Close-out documents: what a subcontractor sends to get retainage released

The close-out documents a subcontract usually asks for, where to find the list, how to deliver them as one binder, and what to send with the release request.

Written by an AI agent working in this repository. Not legal advice: your subcontract and the spec's close-out section decide what is owed and when retainage is due.

Retainage is the last money on a job and usually the slowest. Each pay application held back a share of what you billed, often 5 to 10 percent, and the GC releases it when close-out is finished. On a long job, that can be your whole margin. Most of the delay is paperwork: the punch list isn't signed off, or one document is missing (a warranty letter, a manual, a final waiver), and nobody notices until you ask for the check.

Where the list comes from

There is no single standard list, so read the job's own documents:

  • The subcontract. Look for a close-out exhibit or clause, and for the conditions on final payment and the release of retainage.
  • The spec. On jobs that use the MasterFormat numbering, Division 01 has the general rules, usually in sections 01 77 00 (Closeout Procedures) and 01 78 00 (Closeout Submittals). Each technical section of your scope often lists its own warranty, manuals or extra stock as well.
  • The GC's close-out letter or log, if it sends one. Compare it with the two above: it may ask for something your subcontract doesn't, or leave something out.

Write down where each requirement comes from ("Subcontract Exhibit D", "Spec 26 05 00, 1.6"). When the GC asks for something new at the end, you can point to what was actually required.

The documents most subcontracts ask for

  • Warranty. A letter on your letterhead with the start date (usually substantial completion) and the term, plus any manufacturer warranties the spec calls for.
  • Operation and maintenance (O&M) manuals. Product data, maintenance schedules and parts lists for the equipment you installed. GCs often want them as one PDF with a table of contents.
  • As-built drawings. The field changes marked on the drawings: where the conduit, pipe or duct actually went.
  • Attic stock. Extra material the spec asks you to leave (ceiling tile, carpet, lamps, fittings). Get a signed receipt from whoever takes it, and take a photo when it's delivered.
  • Test and start-up reports. Megger tests, pressure tests, balancing reports and start-up sheets.
  • Owner training. The sign-in sheet and agenda for the training session, if the spec calls for one.
  • Final inspection sign-off. The inspector's final card or report for your permit.
  • Final lien waiver. Usually conditional on the final payment, on the form your state requires where it has one. On some jobs, the waivers from your own suppliers and sub-subs too.
  • Consent of surety. On a bonded job, the surety's consent to final payment.

Some won't apply to your job. Write down why ("no equipment to train on") instead of just leaving it off the list. That way, the question doesn't come up again a month later.

Close the punch list first

The documents are usually the slow part, but the punch list is the gate GCs name first. A few habits keep it from staying open for weeks:

  • Walk your own scope before the GC does. Your list is shorter than theirs, and you can schedule it.
  • Get the GC's list in writing, numbered, with a due date on each item, the day of the walk. Without a due date nothing is ever late, and nothing is ever finished.
  • Push back on items that aren't yours that same week, in writing. A damaged ceiling tile from another trade stays on your list until someone moves it.
  • Record when each item was fixed and by whom, then ask for one back-check per batch. One email naming every fixed item gets them walked together.
  • Get each item initialled or accepted with a name and date. That's what you point to when retainage is held "for the punch list".

The free punch list tracker reads the list as the GC emailed it (or as a table), shows each item as open, overdue, done and waiting on the back-check, accepted, or not yours, and writes the back-check email and a CSV with a column for the GC's initials. It runs in the browser and uploads nothing.

Deliver them once, as one package

Documents sent one at a time over six weeks, to different people, get lost. Then the GC's project manager asks for the warranty you already sent. It works better to send everything together, once the punch list is accepted:

  1. A transmittal on top. One page that lists every document with where it's required, and for each one the date it was due, sent and accepted. Documents that don't apply go on the list too, with the reason.
  2. An index. What follows, in order, with page numbers.
  3. The documents themselves, in the same order as the transmittal.

The GC can check one package against its log instead of searching its inbox. If a GC can only take documents through its own portal, upload them there and keep the same transmittal for your records.

Keep the GC's receipt or acceptance when it comes back, but don't add it to the package itself. It's the GC's document, and it's your proof that the package was delivered and when.

Then ask for the release

When the work is fully billed, the punch list is accepted and every document is in, ask in writing. Address it to the GC's project manager and state the retainage held, the punch list's state, and each document with the date it was sent and accepted. Say what you delivered. Don't claim the subcontract's conditions are met: that's for the GC and the contract to decide. Then bill the release on your next pay application, the way your subcontract asks for it. If you use QuickBooks Online, which has no retainage field, see how subcontractors track retainage in QuickBooks.

If the GC holds retainage long after close-out, look up your state's prompt-payment law. Many states set a deadline for releasing retainage (see prompt payment laws for subcontractors), but whether it covers your job depends on the state and the type of project.

In PayApps

PayApps, the pay-application and job-paperwork tool for subcontractors, has a close-out checklist on every job, on every plan:

  • the standard list (warranty, O&M manuals, as-builts, attic stock, final inspection, final waiver, plus consent of surety on a bonded job) added in one click, and any other document typed in with where it's required;
  • each document marked sent, then accepted, or not required with the reason; overdue ones are flagged;
  • the checklist read with the punch list and the retainage held on your latest pay application, with what still stands in the way listed in plain words;
  • new: the documents themselves kept with each item (the PDF as sent, photos of attic stock delivered, the GC's receipt when it comes back), counted against your company's file storage;
  • new: one close-out binder PDF: a transmittal listing every document and its dates, an index, then each required document's files in checklist order (without the GC's receipts);
  • every file added or removed is recorded in the job's history;
  • once nothing stands in the way, an email to the GC's project manager asking for the release, drafted from what you entered.