On a private Texas job, a subcontractor's monthly notices of claim protect the money billed each month. Retainage, the 5 or 10 percent the GC holds back until the end, needs a notice of its own. It also runs on a different, shorter clock. That clock starts when your work ends, which is often when the office has stopped watching the job.
This post quotes Texas Property Code chapter 53 as amended by H.B. 2237, which covers original contracts entered into on or after 1 January 2022. We read it from the Texas Legislature's statute site on 2026-11-27 (chapter 53). Every date below comes from the same code PayApps runs.
Who needs the retainage notice
Section 53.057(a): "To the extent that a claim for unpaid retainage is not included wholly or partly in a notice provided under Section 53.056, a claimant other than an original contractor whose contract provides for retainage must give notice under this section for a lien for unpaid retainage to be valid."
Three things follow from that sentence:
- It applies to subcontractors and suppliers at any tier, not to the GC (the "original contractor").
- It applies only if your contract provides for retainage.
- A monthly notice that already claimed the retainage covers it. Most monthly notices claim the month's unpaid billing, which leaves the retainage out, so most subs need this notice too.
When it is due
Section 53.057(a-1): the notice goes "to the owner or reputed owner and the original contractor not later than the earlier of: (1) the 30th day after the date the claimant's contract is completed, terminated, or abandoned; or (2) the 30th day after the date the original contract is terminated or abandoned."
So the date usually runs from your contract, not the whole project. A drywall sub that finishes in March has until about mid-April, even if the building keeps going for six months.
The second branch only shortens the deadline. If the GC's contract with the owner is terminated or abandoned before yours ends, your 30 days run from that date instead. An original contract that is simply completed does not start this clock; it starts the affidavit's (below).
A deadline that lands on "a Saturday, Sunday, or legal holiday" moves to the next day that is none of them (§ 53.003(e)). Texas legal holidays are those in Gov't Code § 662.021, which include Confederate Heroes Day, Texas Independence Day, San Jacinto Day, Emancipation Day and LBJ Day as well as the national holidays.
| Your contract ended | 30th day | Last day to send |
|---|---|---|
| 4 Dec 2026 | Sun 3 Jan 2027 | Mon 4 Jan 2027 |
| 15 Jan 2027 | Sun 14 Feb 2027 | Tue 16 Feb 2027 (past Presidents' Day) |
| 21 Apr 2027 | Fri 21 May 2027 | Fri 21 May 2027 |
| 1 May 2027 | Mon 31 May 2027 | Tue 1 Jun 2027 (past Memorial Day) |
| 26 Oct 2027 | Thu 25 Nov 2027 | Mon 29 Nov 2027 (past Thanksgiving and the Friday after) |
By certified mail, "deposit or mailing of the notice in the United States mail in the form required constitutes compliance" (§ 53.003(c)). The last day to mail is the last day.
The form
Section 53.057(a-2) gives the wording, headed "NOTICE OF CLAIM FOR UNPAID RETAINAGE", with the warning "This notice is provided to preserve lien rights." It has lines for the date, the project description or address, the claimant's name, the type of labor or materials, the original contractor's name, the party you contracted with if different, the "Total retainage unpaid", and your contact person and address. You may attach an invoice or billing statement (§ 53.057(a-3)).
The affidavit comes later
A notice is not a lien. If the retainage is still unpaid, § 53.052(d) sets the filing date: "not later than the 15th day of the third month after the month in which the original contract under which the claimant performed was completed, terminated, or abandoned." This one runs from the GC's contract, including a normal completion. Section 53.057(f) then requires "the notice of the filed affidavit as required by Section 53.055."
| Original contract ended in | 15th of the third month after | Last day to file |
|---|---|---|
| December 2026 | Mon 15 Mar 2027 | Mon 15 Mar 2027 |
| February 2027 | Sat 15 May 2027 | Mon 17 May 2027 |
| May 2027 | Sun 15 Aug 2027 | Mon 16 Aug 2027 |
| September 2027 | Wed 15 Dec 2027 | Wed 15 Dec 2027 |
What we added to PayApps
PayApps already printed both Texas notices word for word and kept a log of each one sent, by recipient and month, with a reminder before every monthly date. The retainage notice had no reminder, because nothing in the job said when the contract ended.
Now, on a Texas job's notice log, you save the day your contract was completed, terminated or abandoned, and the day the GC's contract ended and how. PayApps works out:
- the retainage notice date, from your contract or, if sooner, a terminated or abandoned original contract;
- the retainage lien affidavit date, from the original contract;
- both moved past weekends and Texas legal holidays.
While the latest pay app shows retainage held, the cash page and the weekly email carry the retainage notice from the day you save the date until you record a notice to both the owner and the GC. A missed date stays on them for 30 days. The affidavit appears in the 30 days before its date. That includes closed jobs, since a finished job still holding retainage is the usual case. A future date is refused, because a planned finish entered early would start the clock on the wrong day.
PayApps does not decide whether the statute applies to your job (a public job, a pre-2022 contract, or a subcontract with its own terms changes things). It works out the dates from what you enter and cites each section. It is not legal advice, and a construction lawyer in Texas is the person to ask about a specific claim.
The free Texas lien notice guide gives the same dates without an account. PayApps is free on one job. The Texas notices and the notice log are on the Crew plan and up.