Bootstrap p-values for the permit-model comparison: the same 10 of 15 cells survive
Bootstrap p-values leave the same ten significant neural-versus-boosted permit-model cells in 2024; the tiny approximate p-values were never literal.
-
Do neural nets really lose to boosting on permit durations? Multiple testing says: only in some years
Across 45 city, target, quantile and year cells, 32 neural-versus-boosted differences look significant; 24 survive Holm correction.
-
Does a neural net beat boosted trees at predicting permit delays? Three years, per permit
A paired bootstrap on 4 million public permits in three cities: the neural-versus-boosted difference is mostly year-specific, with one stable loss.
-
Does a neural net beat boosted trees at predicting permit timing? 45 paired tests, corrected
Bootstrap p-values for neural minus boosted quantile loss on Chicago, San Francisco and Austin permits, 2022 to 2024, with Holm and BH correction.
-
How long does an Austin building permit take? Real numbers from 335,000 permits
Empirical quantiles of Austin permit timing from the city's open data, 2022 to 2024, now in the build-data permit-duration prior file.
-
Neural versus boosted permit-duration models: a tie overall, slightly worse in 2024
On 45 city, quantile and year cells of open permit data, a small neural net ties LightGBM overall but trails it in 2024.
-
Neural vs boosted permit-duration models, per permit: the 2024 gap mostly doesn't repeat in 2023
A per-permit paired bootstrap on open permit data from Chicago, San Francisco and Austin finds the neural-versus-boosted difference is mostly year-specific.
-
Does a permit-duration model keep beating the city average in other years?
A boosted quantile model for how long a building permit takes beat each city's per-type average in 42 of 45 cells over three test years.
-
How long do city permits really take? A published prior from Chicago and San Francisco
Half of Chicago and SF permits are issued the day they are filed; the 90th percentile is 68 and 95 days. Per-type quantiles are now published as data.
-
How long do building permits take? A published prior for Chicago, San Francisco and Austin
Empirical q10/q50/q90 permit durations for three US cities from their open data feeds, 2022 to 2024, with the same-day share and the per-type spread.
-
Does the neural net's permit-duration deficit survive a multiple-testing correction?
Ten of 15 paired comparisons between a small neural net and gradient boosting on permit durations differ; Holm and Benjamini-Hochberg keep all ten.
-
A small neural net or boosted trees for permit-duration quantiles? A per-permit test
On 4.5 million open permit records a small neural net is within 6% of boosted trees on pinball loss, yet worse in 11 of 15 cells in a per-permit paired test.
-
Is a neural net as good as boosted trees at predicting permit times?
Across 45 city, target and quantile cells, a small neural net ties boosted trees on pinball loss overall, but is slightly worse in 2024.
-
A small neural net ties gradient boosting on permit durations, over three years
Over three test years a small neural net ties gradient boosting on permit-duration quantile loss: within 3% in 43 of 45 cells.
-
San Francisco build-time intervals can be narrower, with a catch
A rule that picks tighter 80% intervals for how long San Francisco permits take to complete holds in two of three years, but only one year passes both tests.
-
A narrower prediction interval for Austin build times does not hold up
A backtest rule for tighter 80% intervals on Austin build time (issue to completion) fails on coverage and width, with the yearly numbers.
-
Narrower permit-time intervals help San Francisco and Chicago, not Austin
A rule for choosing tighter 80% intervals on permit approval time works in two cities and mostly fails in Austin, with the numbers.
-
Can a permit-timing interval be both narrow and honest?
A tested rule for choosing a tighter quantile pair for building-permit wait times works in San Francisco and fails in Chicago, on three test years each.
-
Do building-permit time models agree on build time too? XGBoost vs LightGBM vs linear in SF and Austin
On SF and Austin permit data, XGBoost lands within 0.4 points of LightGBM at issue-to-completion quantiles; a linear model trails at the median.
-
Do open permit feeds predict how long a permit takes? Three cities, one honest answer
A boosted model beats each city's own permit averages in 13 of 15 cells; a model from other cities does not, and conformal intervals miss 80%.
-
How many local permits does a new city need before other cities' data helps?
Pooling three US cities' building-permit records with a few rows of a new city rarely beats a simple per-permit-type baseline built from the same few rows.
-
Do permit duration models transfer between cities?
A leave-one-city-out test on Chicago, San Francisco and Austin permit data: the transfer model loses to each city's own baseline in 13 of 15 cells.
-
Most building permits are issued the day you apply
Across 4.5 million permit records from Chicago, San Francisco and Austin, the median application-to-issue lag is 0 days; the 90th percentile is 56 to 142 days.
-
Which permit fields predict how long a permit takes?
Permutation importance on boosted quantile models of permit duration in three US cities: two to four fields carry 80% of the model's reliance.
-
Do boosted models predict permit wait times better than a city's own averages?
On 2024 permits from three US cities, LightGBM quantile models beat per-type empirical quantiles in 13 of 15 cells; Chicago's tails are the exception.
-
Conformal intervals on building-permit delays: where the guarantee goes quiet
Split-conformal intervals on Chicago, SF and Austin permit data hit 80% in 7 of 15 cells; where same-day permits pin the lower end, the correction is zero.
-
How long does a building permit take? Three cities' 2024 data, and why one average misleads
Open permit feeds from Chicago, San Francisco and Austin show very different same-day issue rates in 2024: 30%, 55% and 6%.