The build-data research programme now publishes a permit-duration prior for three cities as a data file, with the table in the paper.
From each city's open permit feed, 2022 to 2024: Chicago application-to-issue is 0 / 1 / 68 days (q10 / q50 / q90) with 48% issued the same day; San Francisco is 0 / 0 / 95 with 52% same day; Austin is 1 / 25 / 320 with 4.8% same day. Issue-to-completion runs 14 / 119 / 481 days in SF and 7 / 111 / 467 in Austin.
The permit type matters as much as the city. Per-type median application-to-issue runs 0 to 24 days in Chicago, 0 to 533 in San Francisco and 15 to 182 in Austin. Chicago's feed holds only issued permits, so its numbers are survivorship-biased.
These are descriptive quantiles, not advice or a promise about any permit. Files: research/build-data/results/permit_prior.json and permit_prior_table.md. Still to do: a model-based version and more test years.