail or tracking number. PayApps says when each one counts as served under § 713.18:

How it wentCounts as servedNotes
Certified, registered or Global Express Guaranteed mail, mailed by day 40The day mailedKeep the mail log or USPS tracking records (§ 713.18(2)(c))
Same mail, mailed after day 40The day deliveredEnter the date from the green card or tracking when it comes back
Common carrierThe day deliveredSame: from the carrier's proof of delivery
Hand deliveryThe day handed overTo an officer, partner, member or manager, or an authorised agent (§ 713.18(1)(a))
Posting on the siteThe day postedOnly "if service as provided by paragraph (a) or paragraph (b) cannot be accomplished"

The first day of work is saved with the job, so the dates don't change when someone else opens it, and until a notice to the owner is recorded the cash page and the weekly "money to chase" email carry a reminder. It changes as the dates pass: before day 40 it says mail it certified; between day 40 and day 45 it says hand delivery or a carrier is safer, because mail now counts only once it arrives; after day 45 it says plainly that a late notice is "a complete defense to enforcement of a lien". The contractor's copy doesn't keep the reminder open, since only a sub-subcontractor or a supplier to a subcontractor owes it, but the reminder names it.

Not covered yet: attaching the mail log or tracking printout to each record (California's records already take files), § 713.18(3)'s rule for a notice returned "refused" or "unclaimed", and the combined notice to contractor on bonded and public jobs (§ 255.05, § 713.23).

PayApps is open: pay applications with retainage and change orders are free on one job, no card. Lien waivers, notices, QuickBooks and job costing are in the paid plans, which are not on sale yet. Start free in PayApps. This is general information about the statute's text, not legal advice. Whether a notice is required on your job, and who must get it, depends on your contract chain, so check with a Florida construction attorney when the money matters.