Written by an AI agent working in this repository. Not legal advice: your subcontract decides how and when a delay or a change must be noticed, and a daily report is not that notice.
Arguments with a GC usually come down to one day. A change order is questioned: did your crew really spend two days on that reroute? A delay is in dispute: were you rained out, or waiting on the drywall sub? A pay application is cut: was level 2 really 60% roughed in by the 25th? The superintendent remembers one version. Whatever was written down that day is the best evidence anyone has, and on many subcontractor jobs nothing was.
The GC keeps its own daily log. Its log records what the GC saw, from its point of view. Yours should record what your crew did.
What to write each day
Short is fine. What matters is writing it every working day, the same day.
- Date and weather. Conditions as you saw them ("rain after 1 pm, wind 15 mph") and the high and low. Write what happened on site, not what a forecast said.
- Hours lost. If weather, access or another trade stopped work, how many hours. Zero is worth writing too: it shows you checked.
- Crew on site. For each company and trade: how many workers and the hours each worked. That's your own crew, plus anyone working for you (a lift operator, a lower-tier sub). Man-hours follow from workers × hours.
- Work performed. Where and what: "pulled feeders to panels L1 and L2; set boxes level 2, grid C–F". Quantities help when a percent complete is questioned later.
- Delays and problems. Waiting on another trade, no access to an area, missing material, drawings that don't match the field.
- Equipment. Lifts and rentals especially: they cost money by the day.
- Deliveries. What came, from whom, any damage or shortage.
- Visitors and inspections. The inspector and the result, the GC's superintendent, the owner's rep. Write down any direction given on site and who gave it.
- Safety. The toolbox talk, any incident, any near miss.
- Notes. Anything else, especially extra work someone asked for verbally. That's the work that most often never reaches a change order (see T&M tickets and RFI answers).
Keep the photos with the day
A photo is the one thing a GC can't easily argue with, but only if you can say which day it was taken and what it shows. Photos left in a foreman's camera roll get mixed up with other jobs, and nobody can find them when they're needed. Keep them with that day's report:
- Before you cover anything up. Rough-in before the drywall goes on, the slab before it's poured, the conduit before the trench is backfilled. Once it's hidden, the photo is all the proof you have.
- The condition that stopped you. The standing water, the blocked area, the missing embed, the other trade's work that wasn't done. Take a wide shot that shows where you are, then a close-up.
- Extra work before and after. If someone asked for work verbally, photograph the area before you start and again when you finish. Those are the photos a T&M ticket or change order request needs.
- Paper from the day. Delivery tickets, especially short or damaged loads, and the inspector's sign-off or correction notice. A photo of the paper is enough.
A dozen photos a day is plenty. Very large photos make a PDF too heavy to email, so they can be shrunk before upload without losing anything you'd need on a printed page.
The day nobody wrote
A report that's missing on the one day that ends up mattering is the usual failure. So the log should show the gaps: the weekdays since the job's first report that have no report at all. A gap caught on Wednesday can still be filled from memory and the foreman's texts. One found in a dispute months later can't.
Leave the company's holidays out of the count. A GC that asks for a report every workday doesn't expect one on Thanksgiving, and a list that flags every holiday trains people to skip it. The simple way is one list of the days your company takes off, kept where the schedule already reads it, so the lookahead and the daily log agree on what a workday is. A report written on a holiday still counts. Days your crew wasn't scheduled, which no calendar knows about, will still show as gaps. That's fine: a gap is a question to answer, not an error.
Check once a week, not only when you open the log. Monday morning is a good time: last week's missed days are still fresh, and a short report saying "no crew on site" closes a gap as surely as a full one. It also answers the question before anyone asks it.
Make it quick enough that it gets done
Daily reports get skipped when they take too long. Two things help:
- Start from yesterday. On most days the crew and the equipment on site are the same as yesterday, so copy them and type only what changed. Don't copy the weather or the work, though: those have to be that day's.
- Send them in batches. Some GCs want a week's reports every Monday, and a month's reports make good backup for the pay application. One PDF for a date range saves sending twenty attachments.
What a daily report is not
A daily report is a record. It isn't a notice. Most subcontracts require written notice of a delay or a change within a set number of days, delivered in a set way, often to a named person. "Rained out 4 hours" in your daily report is good evidence that the rain happened. On its own it usually doesn't give the notice your subcontract asks for. When a day's report shows lost time or extra work, read the notice clause and send the notice it describes. If a claim is building, talk to a construction attorney before the deadline in that clause passes.
In PayApps
Daily reports are now part of PayApps, the pay-application and job-paperwork tool in development for subcontractors, on every plan:
- one report per job and day, with the fields above, crew lines by company and trade, and man-hours totalled per day and for the job;
- the weekdays since the first report with no report, listed on the log, each a click away from a new report. The company's holidays (the same list the job schedule uses) are left out, and the log names the ones it skipped (added 2026-11-27);
- the weekly email lists last week's missing weekdays per job, less the company's holidays, linked to that job's log. Only jobs someone is still logging (a report in the last 14 days) are listed, and missing days alone never send the email, since a sub isn't on site every weekday;
- "New, with the crew from yesterday" copies the crew and equipment, nothing else;
- photos and files kept with each report: the phone's camera opens from the report, large photos are shrunk before upload, and delivery tickets and inspection reports go in as PDFs or photos;
- "PDF + photos": the report, an index page, then its photos and files in one PDF for the GC;
- every report written, changed or deleted, and every photo added or removed, is in the job's history with who did it and when, so an edit made after the day is visible;
- a PDF per report, one PDF for a week or a month (up to three months), and the whole log as CSV;
- the weather is what you type: nothing is fetched or filled in for you.
Daily reports are on every plan, and PayApps is open: free on one active job, with no card. Start free. The paid plans (more jobs and users, lien waivers, QuickBooks and job costing) are not on sale yet.