Most subcontractors sign whatever waiver the GC sends with the pay application. In a handful of states that can be the wrong document. The state has written the waiver in its statute, and in some of them a waiver that does not follow that form does not release anything.
We read eight of those statutes on each legislature's own site on 2026-11-25 and put them side by side in a new free guide, statutory lien waiver forms by state. Every phrase it quotes was checked against the text we fetched.
How strict each state is, in its own words:
| State | Statute | Forms | The rule |
|---|---|---|---|
| Arizona | A.R.S. § 33-1008 | 4 | unenforceable "unless it follows substantially the following forms" |
| Nevada | NRS 108.2457 | 4 | unenforceable "unless it is in the following forms" |
| Texas | Prop. Code § 53.284 | 4 | unenforceable "unless it substantially complies with the applicable form" |
| Utah | § 38-1a-802 | 2 + check endorsement | meets the section "if it is in substantially the form provided" |
| Florida | § 713.20 | 2 | no one "may require" a different form |
| Michigan | MCL 570.1115 | 4 | "shall be used in substantially the following format" |
| Wyoming | W.S. 29-10-101(b) | 1 | "shall be completed in substantially the following form" |
| California | Civ. Code §§ 8132-8138 | 4 | "null, void, and unenforceable unless it is in substantially the following form" |
| Missouri | RSMo § 429.016.27 | 1, residential only | an unconditional final waiver "shall only be valid if it is on a form that is substantially as follows" |
Three things a sub billing in these states should know:
- Texas: no one may require you to sign an unconditional waiver unless you "received payment in that amount in good and sufficient funds" (§ 53.283). If a GC holds this month's check until you sign an unconditional release, the statute is on your side.
- Florida cuts both ways. A GC may not require a waiver different from the statutory forms, but a different waiver you do sign "is enforceable in accordance with the terms". So the statute protects you only if you read the form before you sign it.
- Utah and Nevada void a waiver paid by a bounced check. In Utah, if the check "fails to clear ... for any reason", the waiver is void and your lien and bond rights stand.
- Michigan asks you to say whether you have been paid in full. Its partial waivers say the waiver, "together with all previous waivers, if any, (circle one) does does not cover all amounts due" through the date. Circle "does not" when retainage or an unpaid change order is still out. Once you are paid in full you "shall provide" a full unconditional waiver (MCL 570.1115(2)). On a home, the owner "may not rely upon" a waiver they did not get directly from you without first checking with you that it is authentic.
Wyoming's single form is worth reading twice. It says the owner may rely on it even if a payment in uncertified funds is later dishonored, and then that it "shall not apply" if the owner's payment is dishonored. The guide quotes both sentences and suggests asking a Wyoming lawyer how they apply to a check from the GC.
Missouri is the odd one (added the same day). Its one form is an unconditional final waiver, and it applies only to "residential real property": new homes of four units or fewer, condominiums and townhouses. A remodel of an owner-occupied home falls under § 429.013 instead, and commercial work has no statutory form at all. On a residential job, a waiver given for less than the amount due at the time waives nothing unless it is that statutory form (§ 429.016.25). The form itself binds you "notwithstanding claimant's failure to receive any promised payment" (§ 429.016.29), so sign it only after the money clears. Once paid in full, you owe it within five calendar days of a written request, or you face a $500 penalty (§ 429.016.30).
California, the biggest market, read last (added the same day). Its code site would not load for us, but the Legislative Counsel also publishes the whole of California law as an official bulk download. We read just the ten sections on waivers out of that 1.2 GB file. Two things in the forms catch subs out:
- Signed change orders are waived unless you list them. Every California form waives rights for work done "pursuant to a written change order that has been fully executed by the parties prior to the date that this document is signed by the claimant ... unless listed as an Exception below". An approved change order you have not been paid for belongs in the exceptions.
- The final forms have one exception line, "Disputed claims for extras in the amount of", followed by an amount. Retainage is not on it. Sign the final unconditional form only once everything, retainage included, has been paid.
A conditional waiver releases the owner, lender or bond surety only once there is evidence of payment: your endorsement on a check that has been paid, or your written acknowledgment (Civ. Code § 8124).
What we could not check. Mississippi is often said to have statutory forms, but we could not open its official text, so it is not listed rather than listed from memory. Massachusetts, Georgia and Mississippi were read the next day (updates below).
Where this goes. The pay-app product we are building for specialty subcontractors already prints the Arizona, California, Florida, Michigan, Missouri, Nevada, Texas, Utah and Wyoming waivers word for word from the statute, with a test that rebuilds each form and compares it with the law. On a California job it fills the names, the through date and the check from the pay application. The conditional progress form also excepts earlier progress payments "for which the claimant has previously given a conditional waiver and release but has not received payment", with their dates and amounts. On a job that pays slowly, that list is easy to get wrong by hand. PayApps fills it in for you from the waivers you marked as given on earlier pay applications that are still unpaid: the date each was signed and what is still owed on it today, so a partial check shrinks the amount and a paid application drops off the list. You can still edit both lines before you print. Michigan's forms leave the "does / does not" choice for you to circle by hand. On a Missouri job it offers the residential form as a choice beside the general one, because only the contractor knows whether the property counts as residential. On a Wyoming job it fills the retainage blank from the pay application's retainage held to date, leaves "has not been paid the sum of" for you to enter, and prints the notary acknowledgment blank for the notary. Because Wyoming's one form acknowledges that payment was received, PayApps prints it only as an unconditional waiver and tracks a conditional Wyoming waiver without printing wording the statute does not give. For a Wyoming job it also prints the preliminary notice of right to lien, the "NOTICE TO OWNER" of W.S. 29-10-101(a), with the blank waiver form the notice says is attached. It does not work out your deadline to send it: that is in W.S. 29-2-112, which we have not encoded, so read it or ask counsel. The product is in development with early access, and nothing is for sale yet: construction tools and early access. To check a waiver you were sent for the common traps, the free lien waiver checker runs in your browser.
Update, 2026-11-25: the waiver checker now knows Wyoming and Missouri
The free lien waiver checker gives an info note when you pick a state whose statute sets the waiver wording. Its list predated this guide and left out Wyoming and Missouri, two of the eight states read above. Both are now in it, and the Missouri note says what the statute says: its form covers unconditional final waivers on residential property only (RSMo § 429.016.27). The note's advice points at this guide for the statute itself. The checker also links the guides a reader needs before and after signing (which of the four waivers to sign, this state table, the waiver log, joint checks and short payments), which it did not before. It still does not decide whether a waiver is valid in your state.
Update, 2026-11-25: California's preliminary notice, read from the same download
Before a California sub or supplier can record a lien, give a stop payment notice or claim on a payment bond, it must have given a preliminary notice (Civ. Code § 8200). We read the ten sections on that notice (§§ 8102-8118 and 8200-8216) from the same Legislative Counsel bulk download as the waivers. Unlike Wyoming, California does not print a form. It lists what the notice must say, and gives one statement, "NOTICE TO PROPERTY OWNER", to copy word for word "in boldface type" (§ 8202(a)(3)). What a subcontractor should know:
- Three people get it: the owner or reputed owner, the direct contractor (the GC with the contract with the owner), and the construction lender, if any (§ 8200(a)). A laborer need not give one. A contractor whose contract is with the owner gives it only to the lender (§ 8200(e)).
- Twenty days. "A preliminary notice shall be given not later than 20 days after the claimant has first furnished work on the work of improvement" (§ 8204(a)). A late notice is not worthless: it still covers work "performed within 20 days prior to the service of the preliminary notice, and at any time thereafter". Work done more than 20 days before you served it is not covered.
- What it must contain: the owner's, direct contractor's and lender's names and addresses; a description of the site with its street address; your name, address and relationship to the parties; who you work for; a general description of the work; and an estimate of the total price (§§ 8102(a), 8202(a)). A general description also covers later work outside it (§ 8206(c)).
- One per contract, not one per job, when you work for more than one subcontractor on the same job (§ 8206(b)).
- How to serve it: personal delivery, or registered or certified mail, express mail or overnight delivery (§§ 8106, 8110). Proof is a declaration with the postal or carrier record (§ 8118), so keep the receipt.
- Licensed subs, take note: on a subcontract over $400, failing to give the notice is grounds for discipline under the Contractors' State License Law (§ 8216).
These rules are for private jobs. Public works have their own notice (§ 9300 ff.), which we have not read yet. PayApps, the pay-app product we are building, now prints the California notice from a job's page. Each item sits under the statute's own words, followed by the bold statement. It fills in the owner, the GC and its address, the site, your company and an estimate (the contract sum plus approved change orders), and leaves the "if any" items off when they are blank. Not legal advice.
Update, 2026-11-25: keeping track of the notices you gave
Giving the notice is half the job. If you ever record a lien, you have to prove you gave it. California says how in § 8118: a "proof of notice declaration" that states three things:
- "The type or description of the notice given."
- "The date, place, and manner of notice, and facts showing that notice was given in the manner required by statute."
- "The name and address of the person to which notice was given."
If you mailed it, the declaration must come with the postal or carrier record: the receipt showing you paid for certified, registered or express mail or overnight delivery, or the return receipt or tracking record (§ 8118(b)). So keep the green card or the tracking printout with the job file.
Two dates trip people up:
- When the 20 days start and end. They run from the day you first furnished work on the job, not from the contract date or your first pay application (§ 8204(a)). Write that day down. A notice mailed on day 20 is on time: mailed notice is complete "when deposited in the mail" (§ 8116(b)).
- Leaving it and mailing a copy is slower. If you leave the notice and mail a copy the way a summons is served (Code Civ. Proc. § 415.20), notice is complete "five days after mailing" (§ 8116(c)). Mailed on day 18, it is complete on day 23: late. Certified mail on day 18 would have been on time.
PayApps now keeps this record. On a California job you enter the day you first furnished work and it shows the last day to give the notice (20 calendar days later; it does not move the date for a weekend or holiday, so treat that day as the latest). You record each notice: to whom, how, the day, where, and the tracking number. It tells you whether each one was on time. For a late one, it shows the first day of work the notice still covers. It prints the § 8118 declaration for each, with § 8118(b)'s list of documents to attach. Until the owner and the GC each have a notice recorded, the cash page and the weekly email remind you. One gap: a California declaration is signed "under penalty of perjury" (Code Civ. Proc. § 2015.5). We could not check that section's official text this time, so PayApps does not print the sentence. Add it, or use your attorney's form. Not legal advice.
Added 2026-11-26: the receipt goes with the record. A lien can come months after the notice, and by then the green card is in a truck or a drawer. Each notice you record in PayApps now holds its own files: take a photo of the certified mail receipt at the counter, and add the return receipt or the tracking printout when it comes back, next to the signed declaration. These are the documents § 8118(b) lists. The job's history now also shows when each notice was recorded or deleted, when the first-furnished date was set, and each file added or removed, with who did it. It exports as a CSV for the file you hand your attorney.
Update, 2026-11-26: Massachusetts, where the waiver is your pay application
Massachusetts was on our "could not check" list. Its legislature's site answered this time, so we read Mass. Gen. Laws c. 254, § 32 from the General Court's published text. It works differently from the other states:
- The rule comes before the form. An agreement connected with a construction contract "purporting to bar the filing of a notice of contract or the taking of any steps to enforce a lien", or to subordinate those rights, "is against public policy and is void and unenforceable". The section then lists four exceptions.
- The one form is a partial waiver, for "persons who have filed or recorded notices of contract under section two", and it must be "substantially in the following form with no material deviation therefrom". The statute gives no final or unconditional form.
- Its header is your G702. Lines 1 to 10 are original contract amount, approved change orders, adjusted contract amount, completed to date, less retainage, total payable to date, less previous payments, current amount due, pending change orders and disputed claims. Retyping those numbers by hand is where a mistake gets in.
- What it keeps back: "retainage, unpaid agreed or pending change orders, and disputed claims as stated above". An amount you leave off lines 5, 9 and 10 is not kept back.
- It is more than a waiver. Part (b) also subordinates your lien for work done through "the twenty-fifth day after the end of the above payment period", to the extent the lender actually advances funds by then. And it is "Signed under the penalties of perjury".
PayApps, the pay-app product we are building, now offers this form on a Massachusetts job, next to the general conditional progress waiver. It does not choose between them for you, because it cannot know whether you recorded a notice of contract. It fills lines 1 to 8 from the pay application's own summary, line 9 from your pending change orders, and the application number and date and the job. The payment goes in words and figures. If you change the figures, the words change with them, unless you typed your own. You fill in the county, the town, any disputed claims and the lender. The day, month and year on the perjury line are left blank for you to write when you sign. The free guide, statutory lien waiver forms by state, now has a Massachusetts row and section. Whether a general-form waiver is enforceable on a Massachusetts job is a question for a Massachusetts lawyer. Not legal advice.
Update, 2026-11-26: Georgia, and the 90 days that run whether or not you are paid
Georgia was the other state on our "could not check" list. Its official Code is published only through LexisNexis, which we could not open. The State does publish the laws that wrote the section, so we read those: SB 315, which rewrote all of O.C.G.A. § 44-14-366 from 1 January 2021, and SB 143, which rewrote the affidavit of nonpayment in 2021. A bill shows what it changes by striking old words and underlining new ones, so we kept the underlined words and dropped the struck ones. We read each change against the bill. Check the current Code before relying on it. What a sub should know:
- Two forms, not four. One is a "Waiver and Release of Lien and Payment Bond Rights Upon Interim Payment" and the other is the same "Upon Final Payment". Neither is called conditional or unconditional. Each waives "upon the receipt of the sum of $____". The interim form covers work through a date you fill in and excepts "any retained amounts". The final form has no exception.
- The 90 days. Once signed, the waiver is conclusively effective at the earliest of three things: the money actually arriving, a separate written acknowledgment that you were paid in full, or "ninety days after the date of the execution of the waiver and release". Only one thing stops the clock: filing an affidavit of nonpayment "in the county in which the property is located" before the 90 days are up (§ 44-14-366(g)(2)). The form's own notice says so: you are deemed to have waived "EVEN IF YOU HAVE NOT ACTUALLY RECEIVED SUCH PAYMENT, 90 DAYS AFTER THE DATE STATED ABOVE UNLESS YOU FILE AN AFFIDAVIT OF NONPAYMENT". Before 2021 the period was 60 days, and a claim of lien stopped it too. The 2020 Act struck both. So if you sign a Georgia waiver with the pay application and the check never comes, put the 90th day on your calendar.
- The affidavit has its own statutory form, sworn before a notary. Within seven days of filing it, send a copy to the owner by registered or certified mail or statutory overnight delivery. In some cases a copy also goes to the contractor at the address on the notice of commencement.
- Twelve point, under seal. Both waiver forms must "be in at least 12 point font" and "need not be in boldface capital letters". They are signed under seal, with lines for a witness and an address. A waiver covers only your lien and payment bond rights and "shall not be deemed to affect any other rights or remedies" (§ 44-14-366(a)), which is what the 2020 Act was passed to say.
PayApps, the pay-app product we are building, now prints both Georgia forms word for word. The interim form is offered for a progress waiver and the final form for a final one. It prints every line at 12 point, as the statute requires. From the job and the pay application it fills in the contractor, the project, the owner, the property, the amount and the through date. You fill in the county, the city and what you furnished. Day and month go on by hand when you sign under seal.
Later the same day it gained the clock and the affidavit. When a Georgia waiver is marked sent and the payments recorded on its pay application do not cover it, the waiver list shows the day the 90 days end and how much is still unpaid, and the cash page and the weekly email name it from 30 days before the end. One click opens the affidavit of nonpayment in the statute's wording, filled from the waiver: the county, the contractor, the work, the project, the owner and the property, the waiver's date and amount, and the amount still unpaid. You check it, print it at 12 point and swear it before a notary. It counts 90 calendar days from the day you marked the waiver sent and does not move the date for a weekend or holiday, so do not wait for the last day. Recording that you filed it is next. The free guide, statutory lien waiver forms by state, now has a Georgia row and section. Not legal advice: ask a Georgia lawyer before relying on a waiver.
Update, 2026-11-26: Mississippi, and 60 days instead of 90
Mississippi was the last state on our "could not check" list. Its official Code is published only through LexisNexis, which we could not open. Both sections that matter were created new by one Act, SB 2622 (2014), which the Legislature still publishes as sent to the Governor (approved 11 April 2014). We read that, compared it with the PDF of the same bill, and searched the Legislature's lists of measures for 2015 to 2026 for a later amendment. We found none. Check the current Code before relying on it. What a sub should know:
- Two forms, like Georgia's. One is an "Interim Waiver and Release upon Payment", used for any payment other than the final one (Miss. Code Ann. § 85-7-419(2)). The other is a "Waiver and Release upon Final Payment" (§ 85-7-419(3)). A waiver "shall substantially follow" the right form. A blank filled in wrongly does not invalidate it "if the subject matter of the release reasonably may be determined". The interim form excepts retained amounts. Both are sworn before a notary.
- The 60 days. Once you sign, the amount in the waiver is conclusively "deemed paid in full" at the earliest of three things: the money actually arriving, a separate written acknowledgment of payment in full, or "Sixty (60) days after the date of the execution of the waiver and release". The only way to stop the clock is to file an affidavit of nonpayment in the county where the property is before the 60 days run out, and send the owner a true copy (§ 85-7-419(5)(b)). The form's notice says you are deemed paid "EVEN IF YOU HAVE NOT ACTUALLY RECEIVED THE PAYMENT". That notice also names "A CLAIM OF LIEN" as a way to stop the clock, but the statute's list names only the affidavit, so ask counsel before relying on a claim of lien alone. Georgia also gave 60 days before its 2021 rewrite. Mississippi still does.
- Two days for the owner's copy. The affidavit of nonpayment has its own statutory form (§ 85-7-433(3)). Its last paragraph says "WITHIN TWO (2) DAYS OF FILING THIS AFFIDAVIT OF NONPAYMENT" a copy goes to the owner by registered or certified mail or statutory overnight delivery. Georgia gives seven days. Filing suspends the waiver "until payment in full has been received" (§ 85-7-419(5)(e)). If you are then paid in full, you must sign an affidavit that payment was received if asked, and once it is recorded the affidavit of nonpayment "shall be deemed void" ((5)(c)).
PayApps, the pay-app product we are building, prints both Mississippi waivers word for word. It now tracks the 60 days in the same way it tracks Georgia's 90. When a Mississippi waiver is marked sent and the payments recorded on its pay application do not cover it, the waiver list shows the day the 60 days end. The cash page names it from 30 days before the end. One click prints the affidavit of nonpayment in the statute's wording, filled from the waiver. Once you record it as filed, PayApps counts the two days for the owner's copy, and then marks the waiver as suspended until you are paid. Mississippi's affidavit names no copy to a contractor, so PayApps never asks about one. It counts calendar days from the day you marked the waiver sent and does not move the date for a weekend or holiday, so do not wait for the last day. The free guide, statutory lien waiver forms by state, now has a Mississippi row and section. PayApps is in development, and nothing is for sale yet. Not legal advice: ask a Mississippi lawyer before relying on a waiver.
Update, 2026-11-26: the waivers you collect from your own suppliers
Everything above is about the waiver you give. Many GCs also want waivers from the people you pay: the supply house that delivered the wire, the rental yard, the insulation sub you brought in. These are often called lower-tier waivers. A subcontract or the GC's pay-app checklist may ask for them with each application, and a payment can sit until the last one arrives. Whether yours does, and which kind it wants (conditional for this period, unconditional for money you already paid out), is in your subcontract, not in this post.
The work is not the form. The supplier signs its own state's form, or the GC's. The hard part is the list: who owes you one this month, whether you have asked, and who is still out on the day you want to submit. PayApps, the pay-app product we are building, now keeps that list on each pay application:
- Who to ask comes from the job's purchase orders and subcontracts, one row per vendor. Vendors that have invoiced something to date are ticked, and those with nothing invoiced yet are not, because they may have furnished nothing this period. Last month's list is offered too. You tick who owes one, pick the waiver kind, and add them all through the period end in one go.
- Each waiver is shown as not asked, asked (with the days it has been waiting) or received, with the amount and a note. The pay app says "3 of 5 in; still out: Rio Rentals, Valley Insulation".
- The request is a short email in plain words that you copy or open in your mail app: the job, the GC, the kind of waiver, the through date and the amount. PayApps sends nothing itself.
The signed copies go in the pay app's attachments, so they land in the backup packet next to your own waiver. A later part will attach each file to its row and list the waivers still out across jobs in the weekly email. This is on the Crew plan and up, alongside lien waivers. PayApps itself is open and free on one job; the Crew plan is not on sale yet. Not legal advice.
Later the same day: the signed copy filed on its row
When a supplier sends its signed waiver back, "Attach signed" on that supplier's row now files the PDF or photo there. Three things follow. The row is marked received today, unless you had already typed the date it came in. The file is one of the pay application's attachments, so it goes in the backup packet with the rest of your backup. And the packet's index names it "Lower-tier waiver: ABC Supply" instead of a bare file name, so the GC's reviewer can match each waiver to a supplier without opening it.
Only PDFs and JPEG or PNG photos are accepted on a row, because those are what the packet can merge; a Word file would be left out of it and look like a missing waiver. If you remove a supplier from the list, its file stays on the pay app as ordinary backup rather than disappearing. The list of waivers still out across all your jobs, in the weekly email, is the next part (done the same day: below).
Later still: every waiver still out, across all your jobs
A list per pay application works when you are sitting in that pay application. It does not help on a Monday morning with six jobs open and the question "who am I still waiting on?". So the waivers still out now show in two more places.
- The projects page lists every pay application on an open job that has a supplier's or sub's waiver not yet in. One line each: "Clinic TI (#2207), pay app 4 to Harbor Builders: 3 lower-tier waivers still out (ABC Supply, Ferguson and Valley Rebar), the oldest asked for 12 days ago, 1 not asked for yet." The longest wait comes first, and each line opens that pay application's list, where the request email is drafted.
- The weekly "money to chase" email, for everyone who turned it on, carries the same lines under "Lower-tier waivers still out", each linked to its pay application. A waiver still out is enough on its own to send that week's email, because a GC that wants lower-tier waivers can hold the whole payment for the last one.
"Still out" means only what you entered: no received date and no signed copy attached on its row. PayApps does not decide whether your GC needs a waiver from that supplier; you put the supplier on the list. A waiver drops off the moment you attach the signed copy, and a job you close drops off with all its lists. The sample job never shows up in the email. As before, PayApps sends nothing to your suppliers itself, it is still in development with nothing for sale yet, and this is not legal advice.
And then: the request opens already addressed
The request email was a draft with an empty "To" line, so every month someone dug through their inbox for the supply house's accounts-receivable address. Now each supplier on the list can carry an email address. Type it once, when you add the supplier or later with "Email address" on its row, and "Email" opens the draft addressed to it.
PayApps remembers the address for that supplier across all your jobs. A supply house's AR address is usually the same on every job, so next month's list, or a list on another job, has the address filled in when you add the same supplier. The suggestions show which address each supplier will be added with. Names match the way the list already matches them, so "ABC Supply, Inc." and "abc supply inc" are the same supplier. If you correct an address, the newest one is used from then on. Clearing it on a row stops that row from being addressed. Your company's addresses are never shown to another company.
The draft still opens in your own mail app, and you press send. PayApps sends nothing to your suppliers itself. It is still in development, with nothing for sale yet, and this is not legal advice.
Update, 2026-11-27: every statutory form, blank and ready to print
The guide said which states write the waiver for you, but it never showed you the waiver. Each state now has its own page with every statutory form printed in full, word for word, a blank line wherever the statute leaves one (with a small grey caption under it saying what goes there), and a "Print this form" button that prints that form alone:
Arizona (4 forms), California (4), Florida (2), Georgia (2, printed at the 12 point minimum its statute sets), Massachusetts (1), Michigan (4), Mississippi (2), Missouri (1, residential), Nevada (4), Texas (4), Utah (2) and Wyoming (1).
Each page also says, in a table at the top, which kinds of waiver the state prints no form for. Utah has no unconditional form, Florida and Wyoming no conditional one, Massachusetts no final or unconditional one. A GC's form that fills one of those gaps is not the statute's wording, so read it before you sign it.
How we kept the text honest. The forms are not retyped. The pages are generated from the same encoded statute text that PayApps' waiver printer uses, which has tests comparing every form with the statute as a whole, sentence by sentence. A second test checks that every sentence of every form appears on its state's page, so the page cannot drift from the statute's text as we read it (2026-11-25 for most states, 2026-11-26 for Georgia, Mississippi and Massachusetts). Statutes change, so each form links the official section to check before relying on it.
Update, 2026-11-28: Michigan's notice of furnishing, the notice before the waiver
Michigan's waivers (§ 570.1115) were among the first we encoded. The notice that comes before them was not, and in Michigan the two are tied together. A sub or supplier "shall provide a notice of furnishing to the designee and the general contractor, if any, as named in the notice of commencement ... within 20 days after furnishing the first labor or material" (MCL 570.1109(1)). We read §§ 570.1108, 570.1108a, 570.1109 and 570.1111 on the Michigan Legislature's site on 2026-11-28. Four things stood out:
- A late notice costs you exactly what the owner already paid on paper. Work after the notice stays lienable. Work before it stays lienable "except to the extent that payments were made by or on behalf of the owner or lessee to the contractor pursuant to either a contractor's sworn statement or a waiver of lien" (§ 570.1109(6)). So the owner pays the GC against a sworn statement that lists you, and if the GC doesn't pay you, your lien for that earlier work is gone.
- The 20 days wait for the notice of commencement. If the owner never records one, or doesn't hand it over when you ask in writing by certified mail, the time runs until 20 days after it is recorded or given to you (§ 570.1108(10), (11)). Send the request early and keep the receipt.
- The claim of lien needs the proof of service. Within 90 days after your last furnishing, the claim "shall have attached to it a proof of service of a notice of furnishing" (§ 570.1111(4)). So the certified mail receipt from day 20 is part of the lien you might record months later.
- The statute prints the form, and a notice not on the copy attached to the notice of commencement "must be in substantially the following form" (§ 570.1109(4)), WARNING TO OWNER included.
The free guide, Michigan notice of furnishing, covers who gets it, the timeline, and the form word for word. A test checks every quoted phrase against the text we fetched. PayApps now prints the notice from the job page on the Crew plan and up. The GC is filled in as the other contracting party. The designee is left for you to copy from the notice of commencement, because PayApps doesn't hold that document. It does not count the 20 days or keep a log of the notices you served yet (California and Florida have both).