How many days a GC has to pay you, read from seven states' prompt payment laws

Texas gives a GC 7 days, Illinois 15. Prompt payment deadlines in seven states, and which states void pay-if-paid clauses, with a clause reader.

Written by an AI agent working in this repository. Not legal advice: these laws have exceptions, and your subcontract can change what they give you. Ask a construction attorney in your state before relying on them.

A subcontractor's pay application is approved, the owner pays the GC, and then the money sits. Most states have a law about exactly that: a prompt payment statute that says how many days the GC has to pass the owner's payment down, and often what interest it owes when it is late.

We read seven of them on 2026-11-25 and put them in a free guide, prompt payment laws for subcontractors, with a calculator for the interest on a late payment.

StateGC must pay the subInterest when late
Texas (Prop. Code ch. 28)7 days after receiving the owner's payment1½% each month
California (B&P Code §7108.5)7 days after each progress paymentnot confirmed in the current text we read
Illinois (815 ILCS 603)15 days after the contractor is paid10% a year
North Carolina (G.S. 22C)7 days after each payment1% a month or part of a month
Pennsylvania (CASPA)14 days after payment or after your invoice, whichever is laterthe Act's section 5(d) rate (figure not confirmed)
Virginia, public work (§2.2-4354)interest on amounts unpaid 7 days after the GC is paid1% a month unless the contract says otherwise
Florida, local government work (§218.735(6))10 days after the contractor is paidnot confirmed

Three things worth knowing:

  • The clock starts when the GC is paid, not when you bill. So the question to ask every month is when the owner paid. On public jobs that is often a public record.
  • The interest adds up. At Texas's rate, $40,000 paid 45 days late carries $900 of interest. North Carolina counts every part of a month as a full month, so 31 days late is two months.
  • Written notice matters. Texas lets a sub suspend work 10 days after written notice of nonpayment, Illinois after 7 days' notice. Send it in writing even when the call was friendly.

What we could not check. The legislature sites could not be opened directly from where this was written, so each row was read through search results limited to the official sites. Where those results did not show a rate (California's current penalty, Pennsylvania's section 5(d) figure, Florida), the guide says "not confirmed" and the calculator leaves the rate for you to type, rather than repeating a figure from a secondary site. Georgia, New York and Massachusetts are left out for the same reason.

When the subcontract says "only if the GC is paid"

The deadlines above assume the GC was paid. The harder case is when the owner never pays, and the subcontract's payment clause decides who carries that. A pay-when-paid clause ("within 7 days after Contractor's receipt of payment") only sets the timing: courts reading one, such as the Florida Supreme Court in Peacock (1977) and the federal Sixth Circuit in Dyer (1962), held the GC still owes the sub within a reasonable time. A pay-if-paid clause ("receipt of payment is a condition precedent", "Subcontractor assumes the risk of Owner's nonpayment") tries to make the owner's payment a condition of yours.

Whether it holds depends on the state. Of the eleven rules we read on 2026-11-25:

RuleStates
The condition is unenforceableNorth Carolina (G.S. 22C-2), South Carolina (§29-6-230), California (Clarke, 1997), New York (West-Fair, 1995)
Condition void, a delay until the GC is paid allowedWisconsin (§779.135(3))
No defense to your mechanics lien (Maryland: lien or bond) claimIllinois (770 ILCS 60/21(e)), Maryland (Real Prop. §9-113), Missouri (§431.183)
Outside date anywayNevada (NRS 624.626: 45 days after the 25th of the month you billed, even under an "only if or when paid" clause)
Read as timing unless the words clearly shift the riskFlorida (Peacock), Ohio law as read by the Sixth Circuit (Dyer)

The free pay-if-paid vs pay-when-paid clause reader takes a pasted payment clause, says which kind its words make it, quotes the words that decided it, and shows the rule for the project's state with the link to the statute or opinion. It looks for the wording courts have pointed to; it does not read the whole subcontract, so its answer is a starting point for a conversation with the GC or an attorney. In the three lien-only states the clause can still meet a plain contract claim, which is one more reason to keep the lien deadlines.

When the GC pays you and your supplier with one check

Sometimes the money arrives, but as a joint check: one check made out to the sub and its supplier, so the supplier has to endorse before the sub can deposit it. GCs use them so they do not pay twice when a supplier files a lien for material the GC already paid for. The risk sits with the supplier. Under the "joint check rule", as the California Supreme Court put it in Post Bros. Construction Co. v. Yoder (1977) 20 Cal.3d 1, a supplier that endorses with no agreement on the split is treated as paid, and in that case lost both its lien and its bond claim on $54,000 of checks the sub deposited. The court's own advice: refuse to endorse "until assured by escrow of other arrangement" of your share.

How far other states go is less settled. A 2018 handout by surety and construction counsel, hosted by the AGC, groups them: California, Iowa, Louisiana, Missouri, South Carolina, Texas and Washington apply the rule for the contractor and its surety; Arizona, Arkansas and Oregon do not treat endorsement as a lien waiver; Delaware and Maryland void such a waiver; and on federal Miller Act jobs endorsement alone does not waive bond rights. We have read the California opinion and the handout, not every state's cases, and the guide says so.

The free joint check splitter takes the check and what each supplier is owed on the job, splits it (pro rata to the cent when the check is short), shows how much a supplier puts at risk by endorsing with nothing in writing (what it was owed, up to the check, less what it actually gets), says which waiver each payee signs, and writes a one-page split letter for all three to sign before anyone endorses.

Before any clock starts: the GC's billing cutoff

Every deadline above counts from a payment that only happens if your pay application made the GC's billing cycle. Subcontracts and GC billing instructions commonly name a cutoff day ("pay applications are due by the 25th"), because the GC folds every sub's application into its own monthly application to the owner. One that arrives after the cutoff often waits for the next month's draw, so a few days late on the paperwork can mean a month late on the money, and no prompt payment statute helps with that month, because the GC was never paid for your work.

So PayApps (updated 2026-11-26) takes the cutoff day on each job, from the subcontract or the GC's instructions. The job page shows the next cutoff and whether this cycle's application has gone out. A week before each cutoff, if nothing has been submitted, the cash page and the optional Monday email say so, naming the draft that is waiting or saying none is started. If a draft dated before a cutoff is still unsent once the cutoff passes, they say it missed it and suggest asking the GC whether it can still go in this month's draw. A month with nothing drafted is never called missed, since there may have been no work to bill. A day like the 31st falls on the last day of shorter months.

Interest on a late pay app, kept on the job (added 2026-11-27)

The calculator in the guide answers one question about one check. A sub with six jobs and a GC that pays slowly on all of them needs the running number, so PayApps now keeps it. On each job you set the late-payment rate: the one in your subcontract's late-payment clause, or one of the four statutory rates above that we could confirm (Texas 1½% a month, Illinois 10% a year, North Carolina 1% a month or part of a month, Virginia public work 1% a month), each with its link and what to check before relying on it. PayApps does not decide whether a statute covers your job; you do, or your attorney does.

The cash report then shows the interest accrued on every past-due application: simple interest from the day after it was due, on the balance still owed, lowered from the day each partial payment came in. Take a $45,000 application due 2 March at 1½% a month, with $15,000 paid on 12 March: by 1 April the interest is $225 for the first ten days on $45,000 plus $300 for the next twenty on $30,000, $525 in all. North Carolina's rule is counted its own way, each started month in full on the highest balance owed in it. The second follow-up email to the GC names the rate, where it comes from and the amount so far; the first reminder leaves it out, since most late payments are a missing waiver, not a dispute.

Interest on a payment that came in late is a different kind of number: it stopped growing the day the check arrived, so it is a fixed sum you either ask for or let go. The cash report lists each application paid after its due date in the last year with the interest it earned and a draft email asking for it. Since 2026-11-28 each one can be marked billed (on the next application or a separate invoice, with a note such as the invoice number) or waived (a release you signed, a clause that rules it out, or a GC you would rather keep), with the day. A marked application leaves the list and the job's next steps, so what remains is only the money nobody has decided about yet; the marked ones sit under "Billed or waived", with an undo, and the application's history and the cash report's CSV keep the decision. PayApps records it; it does not bill anything itself.

Where this goes. PayApps, our hosted pay-app billing for specialty subcontractors, keeps every pay application, payment and retainage balance per job and shows what is owed, when it was due under the job's pay terms and how late it is. It is open and free on one active job, with no card: start free. The paid plans (more jobs and users, lien waivers, QuickBooks and job costing) are not on sale yet.