Written by an AI agent working in this repository. Your subcontract and the GC's schedule specification decide what schedule you owe and when. A lookahead you keep is your own planning record, not a schedule submission and not a delay notice.
Most GCs run their weekly coordination meeting from a three-week lookahead: the next three weeks of work, with a bar for each working day. The GC builds it from its master schedule, usually in Primavera P6 or Microsoft Project. (If you have the GC's P6 file, our P6 lookahead post shows how to build one from the XER.) Few trade subcontractors have a P6 seat, though. The electrical or drywall foreman walks in with a marked-up printout, or with nothing, and the GC's dates for your work become the only dates on the table.
A short schedule of your own fixes that. It doesn't need to be a CPM network. It needs your activities, in the order your crews do them, with dates you can defend.
What to put on it
- Activities at the level your crew works. "Rough-in level 2", "rough-in inspection L2", "cover inspection", "set fixtures level 2", not "electrical". If a pay application line or a GC milestone depends on it, give it its own activity.
- Who does it. The crew or foreman ("Crew A, Luis"). When two jobs want the same crew in the same week, that column is where you see it.
- Start and finish dates, both inclusive. Count workdays, not calendar days: five workdays from a Monday finishes that Friday.
- What each one waits for. Most of your sequence is finish-to-start: the inspection waits for the rough-in, the cover waits for the inspection. Note any lag, such as a day for the inspector to come or curing before you cover.
- Percent complete, updated weekly. It should agree with what you bill. If the lookahead says rough-in is 30% and the pay application bills 60%, the GC will notice.
Check the sequence
The most common error in a hand-kept schedule is an activity starting before the one it waits for has finished. Usually it was right once, and then the predecessor moved and this one didn't. For each activity with a predecessor, the earliest start is the workday after the predecessor finishes, plus the lag. Anything that starts earlier is out of sequence, and you should fix it before the meeting, not in it.
When the GC slips, move everything after it
When the GC's schedule slips (the deck pour moves a week, the framing inspection fails), your next activity moves, and so does everything that waits on it. In a spreadsheet that means retyping a column of dates and missing one. Instead, move the first affected activity by a number of workdays and let everything downstream move by the same amount. Work that is already done stays where it happened.
Each move is a schedule impact worth recording. Your subcontract's notice clause, not the lookahead, decides whether you are owed time. Write a dated note of what moved and why, and cross-check it against your daily reports for those days.
Take the holidays out
A workday count that ignores holidays is off by one every time it crosses one. Five workdays from Monday 23 November 2026 finish on Friday the 27th by the calendar, but if your crews are off for Thanksgiving and the day after, the work finishes on Tuesday 1 December. The activity that follows a Wednesday finish starts the next Monday, not Thursday.
Start from the federal list, then cut it down to the days your crews actually take. The eleven legal public holidays are in 5 U.S.C. § 6103(a). When one falls on a weekend, federal offices observe it on the Friday before a Saturday or the Monday after a Sunday, so Independence Day 2026 is observed Friday 3 July. Many subcontractors work Columbus Day and Veterans Day, and some union agreements add the day after Thanksgiving. Your company calendar decides; the federal list is only a starting point.
Tie each lost hour to the activity it held up
When you ask the GC for more time, the first question is which work was held up, on which days, and by how much. A daily report that says "lost 6 hours, waiting on framing" answers the "how much". It does not say which of your activities stood still, and three weeks later nobody remembers whether that was the level 2 rough-in or the level 3 boxes.
So on the day it happens, write the hours lost on the daily report and name the activity they held up. At the end of the slip you then have, per activity:
- the days it was held up, oldest first;
- the hours lost each day, and which days a foreman noted a delay without the hours;
- the delay in the foreman's words, and the weather, from the same report.
That list is the backup a time-extension change order needs. It is a record, not an answer: hours lost are not days of contract time, and a delay to one activity may not move your finish at all if other work can go on. How many calendar days to ask for is your call, made against the schedule and the subcontract, and many subcontracts only grant time if written notice went to the GC within a set number of days of the delay starting. Keep the log and send the notice; one does not replace the other.
Start from the GC's P6 file when you can get it
Many GCs will send their P6 export (an .xer file) if you ask. Only a few of its activities are yours, and P6 holds things a sub's own schedule doesn't need:
- Which dates. An activity that has started has an actual start. One that is complete has an actual finish. Use those first. For open work, P6's remaining dates reflect the last update, and the early and planned dates come after them. A finish milestone such as "Rough-in inspection" has only a finish date, so it is one day.
- Which links. P6 activities can wait for several others, linked four ways (finish to start, start to start, finish to finish, start to finish), with leads and lags in hours. For a sub's lookahead, the finish-to-start link that allows the latest start is the one that matters. Lag hours turn into workdays at the activity's calendar: 20 hours on a four-tens calendar is 2 workdays, not 2.5. Write the other links down rather than dropping them.
- What to leave out. Level-of-effort activities (supervision, general conditions) and WBS summaries span other work. They are not tasks your crew starts and finishes.
- The next update. The GC re-issues the schedule after each update. Match each activity by its P6 activity ID, which doesn't change, not by its name, which sometimes does. Then the new dates replace the old ones and your own notes stay.
What to bring to the meeting
- The next three weeks of your open activities, with a bar per workday.
- Anything late, shown to today, so it doesn't drop off the sheet because its finish date passed.
- What each activity waits for, so a GC-side constraint (an area not turned over, a missing inspection) is visible as the reason, not as your delay.
- The date it was printed.
Every job, by crew
The GC's lookahead covers only the GC's job. A subcontractor with more than one job has a question no GC asks: where is each crew next week? Crew A could be on the clinic Monday to Wednesday and on the school from Wednesday, and nobody notices until Wednesday morning.
So keep one more view: the open activities from all your active jobs, grouped by crew instead of by job. For each crew it shows its open activities on every job for this week and next, as bars over the workdays, and the days it has work on two jobs at once. Two jobs on one day is not always a problem (a crew of six can send two to the school for a morning), but it should be a choice someone made, not something the foreman finds out on site.
The grouping only works if each crew is written the same way on every job. "Crew A" on one job and "Electrical crew 1" on another are two crews to any list. Pick a short name per crew or foreman and use it everywhere.
In PayApps
Job schedules are now part of PayApps, the pay-application and job-paperwork tool in development for subcontractors, on every plan:
- activities per job, numbered A-001 onward, with trade or crew, start and finish, percent complete, and optionally the activity each waits for and a lag in workdays;
- each activity's status for today (not started, in progress, done, late start, past finish), and a flag on any activity that starts before its predecessor finishes, with its earliest start;
- "Move with what follows": one activity and everything downstream of it moved by N workdays (or pulled in), with done work left in place and lengths kept;
- the three-week lookahead drawn as bars on the job page, a landscape PDF of it (up to six weeks) for the GC's meeting, and the whole schedule as CSV.
- a company holiday list (added 2026-11-27): type the days you take off, or add the federal holidays for a year and delete the ones your crews work. Every workday count, sequence check, move and lookahead skips them, and the PDF names the holidays it left out;
- a crew lookahead across every active job, grouped by the crew typed on each activity (capitals and spacing ignored, so "Crew A" and "crew a" are one crew), with the days a crew has work on two or more jobs, and a PDF for the Monday crew meeting. The Free plan has one active job, so this page matters once you are on a paid plan;
- delays by activity (added 2026-11-27): a daily report names the activity its lost hours held up, the schedule lists the days and hours per activity, and the delay log (each day's hours, weather and the delay as written) prints as a PDF for one activity or all, in a date range. On a change order, "Attach the delay log" keeps it with the change order's files as backup. It adds up what was typed and never turns hours into days;
- the GC's P6 schedule imported (added 2026-11-27): choose the
.xerfile, find your activities by ID, name or WBS, and tick them. The file is read in your browser and is not uploaded. Dates, percent complete and the driving finish-to-start link come across, and any other links are listed in the notes. Importing the GC's next update matches activities by P6 activity ID and updates them, keeping your trade and notes. Typed activities stay as they are.
Weekends are skipped, and so are the holidays you list. Nothing else is assumed. Dates are the ones you type: nothing is scheduled for you.
The job schedule is on every plan, and PayApps is open: free on one active job, with no card. Start free. The paid plans (more jobs and users, lien waivers, QuickBooks and job costing) are not on sale yet.