Retainage is the 5 or 10 percent of every progress payment an owner holds back until a job is done, and the general contractor usually holds the same back from its subs. For a specialty subcontractor that is often the whole margin on the job, sitting in someone else's account for months.
The new pay app guides add a free schedule-of-values calculator and four guides. The retainage guide's table reads each state's own statute, and it says something worth knowing before you sign a subcontract on public work.
Five percent is the usual ceiling now. Of the first sixteen states in the table, ten cap public retainage at 5% of each payment: California (Public Contract Code §7201), Florida (§255.078), New York (General Municipal Law §106-b), North Carolina (G.S. 143-134.1), Virginia (§2.2-4333), Washington (RCW 60.28.011), Massachusetts (c.30 §39G), Minnesota (§15.72), Oregon (ORS 279C.570) and Utah (§13-8-5), which also caps the total at 5% of the contract price. Nevada holds 5% until the job is half done and may stop after that (NRS 338.515). Texas allows 10% on contracts under $5 million and 5% above. Pennsylvania, Illinois and Arizona start at 10% and step down at 50% complete; Michigan stops withholding new retainage at 50% complete.
The cap often flows down. California and Texas say outright that the prime may not hold more from a sub than the owner holds from the prime, and New York applies the same 5% rule from contractor to subcontractor. Utah goes furthest: its 5% cap covers private nonresidential jobs as well as public ones, applies between subs, and a lower owner rate flows down. Minnesota makes the prime cut subs' retainage whenever the agency cuts its own, and pay it out within 10 days of receiving it. A 10% retainage clause in a subcontract on a 5% public job is worth asking about.
Some details are moving. Florida used to allow 10% until a job was half done; the current text says 5%. North Carolina's small-project exemption reads $150,000 in the statute text we found, while a 2025 session bill (H1123) changes the threshold. The guide says so rather than picking one.
"Reduced at 50%" can mean two different numbers
Added 2026-11-25. A clause that drops retainage from 10% to 5% once the job is half done can be read two ways, and they bill differently.
Take a $100,000 subcontract with $70,000 completed:
- The reduced rate on everything billed. 5% of $70,000 is $3,500 held. The application releases part of what earlier ones held.
- The reduced rate only on work completed after the halfway point. The first $50,000 stays at 10% ($5,000) and the $20,000 after it is held at 5% ($1,000): $6,000 held. Nothing already held comes back early. A statute that stops withholding new retainage at 50%, as Michigan's does in the table, is this reading with 0% after the point: $5,000 stays held however far the job goes.
That $2,500 gap is on one application for one sub. If your sheet uses one reading and the owner's reviewer uses the other, the application gets sent back. The contract decides which applies, and the pay application generator now does both. Under "The reduced rate applies to", choose everything billed or only work completed after that point. In the second mode, each line's share of the amount past the point is in proportion to its work billed. With no stored materials and no per-line rates, that makes the total exact. The generator shows the split in a note, uses it to estimate previous certificates, and carries the mode into next month's application. The Excel download writes the split as live formulas: the reduced rate and the completion point are cells on the continuation sheet, so changing a number in Excel still gives the right retainage. LibreOffice recalculated the workbook from its formulas alone and matched the page to the cent, on a case with stored materials and a line with its own rate.
One limit: the tool assumes the reduction began exactly at the completion point. If the owner applied it from the next application instead, enter the previous certificates from your last application, and the payment due will be exact again.
How the table was made: each row links the legislature's own published statute. The first twelve were read on 2026-11-24 through search results limited to the official legislature domains, because the pages themselves would not load. On 2026-11-25 they did: nine of the twelve rows matched the statute text as written, and California, Pennsylvania and Illinois still refuse automated loads, so the page says which rows rest on which reading. Minnesota, Nevada, Oregon and Utah were added the same day from the statute pages directly. Georgia and New Jersey are still left out because their current text could not be confirmed. Check the linked statute before relying on a row; it is a summary, not legal advice.
Seven more states, and Ohio's rule changed in 2025
Added 2026-11-28. The table had 23 states after this addition (25 with the two below). The seven new rows were each read from the statute page on the legislature's own site, and the text read is kept beside the guide in sources/retainage-caps.txt:
- Iowa holds the least: 3%. Iowa Code §573.12 lets a public owner keep no more than 3% of each monthly payment, and the prime no more than the lesser of 3% and the subcontract's rate from a sub. The figure is in the 2026 Iowa Code, whose history note lists an amendment to those paragraphs by 2025 Acts, chapter 29; check a subcontract form older than that against it.
- Five at 5%: Delaware (29 Del. C. §6962(d)(5), state agencies' large public works contracts, with 60% of what is held releasable on completion), Idaho (Idaho Code §54-1926(3), which caps prime-to-sub retainage at 5% too and makes the prime pay it within 30 days after the subcontract is done), Maine (5 M.R.S. §1746, held until the State accepts the project), Missouri (RSMo §8.960, formerly 34.057; up to 10% on contracts too small to need a bond, $50,000 or less) and Kansas (K.S.A. 16-1904, 5% unless a higher rate up to 10% is needed to ensure performance; roads and bridges are outside the act, and its rights cannot be waived by contract).
- Ohio splits labor and materials. Ohio Rev. Code §153.12 pays labor at no less than 96% of the approved estimate, and §153.14 pays for materials delivered but not yet installed at 92% of invoice. No subcontract may be paid at a lower rate than the contractor.
Ohio subs: the 50% rule is gone. Until 30 September 2025, §153.13 said that once a contract was half complete "no further funds shall be retained" and what had been held went into escrow. House Bill 96 rewrote the section: the current text keeps the release dates (retainage and its interest on the substantially completed portion within 30 days, the rest within 30 days of final completion) and drops the 50% stop and the escrow. An estimator or a contract template written before then may still promise the old rule. Both versions are on codes.ohio.gov and quoted in the sources file.
South Carolina and North Dakota
Added 2026-11-28, later. Two more rows, read the same way and quoted in the same sources file:
- South Carolina holds 3.5%. S.C. Code §11-35-3030(4), in the State Consolidated Procurement Code, says the amount retained from each progress payment "must be no more than three and one-half percent", and it says so of a "contract or subcontract", so the same limit reaches what a general contractor holds from a sub. On a state job each contractor's or sub's work counts as its own division: when a division is certified complete, its retainage goes to the prime, who has ten days to pass it on. Only Iowa's 3% is lower in the table.
- North Dakota stops at 50%. N.D. Cent. Code §48-01.2-13 holds "ten percent of each estimate until the project is fifty percent completed", then no further retainage unless unsatisfactory progress or performance is documented. At 95% complete the governing body may pay up to 95% of what it holds, and an approved estimate left unpaid more than 30 days earns interest (§48-01.2-14).
PayApps' public-job check uses the same rows: mark a job state or local in South Carolina and a 5% rate is flagged as over the cap; in North Dakota a 10% rate is within it, with the note that retainage stops at 50% complete.
Some states set when retainage is paid without capping the rate. Vermont's 9 V.S.A. §4005 is one: retainage is paid within 30 days after final acceptance and passed down within 7 days, but no percentage is set, so it is not in the table.
The other three guides cover how to fill out a pay application line by line, conditional vs unconditional lien waivers (California's four statutory forms and Florida's §713.20), and how change orders flow into the schedule of values. The calculator runs in the browser and uploads nothing.
PayApps, our hosted pay-app billing for subcontractors, is open: the schedule of values, retainage (per line, with its own rate where the subcontract sets one) and change orders are free on one active job, with no card (start free). Lien waivers across every job are on the paid plans, which are not on sale yet.