A free pay application template in Excel whose totals cannot drift

The pay application generator now downloads a blank .xlsx template and the worked application as a workbook with live formulas, checked against LibreOffice.

Most subcontractors bill from a spreadsheet. Someone built it years ago, it gets copied for each job, and every month somebody types over a total by hand because a row was inserted below the SUM range. The pay application generator did the arithmetic in the browser, but it only gave you text and a CSV. A CSV has no formulas, so the first edit after downloading it broke the totals again.

What shipped

Two downloads, both free:

  • A blank template (.xlsx). An Application sheet with the nine summary lines (original contract sum, net change orders, contract sum to date, completed and stored, retainage, earned less retainage, previous certificates, payment due, balance to finish) linked to a lettered Continuation sheet of 30 lines. Retainage on work and on stored materials are two input cells; a line can carry its own rate. Type CO in the type column and the line moves from the original sum to the change orders.
  • The worked application as a workbook. After you work out an application on the page, the same layout comes back filled in, with ten spare rows that every total already covers, so a line added next week is counted without touching a formula.

The layout and wording are the tool's own. It is not the AIA G702/G703 form, which is copyrighted, and the page says so next to the button.

How it was checked

The file is written by about 200 lines of dependency-free JavaScript: a stored zip writer and the SpreadsheetML by hand. Each formula also carries a cached value computed by the page's own arithmetic, because a phone's file preview does not recalculate, and a blank cell where the payment due should be is worse than no file at all. The workbook then asks Excel and LibreOffice to recalculate on open.

So the question is whether the formulas and the page agree. We built the sample application with the awkward cases switched on: retainage reduced from 10% to 5% once the job passed 20% complete (on work only; stored materials keep 10%), a line with its own 7.5% rate and a third of a cent at stake in the rounding, and a deductive change order. LibreOffice recalculated the file headless and exported it as CSV. Every summary line matched the page to the cent: payment due $87,993.33, retainage $14,190.00. The blank template recalculates to zeros, and the tests in workbook.test.mjs check the zip's CRCs, the formulas' targets and the cached values on every run.

Later the same day: the check became a test

That LibreOffice run happened once, by hand, and it had a gap: the file it opened still carried the cached values. A spreadsheet app that trusts the cache shows the right numbers whatever the formulas say, so a matching export did not prove the formulas were right.

recalc.test.mjs now does it properly on every local run. It deletes every cached value from the workbook, so LibreOffice has to work each formula out from scratch, exports the raw values (not the values as displayed, which the cell format rounds to the cent and would hide a formula that is off by a fraction of one), and compares lines 1 to 9 and each line's completed total and retainage with the page's arithmetic. It runs three applications: the page's worked example (payment due $84,870.00), a job past a retainage reduction point where work drops to 2.5% while stored materials stay at 5%, and a line with its own 7.5% rate and odd cents.

Before trusting it, we broke the workbook three ways and checked the test noticed: stored materials charged at the work rate, retainage rounded to a tenth of a cent instead of a cent, and the change-order filter misspelt. The first draft of the test caught none of the first two. Every case had the same rate for work and stored materials, and the export rounded the evidence away. Both holes are closed, and all three breaks now fail. The test skips on machines without LibreOffice, which includes most CI runners, so it is a check to run after touching the workbook code, not a gate.

2026-11-26: a cent on deductive change orders

A red-team pass on the workbook code found one case the three applications missed: half a cent of retainage on a negative amount. Ten percent of a $1,234.55 deductive change order is $123.455. The page used JavaScript's Math.round, which rounds halves up, toward positive, so it credited back $123.45 while the same amount billed held $123.46. The workbook's ROUND formulas, like Excel's and LibreOffice's, round halves away from zero and gave $123.46 both ways. On a job with that change order, the page and the downloaded file disagreed on retainage, and on payment due, by one cent.

The page now rounds the way the spreadsheet does, so a deduction is the mirror image of the same amount billed. A fourth application in recalc.test.mjs covers it, and because that test skips where LibreOffice is not installed, calc.test.mjs gained one that runs everywhere: 300 seeded amounts ending in five cents at 10%, 5%, 2.5% and random rates, each checked that negating the line negates its retainage. Both fail on the old rounding.

The template also has its own page now, free pay application template for Excel, with what each lettered column's formula does and how to roll it to next month. If you are still drawing up the schedule of values itself, the pay app guides have a schedule of values template for that step, and the template page links to it.

One safety detail: everything a user typed goes in as an inline string, never as a formula, so a description that starts with = stays text.

Checking the numbers from a phone

Updated 2026-11-26. Plenty of pay apps get a last look on a phone in the truck before they go out, and the results were hard to read there. At 390 px wide the line-by-line table was 1,004 px across, so you saw Item, Description and Scheduled and had to scroll sideways for everything else. The summary was padded text for pasting into an email, and on a narrow screen each amount wrapped onto the line below its label.

Now, under 600 px, each schedule line is a card: "4 Electrical rough-in" on top, then Scheduled, Previous, This period, Stored, Completed, Percent complete, Balance to finish and Retainage, two to a row with the name above each amount, so the four you check first (Scheduled, Previous, This period, Stored) fit in the top half of the card. A card is 238 px tall on a 390 px phone, down from 310 px when each amount had its own row, and the ten-line example's table went from 3,230 px to 2,511. The summary shows as nine label-and-amount rows ("8. CURRENT PAYMENT DUE (6 - 7) ... $84,870.00" on the worked example). The text you download or print is the same padded text as before; only the on-screen view changed. Input boxes are 16 px on a phone, so iPhone Safari no longer zooms the page when you tap one.

Updated 2026-11-27. Once a schedule is pasted, the page works it out as you edit, with no button press. A dark strip pinned to the bottom of the form shows the payment due, the retainage held and how many findings there are, so you can change the retainage rate at the top of the form and watch the answer move without scrolling down to the result. On the worked example's schedule at the default 10%, the strip reads $84,870.00 due and $24,530.00 held; at 5% it reads $89,585.00 and $12,265.00. A paste the page cannot read puts the reason in the strip and hides the old result, so a stale figure is never on screen. A chosen Excel file still waits for the button, and the live preview counts no usage.

Also updated 2026-11-27, for anyone billing from a phone. The paste box no longer scrolls sideways inside itself on a narrow screen: at 390 px it used to show 322 px of a 542 px line, so you saw the middle of each row; it now wraps, and a note under it says how many lines it holds (11 for the worked example). Both the generator and the template guide now follow the phone's dark setting, from one set of colour tokens; a printed application stays dark ink on white either way. An automated accessibility check (axe, WCAG A and AA) passes on the filled-in result in both colour schemes, at phone and desktop widths.

Why a spreadsheet, for a product we mean to sell

The paid product is PayApps, a hosted pay-app suite: schedules saved per job and carried forward for you, retainage tracked until release, lien waivers checked against the payment. A sub with one job and a good spreadsheet doesn't need it. A sub with eight jobs and eight copies of that spreadsheet does, and they find us by searching for a template first. So the template is free and good.

Update, 2026-11-27: PayApps is open, and takes this workbook

PayApps opened on its Free plan: one active job, no card (start free). If you already bill from this template or the generator's Excel download, you don't retype anything. When you set up the job, choose the workbook: the schedule of values is read from the Continuation sheet (subtotal, total and change-order rows left out of the contract lines and listed, the sheet's own totals checked against its lines), and the work billed to date can be filled in as the job's opening balance, so the first application in PayApps carries on from your last one. The workbook is read in your browser; PayApps' own tests run on files this generator wrote and LibreOffice saved.

Free covers pay applications with retainage and change orders, as PDF and CSV. Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet. The template and the generator stay free.

Source: ventures/pay-application-generator/workbook.mjs. The numbers are arithmetic on what you enter; your contract decides the retainage terms. Not legal, tax or accounting advice.

Update, 2026-11-27: an invoice template for the jobs with no pay application

Not every job gets a pay application. Service calls, small commercial work, residential remodels and time-and-materials work are billed by invoice, and the free invoice templates people find first rarely have a retainage line. The construction invoice template is a one-sheet .xlsx built by the same code as this workbook (the same zip writer and cell styles, in ventures/pay-app-guides/invoice-template.mjs). It has lump-sum and unit-price lines, signed change orders on their own lines, retainage at your contract's rate as a negative line, a deposit applied, the amount due, and a due date worked out from the invoice date and your payment terms. A second figure keeps the retainage held on the job to date, so the closing retainage bill is not a hunt through old invoices.

Sales tax is a cell you type in. Whether construction labor or materials are taxed depends on the state and the kind of contract, and a template that guessed a rate would be wrong for most of its readers.

The check is the same as here: a test recalculates the filled-in example (a drywall sub's first invoice, $21,120.00 of work, $2,112.00 retainage and a $3,000.00 deposit off, $16,008.00 due) in LibreOffice and compares it with the page. The page also says when a GC will want a pay application instead, and how to move invoice lines onto a schedule of values when that happens.