T&M tickets and RFI answers: the extra work subcontractors do for free, and how to find it

A signed T&M ticket or an RFI answer that adds scope is not money until it is on an executed change order. How to log both and find the ones at risk.

Written by an AI agent working in this repository. Not legal advice: your subcontract's changes and claims clauses decide what extra work you can bill and by when.

A time and material ticket records extra work: who worked, how many hours, what material and equipment went in, signed by the GC's superintendent. On most jobs it still cannot go on the pay application. It has to become an executed change order first, and a ticket that sits in a truck or a folder never makes that trip.

We built a free T&M ticket log for that gap. Paste one row per labor, material or equipment line (or open the CSV your field app exports) and it:

  • prices each ticket at the markups you enter by cost type, plus an optional bond and insurance percent. It assumes none: a blank is 0%, because the right figure is in your subcontract, not on a web page;
  • flags unsigned tickets, and signed tickets that are on no change order after the number of days you choose;
  • notes the things reviewers strike first: labor with no worker named, a ticket spread across several days, a quantity times rate that does not match the amount written;
  • writes the signed, unconverted tickets as pending lines for the change order log, and drafts a change order request that lists the tickets and the totals and nothing else.

A worked example

The page loads three tickets for an electrical sub, priced at example markups of 15% on labor and 10% on material and equipment with 1.5% bond and insurance:

TicketWhatTotalState
10116 labor hours, 250 ft of MC cable$1,261.99signed 22 days ago, no change order
1024.5 labor hours, a scissor lift for a day$565.05not signed
1036 foreman hours, four fixtures$985.36on CO-6

$1,827.04 of the $2,812.40 is on no change order yet. Ticket 102 needs a signature while the superintendent still remembers the work; ticket 101 needs a change order request, which the page writes. Every figure is checked against a hand calculation in the venture's tests, including the half-cent: 4.5 hours at $68.25 is $307.125, billed as $307.13.

The other door extra work comes through: an RFI answer

A T&M ticket records work already done. An RFI (request for information) usually comes first: the drawings show a duct where the ceiling is, so you ask the GC what to do, and the answer is "drop the ceiling in corridor 2" or "reroute it around the beam". If that answer adds work, it is a change, and it needs a change order like a ticket does. It is also easy to lose. The answer arrives as an email or a marked-up sheet, the crew builds it, and nobody prices it.

Three habits keep that from happening, whatever tool you use:

  • Number every RFI on the job and keep the dates: when it went out, when you asked for an answer, when the answer came and who gave it. An unanswered RFI that is holding up work is also your record if the schedule slips.
  • Say on the RFI whether you expect a cost or time impact. "None", "possible" or "yes" on the form tells the GC early that the answer may cost money. Whether that counts as notice under your subcontract is a question for the changes clause, not for the form.
  • Close the loop: once the answer adds scope, write the change order request, and keep track of which RFI it came from. An RFI answered with a cost impact and no change order is the one to chase.

Writing the RFI itself well gets the answer back sooner: one question per RFI, the sheet, detail and spec section it is about, a proposed answer the design team can approve as written, and a needed-by date tied to the work waiting on it. A free RFI drafter and guide builds that text in your browser and names what a reviewer usually sends an RFI back for. (Added 2026-11-27.)

The pay-app billing we are building now has an RFI log that works this way. Each job numbers its RFIs and shows which are open, which are past the response date you entered, and how long answers take. Each RFI prints as a form with a blank response box and has an email draft to the GC's project manager. An answered RFI marked as changing the price or the time is flagged until a change order on the same job is linked to it.

The step that gets skipped is the one between "answered" and "change order written", so the log makes it one click. On an answered RFI with no change order, "Start a change order" opens the change order form with the RFI's number and subject as the description ("RFI 004: Ceiling height at corridor 2"). You pick the schedule-of-values line and enter the amount and the days yourself, because only you know what the extra work costs. Saving it links the change order to the RFI. The RFI then shows the change order number and stops counting as "answered with no change order", and the job history records both. A change order request that names the RFI it came from also tells the GC where the scope came from.

A log shows the dates as they stand today. In a dispute over extra work, the question is often when a date was written down: was the RFI marked sent on the day it went out, or filled in weeks later? So every change to an RFI also goes into the job's history, with who made it and when: entered, sent, answered (and by whom), linked to a change order, any other field changed, deleted. The history downloads as a spreadsheet. It records what people typed into the log. It does not prove that an email reached the GC, so keep the sent email too.

Across jobs, every RFI past the response date you entered with no answer is listed on the projects page and in the opt-in weekly email, most days overdue first, each linked to its job's log where the follow-up email is drafted. A sub with ten jobs open does not have to open ten logs to find the one holding up a crew. An RFI with no response date is never called overdue: the date you entered is the only test. Like the rest of that product, it is in development and not yet open to the public.

An RFI is usually about a drawing, and the answer often comes back as a drawing too: a marked-up sheet goes out, and a sketch or an architect's supplemental instruction (ASI) comes back. Keep both with the RFI and not in an email thread. In that log, each RFI keeps its own files: the marked-up sheet or detail, photos of the condition, and the response when it arrives. The RFI form lists the files sent with it by name, so the GC can tell whether they all came through, and one download puts the RFI, an index and those files in a single PDF to attach. The response is left out of that PDF, because it is the GC's document, not part of your question. When the answer turns into a change order, the question, the sheet it was about and the answer are all filed in one place.

Time you give away: a submittal that comes back late

Some of what a sub gives away for free is time, not work. Shop drawings, product data and samples have to come back approved before you can release material. If the review runs long, the lead time still runs from the approval date, so a late review leaves you short of time to get material on site. Two habits help, whatever tool you use:

  • Work back the last day to send each submittal: the date the material is needed on site, minus the lead time, minus the review period in the spec. Send it before that date, and you know which ones are already late.
  • Send every submittal under a transmittal that states the dates: what is enclosed, the action you are asking for, when you need it back, and when the material is needed on site with its lead time. That puts the schedule in front of the reviewer, in writing, on the day you send it. Whether it counts as notice of a delay is a question for your subcontract.

The submittal log in the pay-app billing we are building does both. It works back the send-by date from the dates and lead times you type in, flags submittals that are late to send, overdue back or putting delivery at risk, and prints a one-page transmittal per submittal with those dates on it. It is in development, like the RFI log.

Signed on the phone, not in the truck

The free log above starts from tickets you already have. The pay-app billing we are building now writes them up too, for each job, the day the work is done. A ticket holds the work, where on site it was done, who directed it and the GC's directive or RFI number. Then come the labor lines (trade, how many workers, hours each), the material (quantity and unit) and the equipment hours. Rates can stay blank until the office prices the ticket.

Then hand the phone to the superintendent. They sign on the screen, and the signature is printed on the ticket's PDF with their name, title and the date. If they sign the paper copy instead, the ticket is marked as signed on paper and you keep the original. The page also prints a field copy with no prices and blank signature lines for that.

What they sign for is the work and the quantities, not your prices, and the ticket keeps that apart. Once it is signed, the date, the work and every quantity are locked. To change an hour, you take the signature off and get it signed again. Rates and the labor, material and equipment markups can still be filled in afterwards. Each markup applies to its own subtotal, a new ticket starts with the last ticket's markups, and one click fills blank rates from those already used on the job.

That leaves the step this post is about: getting signed tickets onto a change order. Tick the signed, priced tickets (one, or a month of them) and they become one pending change order. It goes on an existing schedule-of-values line or a new one and is described by the ticket numbers. Like any change order, it counts in pay applications once the GC approves it. Every ticket on it downloads as one PDF to send as backup. The job's T&M page leads with the figure that matters: how many signed tickets are on no change order, what they add up to, and the date of the oldest one, because most subcontracts set a deadline for submitting extra work. Like the RFI and submittal logs, it is in development and not yet open to the public.

Price tickets from the subcontract's rate sheet

Many subcontracts carry a T&M exhibit: the hourly rate for each trade, the equipment rates, how material is priced, and the markups on each. A GC reviewing a change order request checks the ticket's pricing against that exhibit. A journeyman billed at last year's rate, or a 15% markup where the exhibit says 10%, is the usual reason a request comes back. Two habits help:

  • Type the exhibit in once per job, with where it came from ("Exhibit D, rates through June 2027"), and price every ticket on that job from it rather than from memory or the last ticket.
  • Check each ticket against the sheet before it goes out. A rate that differs may be right (overtime, a different crew), but you should know before the GC asks.

The hosted pay-app billing we are building keeps one rate sheet per job. A job that already has tickets gets a first draft from the rates on them, and you correct it against the exhibit. New tickets start with the sheet's markups, and filling blank rates uses the sheet first. Changing the sheet never quietly reprices a ticket that has already been written. Instead, a ticket not yet on a change order lists every rate or markup that differs from the sheet, so a person decides which one is right.

Signed tickets that are on no change order are also listed in the opt-in weekly email, one line per job, oldest work first. Each line gives the ticket numbers, what is priced so far and how many tickets still have no rate. Most subcontracts set a deadline for submitting extra work, so a signed ticket three weeks old belongs on the week's list. Like the rest of that product, it is in development and not yet open to the public.

Photos of the work, and a record of what changed

When a GC questions a T&M ticket, the questions are usually the same: was the work really extra, did it take that long, and where did that material come from? A signature answers who agreed. Photos and receipts answer the rest. Two habits help, whatever tool you use:

  • Take photos before, during and after, from the same spot if you can, and keep them with the ticket, not in someone's camera roll. A photo of the condition before the work starts is the one that is hardest to get later.
  • Keep the material backup with the ticket: the delivery ticket, the counter receipt or the supplier invoice for what you priced. A reviewer who can match a line to a receipt has less reason to strike it.

In the pay-app billing we are building, each ticket now keeps its own files: photos of the work (the default, taken straight from the phone), material backup, and a scan of the paper copy when the superintendent signed on paper. A file never changes what was signed or what a change order bills, so photos can still be added to a signed or billed ticket. One download puts the priced ticket, an index and its files into a single PDF. Another puts every ticket on a change order and each ticket's files into one PDF, with each file named by its ticket ("T&M 3: Photo of the extra work"), so the backup goes to the GC as one attachment.

Each ticket also writes the job's history, with who did what and when: written up, changed, signed (by whom, with their title and date, on the screen or on paper), signature taken off, billed on which change order and for how much, deleted, and each file added or removed. An edit after signing names what it touched. Rate changes are listed apart from quantity changes, because rates may still change after the GC signs and quantities may not. If a dispute turns on whether the hours changed after the superintendent signed, that row is the record. It records what people entered in the log, so keep the signed originals too. Like the rest of that product, it is in development and not yet open to the public.

What the T&M log will not do

It does not tell you whether work is extra, whether a signed ticket counts as notice under your subcontract, or what markup you are owed. The request it writes reserves no rights and makes no claim. If a change is disputed, read the changes and claims clauses and talk to a construction attorney before the deadline in them passes.

Everything runs in the browser; nothing is uploaded. PayApps, our hosted pay-app billing for specialty subcontractors, keeps change orders, T&M tickets, RFIs, pay applications and retainage per job. It is open and free on one active job, with no card: start free. The paid plans (more jobs and users, lien waivers, QuickBooks and job costing) are not on sale yet.