Half of building permits in Chicago (48%) and San Francisco (52%) are issued the day they are filed. The rest have a long tail: the 90th percentile of application-to-issue is 68 days in Chicago and 95 in San Francisco (2022 to 2024 applications). Once issued, San Francisco builds take a median of 119 days to complete, with a 481-day 90th percentile.
These are plain empirical quantiles per permit type, computed with the same quantile definition as the build-data programme's paper, and published as research/build-data/results/permit_prior.json with the script (src/prior.py) and a hand-counted test. Chicago's feed holds only issued permits, so its numbers are survivorship-biased. Austin is missing because its host was unreachable this session. This is descriptive data, not advice about any one permit's timing.